1376-1376 1/2 N EDGECLIFFE DR 90026

Certificate Information: 1376-1376 1/2 N EDGECLIFFE DR 90026

Application / Permit
21010-10000-03239
Plan Check / Job No.
B21LA12137
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
`NEW 3-STORY DUPLEX WITH ATTACHED GARAGE (REAR) 2 OF 3
Permit Issued
Issued on 12/13/2023
Issuing Office
Current Status
CofO Corrected on 1/16/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/28/2021 APPLICANT
Assigned to Plan Check Engineer 7/15/2021 FARSHAD ALIMOHAMADI
Corrections Issued 7/29/2021 FARSHAD ALIMOHAMADI
Quality Review Completed 8/3/2021 SAI KHUM
Building Plans Picked Up 8/5/2021 APPLICANT
Applicant returned to address corrections 2/4/2022 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 3/17/2022 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 4/21/2022 FARSHAD ALIMOHAMADI
Plan Check Approved 8/30/2022 FARSHAD ALIMOHAMADI
Issued 12/13/2023 APPLICANT
CofO in Progress 9/3/2025 FREDDIE RIVERA
CofO Issued-Status Void 9/5/2025 DEROLD HAUFF
Permit Finaled-Status Void 9/5/2025 DEROLD HAUFF
Re-Activate Permit 1/15/2026 DEROLD HAUFF
Permit Finaled 1/16/2026 DEROLD HAUFF
CofO Corrected 1/16/2026 DEROLD HAUFF
Permit Finaled 1/16/2026 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 11/1/2021 STEVE MELGAR
BHO/Hillside ordinance Cleared 11/1/2021 STEVE MELGAR
BHO/Hillside ordinance Cleared 11/1/2021 STEVE MELGAR
BHO/Hillside ordinance Cleared 11/1/2021 STEVE MELGAR
BHO/Hillside ordinance Cleared 11/1/2021 STEVE MELGAR
BHO/Hillside ordinance Cleared 11/1/2021 STEVE MELGAR
Highway dedication Cleared 11/1/2021 STEVE MELGAR
Permit Cleared 11/1/2021 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 11/12/2021 STEVE MELGAR
Sewer availability Cleared 11/12/2021 STEVE MELGAR
GPI Written Notices Cleared 1/20/2022 FARSHAD ALIMOHAMADI
Grading Pre-Inspection Cleared 1/20/2022 FARSHAD ALIMOHAMADI
Hydrant and Access approval Cleared 1/29/2022 RUEL COLE
Low Impact Development Cleared 2/23/2022 ROGELIO CORTES
Trees in Parkway Cleared 5/10/2022 ADALBERTO VERA
Frnt yard landscape/Water mgmt Cleared 8/17/2022 MAXFIELD VERMY
Building over 36-ft Cleared 8/30/2022 CALOSHA APPROVED
Roof/Waste drainage to street Cleared 8/31/2022 STEVE MELGAR

Contact Information

Contractor Elm Construction; Lic. No.: 1099704-B 1976 S LA CIENEGA BLVD   C-127    LOS ANGELES, CA 90034
Engineer Dorta,, Michael Rohrs; Lic. No.: C72538 2445 VIA SONOMA      PALOS VERDES ESTATES, CA 90274

Inspector Information

FREDDIE RIVERA, (213) 202-3437 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/18/2024 Approved FREDDIE RIVERA
Underground Mechanical 1/24/2024 Corrections Issued FREDDIE RIVERA
PLUMBING-Rough 1/26/2024 Partial Approval FREDDIE RIVERA
Special/Order Compliance 1/26/2024 Corrections Issued FREDDIE RIVERA
Footing/Foundation/Slab 2/15/2024 Partial Inspection FREDDIE RIVERA
Excavation/Setback/Form/Re-Bar 2/16/2024 Conditional Approval FREDDIE RIVERA
Special/Order Compliance 2/16/2024 Corrections Issued FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 3/14/2024 Partial Approval FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 3/26/2024 Partial Approval JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 4/17/2024 Partial Approval FREDDIE RIVERA
ELECTRICAL-Rough 7/29/2024 Corrections Issued FREDDIE RIVERA
HVAC-Rough 7/29/2024 No Access for Inspection FREDDIE RIVERA
PLUMBING-Rough 7/29/2024 Approved FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 7/30/2024 Corrections Issued FREDDIE RIVERA
ELECTRICAL-Rough 7/31/2024 Not Ready for Inspection HAMIK HARTOUNIAN
HVAC-Rough 7/31/2024 Corrections Issued HAMIK HARTOUNIAN
ELECTRICAL-Rough 8/1/2024 Approved FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 8/1/2024 Corrections Issued FREDDIE RIVERA
HVAC-Rough 8/1/2024 Corrections Issued FREDDIE RIVERA
Deputy Wood Construction 8/2/2024 Conditional Approval FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 8/6/2024 Corrections Issued FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 8/15/2024 Partial Approval FREDDIE RIVERA
HVAC-Rough 8/15/2024 Approved FREDDIE RIVERA
Wood Frame 8/20/2024 Corrections Issued FREDDIE RIVERA
BUILDING-Rough-Frame 8/21/2024 Approved FREDDIE RIVERA
Green Building Rough 8/21/2024 Approved FREDDIE RIVERA
Verify Sprinkler Sign Off 8/21/2024 Approved FREDDIE RIVERA
Insulation 9/9/2024 Approved FREDDIE RIVERA
Drywall Nailing 9/17/2024 Approved NICHOLAS LOPEZ
Interior/Exterior Lathing 9/17/2024 Partial Approval NICHOLAS LOPEZ
Interior/Exterior Lathing 11/19/2024 Approved NICHOLAS LOPEZ
Underground Mechanical 5/6/2025 Approved FREDDIE RIVERA
Sewer 5/7/2025 Approved ALEX COLIN
ELECTRICAL-Final 5/23/2025 Corrections Issued FREDDIE RIVERA
Final 5/23/2025 Partial Inspection FREDDIE RIVERA
Footing/Foundation/Slab 5/23/2025 Partial Inspection FREDDIE RIVERA
Green Building Final 5/23/2025 Partial Inspection FREDDIE RIVERA
HVAC-Final 5/23/2025 Corrections Issued FREDDIE RIVERA
PLUMBING-Final 5/23/2025 Partial Inspection FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 5/23/2025 SGSOV Not Ready FREDDIE RIVERA
Service/Power Release 5/23/2025 Partial Inspection FREDDIE RIVERA
Smoke Detectors 5/23/2025 Approved FREDDIE RIVERA
ELECTRICAL-Final 5/28/2025 Approved FREDDIE RIVERA
HVAC-Final 5/28/2025 Approved FREDDIE RIVERA
PLUMBING-Final 5/28/2025 Corrections Issued FREDDIE RIVERA
Final 5/30/2025 Partial Inspection FREDDIE RIVERA
Footing/Foundation/Slab 5/30/2025 Approved FREDDIE RIVERA
Gas Test 5/30/2025 Approved FREDDIE RIVERA
Green Building Final 5/30/2025 Partial Inspection FREDDIE RIVERA
PLUMBING-Final 5/30/2025 Approved FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 5/30/2025 SGSOV Not Ready FREDDIE RIVERA
Service/Power Release 5/30/2025 Partial Inspection FREDDIE RIVERA
Service/Power Release 6/11/2025 Approved FREDDIE RIVERA
Final 8/22/2025 Corrections Issued FREDDIE RIVERA
Green Building Final 8/22/2025 Approved FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 8/22/2025 SGSOV Approved FREDDIE RIVERA
Final 8/26/2025 OK to Issue CofO FREDDIE RIVERA