5407 S WESTERN AVE 1-60 90062

Certificate Information: 5407 S WESTERN AVE 1-60 90062

Application / Permit
21010-10000-03332
Plan Check / Job No.
B21LA12532
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
NEW 4 STORY 60 UNITS (100% AFFORDABLE, 59 AFFORDABLE + 1 MANAGER'S UNIT) AFFORDABLE HOUSING APARTMENT TO INCLUDE 3 STORY TYPE IIIA APARTMENT OVER 1 STORY TYPE IA PARKING/LOBBY/AMENITY PER QPSH (14.00.A.13) (QPSH) Project per LAMC 14.00.A.13.
Permit Issued
Issued on 5/8/2024
Issuing Office
Metro
Current Status
Issued on 5/8/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/15/2021 APPLICANT
Assigned to Plan Check Engineer 7/22/2021 VU NGUYEN
Corrections Issued 7/29/2021 VU NGUYEN
Quality Review Completed 8/3/2021 EUGENE BARBEAU
Plan Check Approved 5/8/2024 MANUEL MONTUFAR
Issued 5/8/2024 APPLICANT
TCO Issued (Expire Date: 04-05-2026) 10/7/2025 ERNESTO CORRAL
TCO Issued (Expire Date: 09-28-2026) 4/1/2026 RAFAEL ESPINOZA

Permit Application Clearance Information

Address approval Cleared 12/6/2023 WALLIE JONG
Community Plan Implem. Overlay Cleared 12/6/2023 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 12/7/2023 WALLIE JONG
Sewer availability Cleared 12/11/2023 WALLIE JONG
Bicycle Parking Cleared 1/8/2024 KATHERINE MENDOZA
Historic Resource Verification Cleared 1/10/2024 RAFAEL FONTES
Miscellaneous Cleared 1/10/2024 DANIEL CORONADO
Miscellaneous Cleared 1/10/2024 DANIEL CORONADO
Miscellaneous Cleared 1/10/2024 DANIEL CORONADO
Miscellaneous Cleared 1/10/2024 DANIEL CORONADO
Building over 36-ft Cleared 1/17/2024 CALOSHA APPROVED
Redevelopment Project Area Cleared 1/30/2024 ELIZABETH GALLARDO
Permit Cleared 2/2/2024 CELINA MORENO
Highway dedication Cleared 2/6/2024 WALLIE JONG
Community Plan Implem. Overlay Cleared 2/8/2024 ADALBERTO VERA
Community Plan Implem. Overlay Cleared 2/13/2024 RIDWAN HARDY
DAS Clearance Cleared 2/21/2024 VU NGUYEN
Hydrant and Access approval Cleared 3/15/2024 LAVEON RIDER
Miscellaneous Cleared 4/3/2024 HAMZA KHAN
Frnt yard landscape/Water mgmt Cleared 4/5/2024 FIPE LEILUA
Opn space landscape/Water mgmt Cleared 4/5/2024 FIPE LEILUA
Community Plan Implem. Overlay Cleared 4/9/2024 TAIMOUR TANAVOLI
Driveway location Cleared 4/9/2024 TAIMOUR TANAVOLI
Green Code Cleared 4/17/2024 VU NGUYEN
Fire Marshal Fire Life Safety Cleared 4/22/2024 MENOA AGHAJANI
Community Plan Implem. Overlay Cleared 4/30/2024 MANERI ROMAN
Low Impact Development (LID) Cleared 5/1/2024 SARAH YOUSSEF
Public Housing Cleared 5/1/2024 GLEN OLIVER
Roof/Waste drainage to street Cleared 5/2/2024 WALLIE JONG
Trees in Parkway Cleared 5/2/2024 DYNL MIRANDA
Density Bonus Cleared 5/7/2024 LOUIE MILLER

Contact Information

Architect Flores,, Raeven I; Lic. No.: C32188 234 SOUTH CIRCLE DRIVE      SAN GABRIEL, CA 91776
Contractor Benchmark Contractors Inc; Lic. No.: 462263-B 3330 OCEAN PARK BLVD      SANTA MONICA, CA 90405
Engineer Berliner,, Neal David; Lic. No.: GE2576 4913 MONUMENT ST      SIMI VALLEY, CA 93063
Engineer Ekwueme,, Chukwuma Ganiru; Lic. No.: S4416 707 WILSHIRE BLVD STE 4450      LOS ANGELES, CA 90017
Engineer Khoury,, Samir; Lic. No.: C30567 5049 E LOMITA AVE      ORANGE, CA 92869
Landscape Architect Chee,, Tina Mae Lan; Lic. No.: LA6159 2435 KENILWORTH AVE      LOS ANGELES, CA 90039

Inspector Information

ALFREDO LOPEZ, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI
JAMES POWERS, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/31/2024 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/15/2024 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 7/15/2024 Partial Approval JAMES POWERS
Footing/Foundation/Slab 7/15/2024 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/16/2024 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/17/2024 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 7/17/2024 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 7/18/2024 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 7/19/2024 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/23/2024 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 7/24/2024 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/26/2024 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/29/2024 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 7/29/2024 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/30/2024 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 7/31/2024 Partial Approval DANIEL VARNUM
Deputy Reinf. Concrete 8/1/2024 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/5/2024 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/7/2024 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 8/7/2024 Partial Approval JAMES POWERS
Masonry Wall/Backfill 8/8/2024 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/9/2024 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 8/13/2024 Partial Approval DANIEL VARNUM
Footing/Foundation/Slab 8/13/2024 Partial Approval DANIEL VARNUM
Excavation/Setback/Form/Re-Bar 8/14/2024 Partial Inspection LARRY ARNICK
Excavation/Setback/Form/Re-Bar 8/19/2024 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/20/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 8/22/2024 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/23/2024 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/28/2024 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/29/2024 Partial Approval JAMES POWERS
Footing/Foundation/Slab 8/29/2024 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/3/2024 Partial Approval JAMES POWERS
Reinforced Concrete Frame 9/3/2024 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/4/2024 Partial Approval JAMES POWERS
Green Building Rough 9/4/2024 Not Ready for Inspection JAMES POWERS
Piling/Pier/Caisson 9/4/2024 Partial Approval JAMES POWERS
Reinforced Concrete Frame 9/4/2024 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 9/4/2024 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 9/6/2024 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/9/2024 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 9/9/2024 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/10/2024 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 9/10/2024 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/11/2024 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 9/11/2024 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/12/2024 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 9/12/2024 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/13/2024 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 9/13/2024 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 9/16/2024 Partial Approval JAMES POWERS
Reinforced Masonry Frame 9/16/2024 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 9/17/2024 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 9/18/2024 Partial Approval JAMES POWERS
Reinforced Masonry Frame 9/18/2024 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Masonry 9/19/2024 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 9/20/2024 Partial Approval JAMES POWERS
Reinforced Masonry Frame 9/20/2024 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Masonry 9/23/2024 Partial Approval JAMES POWERS
Reinforced Masonry Frame 9/23/2024 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 9/24/2024 Partial Approval JAMES POWERS
Masonry Wall/Backfill 9/26/2024 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 10/9/2024 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/15/2024 Conditional Approval DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 10/15/2024 Partial Inspection DAVID BURKHEAD
Footing/Foundation/Slab 10/15/2024 Partial Inspection DAVID BURKHEAD
Deputy Reinf. Concrete 10/16/2024 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/17/2024 Partial Approval JAMES POWERS
Green Building Rough 10/17/2024 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 10/17/2024 Not Ready for Inspection JAMES POWERS
Verify Sprinkler Sign Off 10/17/2024 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 10/18/2024 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/21/2024 Partial Approval JAMES POWERS
Footing/Foundation/Slab 10/21/2024 Partial Approval JAMES POWERS
Reinforced Concrete Frame 10/21/2024 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/22/2024 Partial Approval JAMES POWERS
Wood Frame 10/29/2024 Not Ready for Inspection JAMES POWERS
Wood Frame 11/6/2024 Not Ready for Inspection JAMES POWERS
Deputy Wood Construction 11/7/2024 Partial Approval JAMES POWERS
Wood Frame 11/7/2024 Partial Approval JAMES POWERS
Drywall Nailing 11/19/2024 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 11/19/2024 Not Ready for Inspection JAMES POWERS
Wood Frame 11/19/2024 Not Ready for Inspection JAMES POWERS
Deputy Drilled-In Anchors 11/20/2024 Partial Approval JAMES POWERS
Drywall Nailing 11/21/2024 Partial Approval JAMES POWERS
Drywall Nailing 11/22/2024 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 11/22/2024 Partial Approval JAMES POWERS
Wood Frame 11/22/2024 Not Ready for Inspection JAMES POWERS
Deputy Wood Construction 11/25/2024 Conditional Approval LARRY ARNICK
Drywall Nailing 11/25/2024 Not Ready for Inspection LARRY ARNICK
Wood Frame 11/25/2024 Not Ready for Inspection LARRY ARNICK
Deputy Wood Construction 11/27/2024 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 11/27/2024 Not Ready for Inspection JAMES POWERS
Wood Frame 11/27/2024 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 12/2/2024 Partial Approval JAMES POWERS
Drywall Nailing 12/2/2024 Partial Approval JAMES POWERS
Wood Frame 12/2/2024 Not Ready for Inspection JAMES POWERS
Deputy Wood Construction 12/4/2024 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 12/6/2024 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 12/6/2024 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 12/9/2024 Not Ready for Inspection LARRY ARNICK
Insulation 12/9/2024 Not Ready for Inspection LARRY ARNICK
Wood Frame 12/9/2024 Not Ready for Inspection LARRY ARNICK
Insulation 12/11/2024 Partial Approval JAMES POWERS
Drywall Nailing 12/12/2024 Not Ready for Inspection JAMES POWERS
Insulation 12/12/2024 Not Ready for Inspection JAMES POWERS
Deputy Wood Construction 12/18/2024 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 12/18/2024 Partial Approval JAMES POWERS
Wood Frame 12/18/2024 Not Ready for Inspection JAMES POWERS
Deputy Wood Construction 12/19/2024 Partial Approval JAMES POWERS
Drywall Nailing 12/19/2024 Not Ready for Inspection JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 12/19/2024 Partial Approval JAMES POWERS
Drywall Nailing 12/26/2024 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 12/26/2024 Partial Approval JAMES POWERS
Deputy Wood Construction 12/27/2024 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 12/27/2024 Partial Approval JAMES POWERS
Wood Frame 12/27/2024 Partial Approval JAMES POWERS
Drywall Nailing 12/30/2024 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 12/30/2024 Not Ready for Inspection JAMES POWERS
Deputy Wood Construction 1/3/2025 Partial Approval JAMES POWERS
Drywall Nailing 1/3/2025 Partial Approval JAMES POWERS
Drywall Nailing 1/6/2025 Not Ready for Inspection JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 1/6/2025 Not Ready for Inspection JAMES POWERS
Insulation 1/6/2025 Not Ready for Inspection JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 1/7/2025 Partial Approval JAMES POWERS
Insulation 1/7/2025 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 1/10/2025 Not Ready for Inspection JAMES POWERS
Deputy Wood Construction 1/13/2025 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 1/14/2025 Partial Approval JAMES POWERS
Insulation 1/14/2025 Partial Approval JAMES POWERS
Drywall Nailing 1/15/2025 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 1/15/2025 Partial Approval JAMES POWERS
Drywall Nailing 1/16/2025 Not Ready for Inspection JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 1/16/2025 Not Ready for Inspection JAMES POWERS
Drywall Nailing 1/21/2025 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 1/21/2025 Partial Approval JAMES POWERS
Interior/Exterior Lathing 1/21/2025 Not Ready for Inspection JAMES POWERS
Interior/Exterior Lathing 1/22/2025 Partial Approval JAMES POWERS
Deputy Wood Construction 1/23/2025 Partial Approval JAMES POWERS
Drywall Nailing 1/24/2025 Not Ready for Inspection JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 1/24/2025 Partial Approval JAMES POWERS
Insulation 1/24/2025 Not Ready for Inspection JAMES POWERS
Drywall Nailing 1/28/2025 Partial Approval JAMES POWERS
Insulation 1/28/2025 Partial Approval JAMES POWERS
Drywall Nailing 1/29/2025 Partial Approval JAMES POWERS
Insulation 1/29/2025 Partial Approval JAMES POWERS
Drywall Nailing 1/30/2025 Not Ready for Inspection JAMES POWERS
Insulation 1/30/2025 Not Ready for Inspection JAMES POWERS
Drywall Nailing 2/3/2025 Partial Approval LARRY ARNICK
Insulation 2/3/2025 Partial Approval LARRY ARNICK
Interior/Exterior Lathing 2/3/2025 Partial Approval LARRY ARNICK
Drywall Nailing 2/4/2025 Partial Approval JAMES POWERS
Insulation 2/4/2025 Partial Approval JAMES POWERS
Drywall Nailing 2/7/2025 Partial Approval JAMES POWERS
Insulation 2/7/2025 Partial Approval JAMES POWERS
Drywall Nailing 2/11/2025 Partial Approval JAMES POWERS
Insulation 2/11/2025 Partial Approval JAMES POWERS
Drywall Nailing 2/13/2025 Partial Approval JAMES POWERS
Drywall Nailing 2/20/2025 Conditional Approval DARRYL ARNOLD
Light Gage Steel Frame 2/20/2025 Approved DARRYL ARNOLD
Drywall Nailing 2/24/2025 Partial Approval LARRY ARNICK
Insulation 2/24/2025 Partial Approval LARRY ARNICK
Drywall Nailing 2/25/2025 Not Ready for Inspection LARRY ARNICK
Insulation 2/25/2025 Partial Approval LARRY ARNICK
Insulation 2/28/2025 Partial Approval JAMES POWERS
Drywall Nailing 3/3/2025 Not Ready for Inspection JAMES POWERS
Insulation 3/3/2025 Not Ready for Inspection JAMES POWERS
Drywall Nailing 3/5/2025 Partial Approval JAMES POWERS
Insulation 3/5/2025 Not Ready for Inspection JAMES POWERS
Drywall Nailing 3/7/2025 Not Ready for Inspection JAMES POWERS
Insulation 3/7/2025 Not Ready for Inspection JAMES POWERS
Drywall Nailing 3/11/2025 Partial Approval JAMES POWERS
Insulation 3/11/2025 Partial Approval JAMES POWERS
Light Gage Steel Frame 3/11/2025 Partial Approval JAMES POWERS
Drywall Nailing 3/13/2025 Partial Approval JAMES POWERS
Insulation 3/18/2025 Not Ready for Inspection JAMES POWERS
Insulation 3/19/2025 Partial Approval JAMES POWERS
Drywall Nailing 3/20/2025 Partial Approval JAMES POWERS
Drywall Nailing 3/26/2025 Partial Approval JAMES POWERS
Insulation 3/26/2025 Partial Approval JAMES POWERS
Drywall Nailing 3/27/2025 Not Ready for Inspection JAMES POWERS
Insulation 3/27/2025 Partial Approval JAMES POWERS
Drywall Nailing 4/1/2025 Partial Approval JAMES POWERS
Insulation 4/1/2025 Not Ready for Inspection JAMES POWERS
Drywall Nailing 4/2/2025 Not Ready for Inspection JAMES POWERS
Insulation 4/8/2025 Partial Approval JAMES POWERS
Light Gage Steel Frame 4/8/2025 Partial Approval JAMES POWERS
Drywall Nailing 4/17/2025 Partial Approval JAMES POWERS
Drywall Nailing 4/18/2025 Not Ready for Inspection JAMES POWERS
Footing/Foundation/Slab 4/18/2025 Not Ready for Inspection JAMES POWERS
Light Gage Steel Frame 4/18/2025 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 4/22/2025 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 4/23/2025 Conditional Approval LARRY ARNICK
Footing/Foundation/Slab 4/23/2025 Not Ready for Inspection LARRY ARNICK
Light Gage Steel Frame 5/2/2025 Not Ready for Inspection LARRY ARNICK
Drywall Nailing 5/7/2025 Partial Approval JAMES POWERS
Drywall Nailing 5/21/2025 Partial Approval JAMES POWERS
Drywall Nailing 5/29/2025 Partial Approval JAMES POWERS
Light Gage Steel Frame 5/29/2025 Partial Approval JAMES POWERS
Insulation 6/6/2025 Not Ready for Inspection JAMES POWERS
Insulation 6/9/2025 Partial Approval JAMES POWERS
Insulation 6/10/2025 Partial Approval JAMES POWERS
Drywall Nailing 6/11/2025 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 6/13/2025 Partial Approval JAMES POWERS
Drywall Nailing 6/13/2025 Not Ready for Inspection JAMES POWERS
Light Gage Steel Frame 6/13/2025 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Masonry 6/17/2025 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 6/18/2025 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 6/20/2025 Partial Approval JAMES POWERS
Drywall Nailing 6/20/2025 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Masonry 6/23/2025 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 6/24/2025 Partial Approval JAMES POWERS
Footing/Foundation/Slab 6/30/2025 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/2/2025 Partial Approval JAMES POWERS
Light Gage Steel Frame 7/10/2025 Not Ready for Inspection JAMES POWERS
Drywall Nailing 7/11/2025 Not Ready for Inspection JAMES POWERS
Final 7/15/2025 Not Ready for Inspection JAMES POWERS
Footing/Foundation/Slab 7/15/2025 Approved JAMES POWERS
Green Building Final 7/15/2025 Approved JAMES POWERS
Green Building Rough 7/15/2025 Approved JAMES POWERS
Reinforced Concrete Frame 7/15/2025 Approved JAMES POWERS
Reinforced Masonry Frame 7/15/2025 Approved JAMES POWERS
SGSOV-Seismic Gas S/O Valve 7/15/2025 SGSOV No Gas JAMES POWERS
Smoke Detectors 7/15/2025 Approved JAMES POWERS
Verify Sprinkler Sign Off 7/15/2025 Approved JAMES POWERS
Deputy Reinf. Concrete 7/22/2025 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/23/2025 Partial Approval JAMES POWERS
Drywall Nailing 8/8/2025 Partial Approval JAMES POWERS
Interior/Exterior Lathing 8/8/2025 Partial Approval JAMES POWERS
Final 9/5/2025 Not Ready for Inspection JAMES POWERS
Final 9/15/2025 Not Ready for Inspection JAMES POWERS
Final 9/22/2025 OK for TCO JAMES POWERS
Verify Rec and Parks Fee Memo 9/22/2025 Not Ready for Inspection JAMES POWERS
Final 10/3/2025 OK for TCO JAMES POWERS
Final 10/17/2025 Not Ready for Inspection JAMES POWERS
Light Gage Steel Frame 11/10/2025 Approved JAMES POWERS
Special/Order Compliance 3/10/2026 Approved JAMES POWERS