1035-1037 N CORONADO ST 90026

Certificate Information: 1035-1037 N CORONADO ST 90026

Application / Permit
21010-10000-03263
Plan Check / Job No.
B21LA12315
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan ADU per GC 65852.2 (e) (1) (D). the LID clearance has been deferred. approval for LID requirements shall be obtained from LASAN prior to the issuance of CofO
Permit Issued
Issued on 3/29/2022
Issuing Office
Current Status
CofO Issued on 9/28/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/26/2021 APPLICANT
Assigned to Plan Check Engineer 8/19/2021 ARSALAN SHABESTARI
Corrections Issued 8/21/2021 ARSALAN SHABESTARI
Quality Review Completed 8/27/2021 MINYE PAK
Applicant returned to address corrections 1/14/2022 ARSALAN SHABESTARI
Applicant returned to address corrections 2/7/2022 ARSALAN SHABESTARI
Plan Check Approved 3/17/2022 ARSALAN SHABESTARI
Issued 3/29/2022 APPLICANT
CofO in Progress 9/15/2023 FREDDIE RIVERA
Permit Finaled 9/28/2023 DEROLD HAUFF
CofO Issued 9/28/2023 DEROLD HAUFF
Permit Finaled 9/28/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 9/9/2021 WALLIE JONG
Highway dedication Cleared 9/9/2021 WALLIE JONG
Frnt yard landscape/Water mgmt Cleared 10/18/2021 RICHARD REASER
Hydrant and Access approval Cleared 10/22/2021 JOHN CONNEALLY
Eng Process Fee Ord 176,300 Cleared 1/5/2022 WALLIE JONG
Sewer availability Cleared 1/5/2022 WALLIE JONG
Roof/Waste drainage to street Cleared 1/14/2022 WALLIE JONG
GPI Written Notices Cleared 3/10/2022 ARSALAN SHABESTARI
Grading Pre-Inspection Cleared 3/10/2022 ARSALAN SHABESTARI
Construction near power lines Cleared 3/14/2022 NADER ISKANDER
Construction within easement Cleared 3/14/2022 NADER ISKANDER

Contact Information

Contractor Marcos Construction Inc; Lic. No.: 686859-B P O BOX 65552      LOS ANGELES, CA 90065

Inspector Information

FREDDIE RIVERA, (213) 202-3437 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/17/2022 Partial Approval FREDDIE RIVERA
Pre-Inspection 5/17/2022 Corrections Issued FREDDIE RIVERA
Excavation/Setback/Form/Re-Bar 5/26/2022 Partial Approval FREDDIE RIVERA
Masonry Wall/Backfill 6/7/2022 Approved FREDDIE RIVERA
Excavation/Setback/Form/Re-Bar 6/23/2022 Corrections Issued FREDDIE RIVERA
Excavation/Setback/Form/Re-Bar 6/30/2022 Approved FREDDIE RIVERA
Footing/Foundation/Slab 6/30/2022 Approved FREDDIE RIVERA
METHANE-Barrier 6/30/2022 Approved FREDDIE RIVERA
METHANE-Subgrade 6/30/2022 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 7/29/2022 Partial Approval FREDDIE RIVERA
PLUMBING-Rough 7/29/2022 Partial Approval FREDDIE RIVERA
ELECTRICAL-Rough 9/9/2022 Approved FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 9/9/2022 Partial Approval FREDDIE RIVERA
Underground Mechanical 9/9/2022 Partial Approval FREDDIE RIVERA
PLUMBING-Rough 9/13/2022 Corrections Issued FREDDIE RIVERA
PLUMBING-Rough 9/15/2022 Approved FREDDIE RIVERA
Sewer 10/17/2022 Corrections Issued FREDDIE RIVERA
Underground Mechanical 10/17/2022 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 10/27/2022 Partial Inspection FREDDIE RIVERA
Green Building Rough 10/27/2022 Partial Inspection FREDDIE RIVERA
HVAC-Rough 10/27/2022 Approved FREDDIE RIVERA
Insulation 10/27/2022 Partial Approval FREDDIE RIVERA
METHANE-Rough 10/27/2022 Approved FREDDIE RIVERA
Verify Sprinkler Sign Off 10/27/2022 Partial Inspection FREDDIE RIVERA
BUILDING-Rough-Frame 11/9/2022 Partial Inspection FREDDIE RIVERA
Green Building Rough 11/9/2022 Partial Inspection FREDDIE RIVERA
Interior/Exterior Lathing 11/9/2022 Conditional Approval FREDDIE RIVERA
Verify Sprinkler Sign Off 11/9/2022 Corrections Issued FREDDIE RIVERA
Special/Order Compliance 12/2/2022 Corrections Issued FREDDIE RIVERA
Wood Frame 12/2/2022 Partial Approval JONATHAN QUACH
Wood Frame 12/19/2022 Not Ready for Inspection DAVID BURKHEAD
BUILDING-Rough-Frame 12/21/2022 Partial Approval STUART CHAPMAN
Green Building Rough 12/21/2022 Approved STUART CHAPMAN
Verify Sprinkler Sign Off 12/21/2022 Approved STUART CHAPMAN
Insulation 12/28/2022 Approved FREDDIE RIVERA
Drywall Nailing 1/18/2023 Approved THOMAS LOGRASSO
Interior/Exterior Lathing 1/18/2023 Partial Approval THOMAS LOGRASSO
Shower Pan 1/18/2023 Approved THOMAS LOGRASSO
Sewer 4/14/2023 Corrections Issued FREDDIE RIVERA
Sewer 4/19/2023 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 6/8/2023 Partial Inspection FREDDIE RIVERA
Final 6/8/2023 Partial Inspection FREDDIE RIVERA
Green Building Final 6/8/2023 Partial Inspection FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 6/8/2023 SGSOV Not Ready FREDDIE RIVERA
Service/Power Release 6/8/2023 Partial Inspection FREDDIE RIVERA
Smoke Detectors 6/8/2023 Partial Inspection FREDDIE RIVERA
BUILDING-Rough-Frame 7/3/2023 Approved FREDDIE RIVERA
Final 7/3/2023 Corrections Issued FREDDIE RIVERA
Green Building Final 7/3/2023 Partial Approval FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 7/3/2023 SGSOV Not Ready FREDDIE RIVERA
Service/Power Release 7/3/2023 Partial Inspection FREDDIE RIVERA
Smoke Detectors 7/3/2023 Approved FREDDIE RIVERA
ELECTRICAL-Final 8/15/2023 Not Ready for Inspection ALIZAH MAYAGOITIA
Final 8/15/2023 Not Ready for Inspection ALIZAH MAYAGOITIA
Green Building Final 8/15/2023 Approved ALIZAH MAYAGOITIA
HVAC-Final 8/15/2023 Approved ALIZAH MAYAGOITIA
PLUMBING-Final 8/15/2023 Approved ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 8/15/2023 SGSOV Approved ALIZAH MAYAGOITIA
Service/Power Release 8/15/2023 Not Ready for Inspection ALIZAH MAYAGOITIA
ELECTRICAL-Final 8/17/2023 Approved FREDDIE RIVERA
Final 8/17/2023 Conditional Approval FREDDIE RIVERA
Service/Power Release 8/17/2023 Approved FREDDIE RIVERA