9820 W KINCARDINE AVE 90034

Certificate Information: 9820 W KINCARDINE AVE 90034

Application / Permit
21010-10000-03247
Plan Check / Job No.
B21LA12212
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 3-STORY SFD WITH ATTACHED GARAGE
Permit Issued
Issued on 1/6/2022
Issuing Office
Current Status
CofO Issued on 8/14/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/2/2021 APPLICANT
Assigned to Plan Check Engineer 8/12/2021 MAHNAZ NOURHASHEMI
Corrections Issued 8/19/2021 MAHNAZ NOURHASHEMI
Quality Review Completed 8/24/2021 JASON HEALEY
Applicant returned to address corrections 11/5/2021 MAHNAZ NOURHASHEMI
Building Plans Picked Up 11/12/2021 APPLICANT
Plan Check Approved 12/9/2021 MAHNAZ NOURHASHEMI
Issued 1/6/2022 APPLICANT
Permit Finaled 8/14/2024 RICHARD STEINBACH
CofO Issued 8/14/2024 RICHARD STEINBACH
Permit Finaled 8/14/2024 RICHARD STEINBACH

Permit Application Clearance Information

Permit Cleared 9/1/2021 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 9/3/2021 DINAH GARIN
Sewer availability Cleared 9/3/2021 DINAH GARIN
Specific Plan Cleared 9/30/2021 PETE EYRE
Hydrant and Access approval Cleared 10/21/2021 JOHN CONNEALLY
GPI Written Notices Cleared 11/5/2021 MAHNAZ NOURHASHEMI
Grading Pre-Inspection Cleared 11/5/2021 MAHNAZ NOURHASHEMI
Trees in Parkway Cleared 11/17/2021 ADALBERTO VERA
Low Impact Development Cleared 12/6/2021 MARCO SANCHEZ
Roof/Waste drainage to street Cleared 12/8/2021 DINAH GARIN

Contact Information

Architect Borghei,, Mo; Lic. No.: C17777 12249 DOROTHY STREET      LOS ANGELES, CA 90049
Contractor Owner-Builder       ,
Engineer Yaprak,, Taskin Tolga; Lic. No.: C72927 560 31ST ST      MANHATTAN BEACH, CA 90266

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/1/2022 Partial Inspection KEVIN SARGSYAN
PLUMBING-Rough 4/4/2022 Partial Approval KEVIN SARGSYAN
Footing/Foundation/Slab 4/12/2022 Partial Approval OGANES TARAKHCHYAN
Deputy Reinf. Concrete 4/14/2022 No Result Entered RONALD WEBER
Reinforced Concrete Frame 4/28/2022 Partial Approval KEVIN SARGSYAN
Footing/Foundation/Slab 4/29/2022 Not Ready for Inspection OGANES TARAKHCHYAN
Deputy Reinf. Concrete 5/2/2022 Partial Approval OGANES TARAKHCHYAN
Footing/Foundation/Slab 5/26/2022 Corrections Issued KEVIN SARGSYAN
PLUMBING-Rough 5/31/2022 Partial Approval KEVIN SARGSYAN
Reinforced Concrete Frame 5/31/2022 Partial Approval KEVIN SARGSYAN
Deputy Reinf. Concrete 6/3/2022 Conditional Approval MICHAEL PELHAM
Deputy Drilled-In Anchors 6/23/2022 Conditional Approval KEVIN SARGSYAN
PLUMBING-Rough 7/12/2022 Corrections Issued KEVIN SARGSYAN
PLUMBING-Rough 7/13/2022 Partial Approval KEVIN SARGSYAN
Footing/Foundation/Slab 7/26/2022 Corrections Issued STEPHANIE SWANSON
Special/Order Compliance 7/26/2022 Partial Inspection MICHAEL PELHAM
Floor/Roof Diaphrgm/Shear Wall 8/18/2022 Conditional Approval JOHN KIDWELL
Gas Test 9/2/2022 Partial Inspection OGANES TARAKHCHYAN
Deputy Wood Construction 9/23/2022 Partial Approval OGANES TARAKHCHYAN
Pre-Inspection 10/6/2022 Partial Approval OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 10/21/2022 Not Ready for Inspection OGANES TARAKHCHYAN
Deputy Drilled-In Anchors 11/14/2022 Conditional Approval OGANES TARAKHCHYAN
Pre-Inspection 11/16/2022 Partial Approval OGANES TARAKHCHYAN
Pre-Inspection 11/22/2022 Not Ready for Inspection OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 12/6/2022 Partial Approval OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 12/8/2022 Partial Approval JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 12/12/2022 Approved OGANES TARAKHCHYAN
ELECTRICAL-Rough 12/22/2022 Not Ready for Inspection OGANES TARAKHCHYAN
PLUMBING-Rough 12/22/2022 Not Ready for Inspection OGANES TARAKHCHYAN
PLUMBING-Rough 1/3/2023 Approved OGANES TARAKHCHYAN
ELECTRICAL-Rough 1/5/2023 Approved OGANES TARAKHCHYAN
HVAC-Rough 1/11/2023 Approved OGANES TARAKHCHYAN
BUILDING-Rough-Frame 1/13/2023 Partial Approval OGANES TARAKHCHYAN
Green Building Rough 1/13/2023 Approved OGANES TARAKHCHYAN
Verify Sprinkler Sign Off 1/13/2023 Approved OGANES TARAKHCHYAN
BUILDING-Rough-Frame 2/13/2023 Approved ASHLEY THOMPSON
Insulation 2/13/2023 Approved ASHLEY THOMPSON
Interior/Exterior Lathing 2/13/2023 Partial Approval ASHLEY THOMPSON
Drywall Nailing 2/17/2023 Not Ready for Inspection ASHLEY THOMPSON
Drywall Nailing 2/27/2023 Approved STEPHANIE SWANSON
Pre-Inspection 3/6/2023 Partial Approval ASHLEY THOMPSON
Interior/Exterior Lathing 3/23/2023 Partial Approval HERBERT GIRON
Shower Pan 4/12/2023 Approved JESUS PINEDA
Interior/Exterior Lathing 4/20/2023 Approved CLAYTON GRAHAM
Pre-Inspection 8/10/2023 Partial Inspection CLAYTON GRAHAM
Deputy Reinf. Concrete 8/24/2023 Conditional Approval CLAYTON GRAHAM
Sewer 9/18/2023 Approved CARLOS MATAMOROS
Underground Mechanical 9/18/2023 Approved CARLOS MATAMOROS
PLUMBING-Final 2/21/2024 Approved OGANES TARAKHCHYAN
ELECTRICAL-Final 3/8/2024 Corrections Issued OGANES TARAKHCHYAN
HVAC-Final 4/15/2024 Approved OGANES TARAKHCHYAN
Final 4/18/2024 Corrections Issued OGANES TARAKHCHYAN
Footing/Foundation/Slab 4/18/2024 Approved OGANES TARAKHCHYAN
Green Building Final 4/18/2024 Approved OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 4/18/2024 SGSOV Approved OGANES TARAKHCHYAN
Service/Power Release 4/18/2024 Approved OGANES TARAKHCHYAN
Smoke Detectors 4/18/2024 Approved OGANES TARAKHCHYAN
Final 7/30/2024 Conditional Approval MICHAEL PELHAM
Deputy Reinf. Concrete 8/10/2024 Approved MICHAEL PELHAM