1035-1037 N CORONADO ST 90026
Certificate Information: 1035-1037 N CORONADO ST 90026
- Application / Permit
- 21010-10000-03263
- Plan Check / Job No.
- B21LA12315
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan ADU per GC 65852.2 (e) (1) (D). the LID clearance has been deferred. approval for LID requirements shall be obtained from LASAN prior to the issuance of CofO
- Permit Issued
- Issued on 3/29/2022
- Issuing Office
- Current Status
- CofO Issued on 9/28/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/26/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/19/2021 | ARSALAN SHABESTARI |
| Corrections Issued | 8/21/2021 | ARSALAN SHABESTARI |
| Quality Review Completed | 8/27/2021 | MINYE PAK |
| Applicant returned to address corrections | 1/14/2022 | ARSALAN SHABESTARI |
| Applicant returned to address corrections | 2/7/2022 | ARSALAN SHABESTARI |
| Plan Check Approved | 3/17/2022 | ARSALAN SHABESTARI |
| Issued | 3/29/2022 | APPLICANT |
| CofO in Progress | 9/15/2023 | FREDDIE RIVERA |
| Permit Finaled | 9/28/2023 | DEROLD HAUFF |
| CofO Issued | 9/28/2023 | DEROLD HAUFF |
| Permit Finaled | 9/28/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 9/9/2021 | WALLIE JONG |
| Highway dedication | Cleared | 9/9/2021 | WALLIE JONG |
| Frnt yard landscape/Water mgmt | Cleared | 10/18/2021 | RICHARD REASER |
| Hydrant and Access approval | Cleared | 10/22/2021 | JOHN CONNEALLY |
| Eng Process Fee Ord 176,300 | Cleared | 1/5/2022 | WALLIE JONG |
| Sewer availability | Cleared | 1/5/2022 | WALLIE JONG |
| Roof/Waste drainage to street | Cleared | 1/14/2022 | WALLIE JONG |
| GPI Written Notices | Cleared | 3/10/2022 | ARSALAN SHABESTARI |
| Grading Pre-Inspection | Cleared | 3/10/2022 | ARSALAN SHABESTARI |
| Construction near power lines | Cleared | 3/14/2022 | NADER ISKANDER |
| Construction within easement | Cleared | 3/14/2022 | NADER ISKANDER |
Contact Information
| Contractor | Marcos Construction Inc; Lic. No.: 686859-B | P O BOX 65552 LOS ANGELES, CA 90065 |
Inspector Information
| FREDDIE RIVERA, (213) 202-3437 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/17/2022 | Partial Approval | FREDDIE RIVERA |
| Pre-Inspection | 5/17/2022 | Corrections Issued | FREDDIE RIVERA |
| Excavation/Setback/Form/Re-Bar | 5/26/2022 | Partial Approval | FREDDIE RIVERA |
| Masonry Wall/Backfill | 6/7/2022 | Approved | FREDDIE RIVERA |
| Excavation/Setback/Form/Re-Bar | 6/23/2022 | Corrections Issued | FREDDIE RIVERA |
| Excavation/Setback/Form/Re-Bar | 6/30/2022 | Approved | FREDDIE RIVERA |
| Footing/Foundation/Slab | 6/30/2022 | Approved | FREDDIE RIVERA |
| METHANE-Barrier | 6/30/2022 | Approved | FREDDIE RIVERA |
| METHANE-Subgrade | 6/30/2022 | Approved | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 7/29/2022 | Partial Approval | FREDDIE RIVERA |
| PLUMBING-Rough | 7/29/2022 | Partial Approval | FREDDIE RIVERA |
| ELECTRICAL-Rough | 9/9/2022 | Approved | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 9/9/2022 | Partial Approval | FREDDIE RIVERA |
| Underground Mechanical | 9/9/2022 | Partial Approval | FREDDIE RIVERA |
| PLUMBING-Rough | 9/13/2022 | Corrections Issued | FREDDIE RIVERA |
| PLUMBING-Rough | 9/15/2022 | Approved | FREDDIE RIVERA |
| Sewer | 10/17/2022 | Corrections Issued | FREDDIE RIVERA |
| Underground Mechanical | 10/17/2022 | Approved | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 10/27/2022 | Partial Inspection | FREDDIE RIVERA |
| Green Building Rough | 10/27/2022 | Partial Inspection | FREDDIE RIVERA |
| HVAC-Rough | 10/27/2022 | Approved | FREDDIE RIVERA |
| Insulation | 10/27/2022 | Partial Approval | FREDDIE RIVERA |
| METHANE-Rough | 10/27/2022 | Approved | FREDDIE RIVERA |
| Verify Sprinkler Sign Off | 10/27/2022 | Partial Inspection | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 11/9/2022 | Partial Inspection | FREDDIE RIVERA |
| Green Building Rough | 11/9/2022 | Partial Inspection | FREDDIE RIVERA |
| Interior/Exterior Lathing | 11/9/2022 | Conditional Approval | FREDDIE RIVERA |
| Verify Sprinkler Sign Off | 11/9/2022 | Corrections Issued | FREDDIE RIVERA |
| Special/Order Compliance | 12/2/2022 | Corrections Issued | FREDDIE RIVERA |
| Wood Frame | 12/2/2022 | Partial Approval | JONATHAN QUACH |
| Wood Frame | 12/19/2022 | Not Ready for Inspection | DAVID BURKHEAD |
| BUILDING-Rough-Frame | 12/21/2022 | Partial Approval | STUART CHAPMAN |
| Green Building Rough | 12/21/2022 | Approved | STUART CHAPMAN |
| Verify Sprinkler Sign Off | 12/21/2022 | Approved | STUART CHAPMAN |
| Insulation | 12/28/2022 | Approved | FREDDIE RIVERA |
| Drywall Nailing | 1/18/2023 | Approved | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 1/18/2023 | Partial Approval | THOMAS LOGRASSO |
| Shower Pan | 1/18/2023 | Approved | THOMAS LOGRASSO |
| Sewer | 4/14/2023 | Corrections Issued | FREDDIE RIVERA |
| Sewer | 4/19/2023 | Approved | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 6/8/2023 | Partial Inspection | FREDDIE RIVERA |
| Final | 6/8/2023 | Partial Inspection | FREDDIE RIVERA |
| Green Building Final | 6/8/2023 | Partial Inspection | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 6/8/2023 | SGSOV Not Ready | FREDDIE RIVERA |
| Service/Power Release | 6/8/2023 | Partial Inspection | FREDDIE RIVERA |
| Smoke Detectors | 6/8/2023 | Partial Inspection | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 7/3/2023 | Approved | FREDDIE RIVERA |
| Final | 7/3/2023 | Corrections Issued | FREDDIE RIVERA |
| Green Building Final | 7/3/2023 | Partial Approval | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 7/3/2023 | SGSOV Not Ready | FREDDIE RIVERA |
| Service/Power Release | 7/3/2023 | Partial Inspection | FREDDIE RIVERA |
| Smoke Detectors | 7/3/2023 | Approved | FREDDIE RIVERA |
| ELECTRICAL-Final | 8/15/2023 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Final | 8/15/2023 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Green Building Final | 8/15/2023 | Approved | ALIZAH MAYAGOITIA |
| HVAC-Final | 8/15/2023 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 8/15/2023 | Approved | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 8/15/2023 | SGSOV Approved | ALIZAH MAYAGOITIA |
| Service/Power Release | 8/15/2023 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 8/17/2023 | Approved | FREDDIE RIVERA |
| Final | 8/17/2023 | Conditional Approval | FREDDIE RIVERA |
| Service/Power Release | 8/17/2023 | Approved | FREDDIE RIVERA |