5027 S 11TH AVE 90043
Certificate Information: 5027 S 11TH AVE 90043
- Application / Permit
- 21010-10000-03250
- Plan Check / Job No.
- B21LA12258
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) One story detached ADU on the rear side of lot per LAMC 12.22 A 33 (c)(d)
- Permit Issued
- Issued on 3/7/2022
- Issuing Office
- Current Status
- CofO Issued on 4/29/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/30/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/9/2021 | RAMA DABADGE |
| Corrections Issued | 7/9/2021 | RAMA DABADGE |
| Applicant returned to address corrections | 8/23/2021 | RAHEL BEYENE |
| Applicant returned to address corrections | 9/20/2021 | RAHEL BEYENE |
| Plan Check Approved | 11/1/2021 | SINA KHOSRAVI |
| Issued | 3/7/2022 | APPLICANT |
| Building Plans Picked Up | 3/17/2022 | APPLICANT |
| CofO in Progress | 4/20/2023 | ANTHONY EGSON |
| Permit Finaled | 4/29/2023 | DEROLD HAUFF |
| CofO Issued | 4/29/2023 | DEROLD HAUFF |
| Permit Finaled | 4/29/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 7/23/2021 | CELINA MORENO |
| Roof/Waste drainage to street | Cleared | 7/23/2021 | CELINA MORENO |
| Sewer availability | Cleared | 7/28/2021 | CELINA MORENO |
| Hydrant and Access approval | Cleared | 8/12/2021 | MATTHEW CRAIG |
| Eng Process Fee Ord 176,300 | Cleared | 8/18/2021 | CELINA MORENO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Chi,, Joseph Chiwol; Lic. No.: C53156 | 19623 BOMAR CT ROWLAND HEIGHTS, CA 91748 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 5/3/2022 | Approved | ANTHONY EGSON |
| Footing/Foundation/Slab | 6/7/2022 | Corrections Issued | ANTHONY EGSON |
| Footing/Foundation/Slab | 6/15/2022 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 8/16/2022 | Not Ready for Inspection | ANTHONY EGSON |
| ELECTRICAL-Rough | 8/16/2022 | Corrections Issued | ANTHONY EGSON |
| Green Building Rough | 8/16/2022 | Not Ready for Inspection | ANTHONY EGSON |
| PLUMBING-Rough | 8/16/2022 | Approved | ANTHONY EGSON |
| Sewer | 8/16/2022 | Approved | ANTHONY EGSON |
| Underground Mechanical | 8/16/2022 | Approved | ANTHONY EGSON |
| Verify Sprinkler Sign Off | 8/16/2022 | Approved | ANTHONY EGSON |
| ELECTRICAL-Rough | 8/24/2022 | Approved | ANTHONY EGSON |
| Wood Frame | 8/24/2022 | Corrections Issued | ANTHONY EGSON |
| Wood Frame | 9/2/2022 | Approved | ANTHONY EGSON |
| Insulation | 9/21/2022 | Corrections Issued | ANTHONY EGSON |
| Interior/Exterior Lathing | 9/21/2022 | Approved | ANTHONY EGSON |
| Drywall Nailing | 10/3/2022 | Approved | ANTHONY EGSON |
| Green Building Rough | 10/3/2022 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 10/3/2022 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 12/2/2022 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 12/2/2022 | Corrections Issued | ANTHONY EGSON |
| Final | 12/2/2022 | Not Ready for Inspection | ANTHONY EGSON |
| Green Building Final | 12/2/2022 | Corrections Issued | ANTHONY EGSON |
| HVAC-Final | 12/2/2022 | Not Ready for Inspection | ANTHONY EGSON |
| PLUMBING-Final | 12/2/2022 | Approved | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 12/2/2022 | SGSOV Not Required | ANTHONY EGSON |
| Service/Power Release | 12/2/2022 | Not Ready for Inspection | ANTHONY EGSON |
| Smoke Detectors | 12/2/2022 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 12/14/2022 | Corrections Issued | ANTHONY EGSON |
| Final | 12/14/2022 | Not Ready for Inspection | ANTHONY EGSON |
| Green Building Final | 12/14/2022 | Approved | ANTHONY EGSON |
| HVAC-Final | 12/14/2022 | Approved | ANTHONY EGSON |
| PLUMBING-Final | 12/14/2022 | Approved | ANTHONY EGSON |
| Service/Power Release | 12/14/2022 | Not Ready for Inspection | ANTHONY EGSON |
| Final | 12/20/2022 | Not Ready for Inspection | ANTHONY EGSON |
| Service/Power Release | 12/20/2022 | Corrections Issued | ANTHONY EGSON |
| ELECTRICAL-Final | 2/28/2023 | Approved | ANTHONY EGSON |
| Final | 2/28/2023 | Not Ready for Inspection | ANTHONY EGSON |
| Service/Power Release | 2/28/2023 | Not Ready for Inspection | ANTHONY EGSON |
| Final | 4/20/2023 | OK to Issue CofO | ANTHONY EGSON |
| Service/Power Release | 4/20/2023 | Approved | ANTHONY EGSON |