1722 S FAIRFAX AVE 90019
Certificate Information: 1722 S FAIRFAX AVE 90019
- Application / Permit
- 21010-10000-03170
- Plan Check / Job No.
- B21LA11952
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- *ePLAN CHECK* New Detached ADU of 437.80 sq ft including 1 bedroom, 1 bath, full kitchen, and laundry space. New porch attached to the new ADU of 180 sq ft
- Permit Issued
- Issued on 6/5/2023
- Issuing Office
- Current Status
- CofO Issued on 5/7/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/1/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/22/2021 | ARSALAN SHABESTARI |
| Corrections Issued | 7/24/2021 | ARSALAN SHABESTARI |
| Quality Review Completed | 7/25/2021 | PRANITA SHAH |
| Plan Check Approved | 1/18/2023 | ARSALAN SHABESTARI |
| Issued | 6/5/2023 | APPLICANT |
| CofO in Progress | 5/6/2024 | JEFFREY MEAD |
| Permit Finaled | 5/7/2024 | DEROLD HAUFF |
| CofO Issued | 5/7/2024 | DEROLD HAUFF |
| Permit Finaled | 5/7/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 8/12/2021 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 8/18/2021 | STEVE MELGAR |
| Sewer availability | Cleared | 8/18/2021 | STEVE MELGAR |
| Hydrant and Access approval | Cleared | 10/3/2021 | GILBERT URREA |
| Construction near power lines | Cleared | 8/12/2022 | RIDWAN HARDY |
| Construction within easement | Cleared | 8/12/2022 | RIDWAN HARDY |
| Low Impact Development | Cleared | 8/19/2022 | CHRIS VONG |
| Roof/Waste drainage to street | Cleared | 12/19/2022 | STEVE MELGAR |
Contact Information
| Contractor | Libertas Investments Inc; Lic. No.: 1033100-B | , |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/9/2023 | Partial Inspection | ALIZAH MAYAGOITIA |
| Sewer | 6/9/2023 | Partial Approval | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 6/14/2023 | Corrections Issued | JOSE AVILA |
| METHANE-Barrier | 6/14/2023 | Approved | JOSE AVILA |
| METHANE-Subgrade | 6/14/2023 | Approved | JOSE AVILA |
| Excavation/Setback/Form/Re-Bar | 8/16/2023 | Approved | JOSE AVILA |
| Special/Order Compliance | 8/16/2023 | Order to Comply Issued | RONNIE MINDANAO |
| Floor/Roof Diaphrgm/Shear Wall | 8/30/2023 | Corrections Issued | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 9/21/2023 | Approved | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 10/18/2023 | Corrections Issued | JOSE AVILA |
| ELECTRICAL-Rough | 11/7/2023 | Approved | JOSE AVILA |
| HVAC-Rough | 11/7/2023 | Conditional Approval | JOSE AVILA |
| PLUMBING-Rough | 11/7/2023 | Corrections Issued | JOSE AVILA |
| Wood Frame | 11/7/2023 | Approved | JOSE AVILA |
| Deputy Drilled-In Anchors | 12/5/2023 | Conditional Approval | RONNIE MINDANAO |
| Deputy Wood Construction | 12/5/2023 | Conditional Approval | RONNIE MINDANAO |
| Floor/Roof Diaphrgm/Shear Wall | 12/6/2023 | Partial Approval | STUART CHAPMAN |
| HVAC-Rough | 12/6/2023 | Corrections Issued | STUART CHAPMAN |
| PLUMBING-Rough | 12/6/2023 | Approved | STUART CHAPMAN |
| Excavation/Setback/Form/Re-Bar | 1/10/2024 | Partial Approval | BRENDAN MORELLI |
| Interior/Exterior Lathing | 1/10/2024 | Corrections Issued | BRENDAN MORELLI |
| Interior/Exterior Lathing | 1/16/2024 | Not Ready for Inspection | RONNIE MINDANAO |
| Interior/Exterior Lathing | 1/25/2024 | Partial Approval | STUART CHAPMAN |
| Insulation | 2/22/2024 | Approved | STUART CHAPMAN |
| Drywall Nailing | 2/27/2024 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 3/6/2024 | Approved | STUART CHAPMAN |
| BUILDING-Rough-Frame | 4/24/2024 | Approved | JOAQUIN GREENOUGH |
| Final | 4/24/2024 | Corrections Issued | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 4/24/2024 | Approved | JOAQUIN GREENOUGH |
| Green Building Final | 4/24/2024 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Green Building Rough | 4/24/2024 | Approved | JOAQUIN GREENOUGH |
| METHANE-Final | 4/24/2024 | Approved | JOAQUIN GREENOUGH |
| METHANE-Rough | 4/24/2024 | Approved | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 4/24/2024 | SGSOV Not Ready | JOAQUIN GREENOUGH |
| Service/Power Release | 4/24/2024 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Smoke Detectors | 4/24/2024 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Verify Sprinkler Sign Off | 4/24/2024 | Approved | JOAQUIN GREENOUGH |
| Final | 5/1/2024 | OK to Issue CofO | JEFFREY MEAD |
| Green Building Final | 5/1/2024 | Approved | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 5/1/2024 | SGSOV Approved | JEFFREY MEAD |
| Service/Power Release | 5/1/2024 | Not Required | JEFFREY MEAD |
| Smoke Detectors | 5/1/2024 | Approved | JEFFREY MEAD |