1324 1/2 E 108TH ST 90059
Certificate Information: 1324 1/2 E 108TH ST 90059
- Application / Permit
- 21010-10000-03171
- Plan Check / Job No.
- B21LA11955
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EXISTING GARAGE CONVERTED TO A.D.U. PER GCS 65852.2(e)(1)(A)
- Permit Issued
- Issued on 8/18/2021
- Issuing Office
- Current Status
- CofO Issued on 8/31/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/28/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/2/2021 | JOE VO |
| Corrections Issued | 7/2/2021 | JOE VO |
| Plan Check Approved | 8/9/2021 | JOE VO |
| Issued | 8/18/2021 | APPLICANT |
| CofO in Progress | 8/31/2023 | JOHN KLARIN |
| Permit Finaled | 8/31/2023 | ANSON MAGLASANG |
| CofO Issued | 8/31/2023 | ANSON MAGLASANG |
| Permit Finaled | 8/31/2023 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 7/14/2021 | JEANIE LAM |
| Sewer availability | Cleared | 7/14/2021 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 8/10/2021 | JEANIE LAM |
Contact Information
| Contractor | All In One Construction; Lic. No.: 674782-B | 1056 CYPRESS AVENUE #H LA HABRA, CA 90631 |
| Engineer | Melchor,, Oscar Elias; Lic. No.: NA76828 | , |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/16/2021 | Conditional Approval | WILLIAM ROSE |
| Excavation/Setback/Form/Re-Bar | 9/22/2021 | Corrections Issued | EUGENE CASSIDY |
| Footing/Foundation/Slab | 9/22/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| PLUMBING-Rough | 9/22/2021 | Partial Approval | EUGENE CASSIDY |
| Footing/Foundation/Slab | 9/28/2021 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 10/28/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 10/28/2021 | Partial Approval | EUGENE CASSIDY |
| Green Building Rough | 10/28/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| Wood Frame | 10/28/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| ELECTRICAL-Rough | 1/11/2022 | Partial Approval | EUGENE CASSIDY |
| PLUMBING-Rough | 1/11/2022 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 1/14/2022 | Corrections Issued | EUGENE CASSIDY |
| Green Building Rough | 1/14/2022 | Conditional Approval | EUGENE CASSIDY |
| Interior/Exterior Lathing | 1/14/2022 | Partial Approval | EUGENE CASSIDY |
| Wood Frame | 1/14/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| Insulation | 1/25/2022 | Corrections Issued | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 2/4/2022 | Partial Approval | AMY COLIN |
| Drywall Nailing | 2/4/2022 | Corrections Issued | AMY COLIN |
| HVAC-Rough | 2/4/2022 | Corrections Issued | AMY COLIN |
| Insulation | 2/4/2022 | Approved | AMY COLIN |
| Drywall Nailing | 2/10/2022 | Approved | JOHN KLARIN |
| Green Building Rough | 2/10/2022 | Approved | JOHN KLARIN |
| Sewer | 3/18/2022 | Approved | EUGENE CASSIDY |
| Drywall Nailing | 6/28/2022 | Approved | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 12/13/2022 | SGSOV Not Ready | JOHN KLARIN |
| BUILDING-Rough-Frame | 12/20/2022 | Approved | JOHN KLARIN |
| Final | 12/20/2022 | Corrections Issued | JOHN KLARIN |
| Green Building Final | 12/20/2022 | Corrections Issued | JOHN KLARIN |
| SGSOV-Seismic Gas S/O Valve | 12/20/2022 | SGSOV Approved | JOHN KLARIN |
| Smoke Detectors | 12/20/2022 | Approved | JOHN KLARIN |
| Final | 2/3/2023 | Corrections Issued | JOHN KLARIN |
| Green Building Final | 2/3/2023 | Approved | JOHN KLARIN |
| Final | 4/14/2023 | Corrections Issued | JOHN KLARIN |
| Final | 8/21/2023 | No Access for Inspection | JOHN KLARIN |
| Final | 8/25/2023 | Corrections Issued | JAMES CHAVEZ |
| ELECTRICAL-Final | 8/30/2023 | Approved | JOHN KLARIN |
| Final | 8/30/2023 | OK to Issue CofO | JOHN KLARIN |
| HVAC-Final | 8/30/2023 | Approved | JOHN KLARIN |
| PLUMBING-Final | 8/30/2023 | Approved | JOHN KLARIN |