629 E 38TH ST 90011
Certificate Information: 629 E 38TH ST 90011
- Application / Permit
- 21010-10000-03166
- Plan Check / Job No.
- B21LA11917
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 1 STORY ACCESSORY DWELLING UNIT
- Permit Issued
- Issued on 1/28/2022
- Issuing Office
- Current Status
- CofO Issued on 7/15/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/26/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/2/2021 | FERNANDO FLORES |
| Corrections Issued | 7/8/2021 | FERNANDO FLORES |
| Applicant returned to address corrections | 12/21/2021 | TSE MING HUANG |
| Plan Check Approved | 1/13/2022 | FERNANDO FLORES |
| Issued | 1/28/2022 | APPLICANT |
| Building Plans Picked Up | 2/3/2022 | APPLICANT |
| CofO in Progress | 7/12/2022 | JOAQUIN GREENOUGH |
| CofO Issued | 7/15/2022 | DEROLD HAUFF |
| Permit Finaled | 7/15/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 8/3/2021 | JEANIE LAM |
| Hydrant and Access approval | Cleared | 9/13/2021 | MATTHEW CRAIG |
| Construction near power lines | Cleared | 9/17/2021 | RIDWAN HARDY |
| Eng Process Fee Ord 176,300 | Cleared | 10/7/2021 | JEANIE LAM |
| Sewer availability | Cleared | 10/7/2021 | JEANIE LAM |
| Low Impact Development | Cleared | 12/10/2021 | LONDY ALVARADO |
| Roof/Waste drainage to street | Cleared | 1/28/2022 | AMAAN MALIK |
Contact Information
| Contractor | West Coast Rivers Construction Co; Lic. No.: 892174-B | P O BOX 146 DOWNEY, CA 90241 |
| Engineer | Mena,, Rolando A; Lic. No.: C50331 | 544 1/2 BRITTANIA ST #A LOS ANGELES, CA 90033 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/14/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 2/14/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 2/14/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Underground Mechanical | 2/14/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Underground Mechanical | 2/23/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 2/28/2022 | Partial Approval | STUART CHAPMAN |
| Footing/Foundation/Slab | 3/3/2022 | Approved | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 3/21/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Wood Frame | 3/21/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Deputy Wood Construction | 3/22/2022 | Conditional Approval | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 3/29/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 3/29/2022 | Approved | JOAQUIN GREENOUGH |
| Green Building Rough | 3/29/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| HVAC-Rough | 3/29/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 3/29/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Verify Sprinkler Sign Off | 3/29/2022 | Approved | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 4/8/2022 | Approved | JOAQUIN GREENOUGH |
| Green Building Rough | 4/8/2022 | Approved | JOAQUIN GREENOUGH |
| HVAC-Rough | 4/8/2022 | Approved | JOAQUIN GREENOUGH |
| Interior/Exterior Lathing | 4/8/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 4/8/2022 | Approved | JOAQUIN GREENOUGH |
| Insulation | 4/12/2022 | Approved | JOAQUIN GREENOUGH |
| Interior/Exterior Lathing | 4/12/2022 | Partial Approval | JOAQUIN GREENOUGH |
| Drywall Nailing | 4/15/2022 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 4/15/2022 | Approved | STUART CHAPMAN |
| Final | 5/31/2022 | Corrections Issued | ANTHONY EGSON |
| Green Building Final | 5/31/2022 | Approved | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 5/31/2022 | SGSOV Not Required | ANTHONY EGSON |
| Service/Power Release | 5/31/2022 | Approved | ANTHONY EGSON |
| Smoke Detectors | 5/31/2022 | Approved | ANTHONY EGSON |
| Final | 6/10/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Final | 6/21/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Final | 6/29/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Final | 7/6/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Final | 7/11/2022 | OK to Issue CofO | JOAQUIN GREENOUGH |