8910 S ST ANDREWS PL 90047
Certificate Information: 8910 S ST ANDREWS PL 90047
- Application / Permit
- 21010-10000-03278
- Plan Check / Job No.
- B21LA12381
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW ONE STORY ADU AT REAR OF THE LOT (1,200 SF max per Ordinance, 12.22 A.33(c) AND (d))
- Permit Issued
- Issued on 5/23/2022
- Issuing Office
- Current Status
- CofO Issued on 7/24/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/30/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/9/2021 | RICARDO RAMIREZ |
| Corrections Issued | 7/10/2021 | RICARDO RAMIREZ |
| Applicant returned to address corrections | 11/5/2021 | RICARDO RAMIREZ |
| Plan Check Approved | 12/6/2021 | ADAM HEGAZI |
| Plan Check Approved | 12/6/2021 | AUNG SOE |
| Issued | 5/23/2022 | APPLICANT |
| Building Plans Picked Up | 5/26/2022 | APPLICANT |
| CofO in Progress | 7/3/2024 | JOSE MACIAS |
| Permit Finaled | 7/24/2024 | DEROLD HAUFF |
| CofO Issued | 7/24/2024 | DEROLD HAUFF |
| Permit Finaled | 7/24/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 7/26/2021 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 7/28/2021 | CELINA MORENO |
| Sewer availability | Cleared | 7/28/2021 | CELINA MORENO |
| Construction near power lines | Cleared | 9/30/2021 | RIDWAN HARDY |
| Hydrant and Access approval | Cleared | 10/2/2021 | RUEL COLE |
| Low Impact Development | Cleared | 10/6/2021 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 10/12/2021 | CELINA MORENO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Espino,, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
| Geologist | Kaligi,, Azad Adam; Lic. No.: GEO9287 | 445 S FIGEUROA ST 3100 LOS ANGELES, CA 90071 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 6/13/2022 | Approved | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 6/29/2022 | Corrections Issued | ENRIQUE MIRELES |
| METHANE-Barrier | 6/29/2022 | Not Ready for Inspection | ENRIQUE MIRELES |
| METHANE-Subgrade | 6/29/2022 | Not Ready for Inspection | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 7/5/2022 | Corrections Issued | ENRIQUE MIRELES |
| METHANE-Barrier | 7/5/2022 | Not Ready for Inspection | ENRIQUE MIRELES |
| METHANE-Subgrade | 7/5/2022 | Not Ready for Inspection | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 7/13/2022 | Corrections Issued | ENRIQUE MIRELES |
| METHANE-Barrier | 7/13/2022 | Not Ready for Inspection | ENRIQUE MIRELES |
| METHANE-Subgrade | 7/13/2022 | Not Ready for Inspection | ENRIQUE MIRELES |
| Excavation/Setback/Form/Re-Bar | 9/2/2022 | Approved | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 9/2/2022 | Approved | ENRIQUE MIRELES |
| METHANE-Barrier | 9/2/2022 | Approved | ENRIQUE MIRELES |
| METHANE-Subgrade | 9/2/2022 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 10/14/2022 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 10/14/2022 | Approved | ENRIQUE MIRELES |
| HVAC-Rough | 10/14/2022 | Approved | ENRIQUE MIRELES |
| Shower Pan | 10/14/2022 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 11/9/2022 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 11/9/2022 | Approved | ENRIQUE MIRELES |
| Wood Frame | 11/9/2022 | Approved | ENRIQUE MIRELES |
| Insulation | 11/16/2022 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 11/23/2022 | Approved | ENRIQUE MIRELES |
| Sewer | 11/30/2022 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 12/15/2022 | Approved | ENRIQUE MIRELES |
| Service/Power Release | 12/15/2022 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 2/29/2024 | Approved | JOSE MACIAS |
| ELECTRICAL-Final | 2/29/2024 | Corrections Issued | JOSE MACIAS |
| Final | 2/29/2024 | Corrections Issued | JOSE MACIAS |
| METHANE-Final | 2/29/2024 | Approved | JOSE MACIAS |
| METHANE-Rough | 2/29/2024 | Approved | JOSE MACIAS |
| SGSOV-Seismic Gas S/O Valve | 2/29/2024 | SGSOV Not Required | JOSE MACIAS |
| Smoke Detectors | 2/29/2024 | Approved | JOSE MACIAS |
| Verify Sprinkler Sign Off | 2/29/2024 | Approved | JOSE MACIAS |
| Floor/Roof Diaphrgm/Shear Wall | 6/3/2024 | No Access for Inspection | JOSE MACIAS |
| Final | 6/14/2024 | OK to Issue CofO | JOSE MACIAS |