1324 1/2 E 108TH ST 90059

Certificate Information: 1324 1/2 E 108TH ST 90059

Application / Permit
21010-10000-03171
Plan Check / Job No.
B21LA11955
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EXISTING GARAGE CONVERTED TO A.D.U. PER GCS 65852.2(e)(1)(A)
Permit Issued
Issued on 8/18/2021
Issuing Office
Current Status
CofO Issued on 8/31/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/28/2021 APPLICANT
Assigned to Plan Check Engineer 7/2/2021 JOE VO
Corrections Issued 7/2/2021 JOE VO
Plan Check Approved 8/9/2021 JOE VO
Issued 8/18/2021 APPLICANT
CofO in Progress 8/31/2023 JOHN KLARIN
Permit Finaled 8/31/2023 ANSON MAGLASANG
CofO Issued 8/31/2023 ANSON MAGLASANG
Permit Finaled 8/31/2023 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 7/14/2021 JEANIE LAM
Sewer availability Cleared 7/14/2021 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 8/10/2021 JEANIE LAM

Contact Information

Contractor All In One Construction; Lic. No.: 674782-B 1056 CYPRESS AVENUE #H      LA HABRA, CA 90631
Engineer Melchor,, Oscar Elias; Lic. No.: NA76828       ,

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 9/16/2021 Conditional Approval WILLIAM ROSE
Excavation/Setback/Form/Re-Bar 9/22/2021 Corrections Issued EUGENE CASSIDY
Footing/Foundation/Slab 9/22/2021 Not Ready for Inspection EUGENE CASSIDY
PLUMBING-Rough 9/22/2021 Partial Approval EUGENE CASSIDY
Footing/Foundation/Slab 9/28/2021 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 10/28/2021 Not Ready for Inspection EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 10/28/2021 Partial Approval EUGENE CASSIDY
Green Building Rough 10/28/2021 Not Ready for Inspection EUGENE CASSIDY
Wood Frame 10/28/2021 Not Ready for Inspection EUGENE CASSIDY
ELECTRICAL-Rough 1/11/2022 Partial Approval EUGENE CASSIDY
PLUMBING-Rough 1/11/2022 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 1/14/2022 Corrections Issued EUGENE CASSIDY
Green Building Rough 1/14/2022 Conditional Approval EUGENE CASSIDY
Interior/Exterior Lathing 1/14/2022 Partial Approval EUGENE CASSIDY
Wood Frame 1/14/2022 Not Ready for Inspection EUGENE CASSIDY
Insulation 1/25/2022 Corrections Issued ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 2/4/2022 Partial Approval AMY COLIN
Drywall Nailing 2/4/2022 Corrections Issued AMY COLIN
HVAC-Rough 2/4/2022 Corrections Issued AMY COLIN
Insulation 2/4/2022 Approved AMY COLIN
Drywall Nailing 2/10/2022 Approved JOHN KLARIN
Green Building Rough 2/10/2022 Approved JOHN KLARIN
Sewer 3/18/2022 Approved EUGENE CASSIDY
Drywall Nailing 6/28/2022 Approved ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 12/13/2022 SGSOV Not Ready JOHN KLARIN
BUILDING-Rough-Frame 12/20/2022 Approved JOHN KLARIN
Final 12/20/2022 Corrections Issued JOHN KLARIN
Green Building Final 12/20/2022 Corrections Issued JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 12/20/2022 SGSOV Approved JOHN KLARIN
Smoke Detectors 12/20/2022 Approved JOHN KLARIN
Final 2/3/2023 Corrections Issued JOHN KLARIN
Green Building Final 2/3/2023 Approved JOHN KLARIN
Final 4/14/2023 Corrections Issued JOHN KLARIN
Final 8/21/2023 No Access for Inspection JOHN KLARIN
Final 8/25/2023 Corrections Issued JAMES CHAVEZ
ELECTRICAL-Final 8/30/2023 Approved JOHN KLARIN
Final 8/30/2023 OK to Issue CofO JOHN KLARIN
HVAC-Final 8/30/2023 Approved JOHN KLARIN
PLUMBING-Final 8/30/2023 Approved JOHN KLARIN