1122-1122 1/2 E 27TH ST 90011
Certificate Information: 1122-1122 1/2 E 27TH ST 90011
- Application / Permit
- 21010-10000-03303
- Plan Check / Job No.
- B21LA12436
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New construction of two detached Accessory Dwelling Units per CA Govt. Code 65852.2(e)(1)(C) in one building. All work per engineered design.
- Permit Issued
- Issued on 12/9/2021
- Issuing Office
- Current Status
- CofO Issued on 10/4/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/1/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/9/2021 | SAMUEL GONZALEZ |
| Corrections Issued | 7/10/2021 | SAMUEL GONZALEZ |
| Building Plans Picked Up | 7/15/2021 | APPLICANT |
| Applicant returned to address corrections | 12/7/2021 | ADRIANA LOPEZ |
| Issued | 12/9/2021 | APPLICANT |
| CofO in Progress | 9/25/2023 | BRENDAN MORELLI |
| CofO Issued | 10/4/2023 | DEROLD HAUFF |
| Permit Finaled | 10/4/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 7/19/2021 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 7/19/2021 | JEANIE LAM |
| Sewer availability | Cleared | 7/19/2021 | JEANIE LAM |
| Hydrant and Access approval | Cleared | 9/13/2021 | GILBERT URREA |
| Construction near power lines | Cleared | 10/13/2021 | RIDWAN HARDY |
| Low Impact Development | Cleared | 12/1/2021 | MARCO SANCHEZ |
| Roof/Waste drainage to street | Cleared | 12/2/2021 | JEANIE LAM |
Contact Information
| Contractor | Jerahian Araz; Lic. No.: 1045340-B | 250 N COLLEGE PARK DR F36 UPLAND, CA 91786 |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 5/31/2022 | Conditional Approval | LILIANA PORTILLO |
| Excavation/Setback/Form/Re-Bar | 6/6/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 6/6/2022 | Partial Approval | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 6/10/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 6/15/2022 | Approved | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 7/14/2022 | Approved | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 8/30/2022 | Approved | RYAN SALAZAR |
| HVAC-Rough | 8/30/2022 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 8/30/2022 | Approved | RYAN SALAZAR |
| BUILDING-Rough-Frame | 9/19/2022 | Not Ready for Inspection | SHAVONNE ESPINOZA |
| Interior/Exterior Lathing | 9/19/2022 | Not Ready for Inspection | SHAVONNE ESPINOZA |
| Verify Sprinkler Sign Off | 9/19/2022 | Not Ready for Inspection | SHAVONNE ESPINOZA |
| Interior/Exterior Lathing | 9/21/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| BUILDING-Rough-Frame | 9/27/2022 | Not Ready for Inspection | SHAVONNE ESPINOZA |
| Verify Sprinkler Sign Off | 9/27/2022 | Partial Inspection | SHAVONNE ESPINOZA |
| BUILDING-Rough-Frame | 9/29/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| Insulation | 9/29/2022 | Not Ready for Inspection | SHAVONNE ESPINOZA |
| BUILDING-Rough-Frame | 10/4/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| BUILDING-Rough-Frame | 10/7/2022 | Approved | SHAVONNE ESPINOZA |
| Insulation | 10/21/2022 | Conditional Approval | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 10/21/2022 | Partial Approval | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 11/3/2022 | Approved | RYAN SALAZAR |
| Sewer | 11/3/2022 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 11/18/2022 | Approved | ALIZAH MAYAGOITIA |
| Shower Pan | 11/18/2022 | Approved | ALIZAH MAYAGOITIA |
| Underground Mechanical | 4/10/2023 | Corrections Issued | BRENDAN MORELLI |
| Final | 6/8/2023 | Corrections Issued | BRENDAN MORELLI |
| SGSOV-Seismic Gas S/O Valve | 6/8/2023 | SGSOV Approved | BRENDAN MORELLI |
| Service/Power Release | 6/8/2023 | Approved | BRENDAN MORELLI |
| Smoke Detectors | 6/8/2023 | Corrections Issued | BRENDAN MORELLI |
| ELECTRICAL-Final | 6/21/2023 | Corrections Issued | BRENDAN MORELLI |
| HVAC-Final | 6/21/2023 | Corrections Issued | BRENDAN MORELLI |
| PLUMBING-Final | 6/21/2023 | Approved | BRENDAN MORELLI |
| Smoke Detectors | 6/21/2023 | Approved | BRENDAN MORELLI |
| ELECTRICAL-Final | 6/28/2023 | Approved | BRENDAN MORELLI |
| HVAC-Final | 6/28/2023 | Approved | BRENDAN MORELLI |
| Final | 9/12/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 9/14/2023 | OK to Issue CofO | BRENDAN MORELLI |