1643 W 223RD ST 90501
Certificate Information: 1643 W 223RD ST 90501
- Application / Permit
- 21010-10000-03323
- Plan Check / Job No.
- B21LA12502
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePLAN. CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A)
- Permit Issued
- Issued on 8/17/2021
- Issuing Office
- Current Status
- CofO Issued on 1/3/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/2/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/7/2021 | KEVIN MORALES |
| Corrections Issued | 7/7/2021 | KEVIN MORALES |
| Applicant returned to address corrections | 7/15/2021 | CARLOS MONTES |
| Plan Check Approved | 7/21/2021 | KEVIN MORALES |
| Issued | 8/17/2021 | APPLICANT |
| CofO in Progress | 12/21/2021 | RICHARD STEINBACH |
| Permit Finaled | 1/3/2022 | DEROLD HAUFF |
| CofO Issued | 1/3/2022 | DEROLD HAUFF |
| Permit Finaled | 1/3/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 7/13/2021 | ERIK BEASLEY |
| Eng Process Fee Ord 176,300 | Cleared | 7/13/2021 | ERIK BEASLEY |
| Sewer availability | Cleared | 7/13/2021 | ERIK BEASLEY |
Contact Information
| Contractor | Sarrafian Payam; Lic. No.: 1019603-B | 1200 S SHENANDOAH STREET APT 205 LOS ANGELES, CA 90035 |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 9/7/2021 | Partial Approval | ANSON MAGLASANG |
| Footing/Foundation/Slab | 9/14/2021 | Corrections Issued | CRAIG DAVIS |
| Footing/Foundation/Slab | 9/17/2021 | Approved | ANSON MAGLASANG |
| Wood Frame | 10/1/2021 | Corrections Issued | JOHN KLARIN |
| ELECTRICAL-Rough | 10/27/2021 | Approved | JOHN KLARIN |
| PLUMBING-Rough | 10/27/2021 | Approved | JOHN KLARIN |
| Wood Frame | 10/27/2021 | Partial Approval | JOHN KLARIN |
| Insulation | 11/2/2021 | Corrections Issued | ANSON MAGLASANG |
| Interior/Exterior Lathing | 11/2/2021 | Corrections Issued | ANSON MAGLASANG |
| Insulation | 11/4/2021 | Approved | JOHN KLARIN |
| Interior/Exterior Lathing | 11/4/2021 | Approved | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 11/9/2021 | Approved | JOHN KLARIN |
| Drywall Nailing | 11/12/2021 | Approved | JOHN KLARIN |
| Green Building Rough | 11/12/2021 | Approved | JOHN KLARIN |
| Interior/Exterior Lathing | 11/12/2021 | Approved | JOHN KLARIN |
| BUILDING-Rough-Frame | 12/10/2021 | Approved | JOHN KLARIN |
| Final | 12/10/2021 | Corrections Issued | JOHN KLARIN |
| Green Building Final | 12/10/2021 | Corrections Issued | JOHN KLARIN |
| METHANE-Final | 12/10/2021 | Approved | JOHN KLARIN |
| METHANE-Rough | 12/10/2021 | Approved | JOHN KLARIN |
| SGSOV-Seismic Gas S/O Valve | 12/10/2021 | SGSOV Approved | JOHN KLARIN |
| Smoke Detectors | 12/10/2021 | Approved | JOHN KLARIN |
| ELECTRICAL-Final | 12/21/2021 | Approved | RICHARD STEINBACH |
| Final | 12/21/2021 | OK to Issue CofO | RICHARD STEINBACH |
| Green Building Final | 12/21/2021 | Approved | RICHARD STEINBACH |
| HVAC-Final | 12/21/2021 | Approved | RICHARD STEINBACH |
| PLUMBING-Final | 12/21/2021 | Approved | RICHARD STEINBACH |