670 W 28TH ST 90007
Certificate Information: 670 W 28TH ST 90007
- Application / Permit
- 21010-10000-03145
- Plan Check / Job No.
- B21LA11865
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Apartment
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) 1-STORY ACCESSORY DWELLING UNIT WITH ROOFTOP DECK PER CA GOVT CODE 65852.2(e)(1)(A). “The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy.”
- Permit Issued
- Issued on 1/6/2022
- Issuing Office
- Current Status
- CofO Issued on 2/10/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/23/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/15/2021 | DANIEL YIP |
| Corrections Issued | 7/20/2021 | DANIEL YIP |
| Quality Review Completed | 7/26/2021 | JASON HEALEY |
| Building Plans Picked Up | 7/29/2021 | APPLICANT |
| Disabled Access Plans Picked Up | 8/10/2021 | APPLICANT |
| Applicant returned to address corrections | 8/26/2021 | DANIEL YIP |
| Applicant returned to address corrections | 10/22/2021 | DANIEL YIP |
| Plan Check Approved | 12/14/2021 | DANIEL YIP |
| Issued | 1/6/2022 | APPLICANT |
| CofO in Progress | 2/10/2023 | ERNESTO CORRAL |
| CofO Issued | 2/10/2023 | ERNESTO CORRAL |
| Permit Finaled | 2/10/2023 | ERNESTO CORRAL |
Permit Application Clearance Information
| Address approval | Cleared | 7/26/2021 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 7/27/2021 | CECILIO NAVARRO |
| Sewer availability | Cleared | 7/30/2021 | CECILIO NAVARRO |
| Redevelopment Project Area | Cleared | 8/13/2021 | GRACIELA ACOSTA |
| Hydrant and Access approval | Cleared | 9/15/2021 | MATTHEW CRAIG |
| Roof/Waste drainage to street | Cleared | 9/16/2021 | CECILIO NAVARRO |
| ZI | Cleared | 10/4/2021 | JASON CHAN |
| DAS Clearance | Cleared | 10/7/2021 | EDDIE GARIN |
Contact Information
| Contractor | Dh Remodel Services; Lic. No.: 1030925-B | 5850 W 3RD STREET #160 LOS ANGELES, CA 90036 |
Inspector Information
| PAUL BAZERKANIAN, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| LUIS CCAMACHO, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALAN MORELOS, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 3/22/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Green Building Rough | 3/22/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| METHANE-Rough | 3/22/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Pre-Inspection | 3/22/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Verify Sprinkler Sign Off | 3/22/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Insulation | 4/13/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Interior/Exterior Lathing | 4/13/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Pre-Inspection | 4/13/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 11/9/2022 | Partial Approval | JAMES POWERS |
| Drywall Nailing | 11/9/2022 | Approved | JAMES POWERS |
| Final | 11/9/2022 | Not Ready for Inspection | JAMES POWERS |
| Footing/Foundation/Slab | 11/9/2022 | Partial Approval | JAMES POWERS |
| Green Building Final | 11/9/2022 | Approved | JAMES POWERS |
| Green Building Rough | 11/9/2022 | Approved | JAMES POWERS |
| METHANE-Barrier | 11/9/2022 | Not Ready for Inspection | JAMES POWERS |
| METHANE-Final | 11/9/2022 | Not Ready for Inspection | JAMES POWERS |
| METHANE-Rough | 11/9/2022 | Not Ready for Inspection | JAMES POWERS |
| METHANE-Subgrade | 11/9/2022 | Not Ready for Inspection | JAMES POWERS |
| SGSOV-Seismic Gas S/O Valve | 11/9/2022 | SGSOV Approved | JAMES POWERS |
| Service/Power Release | 11/9/2022 | Not Ready for Inspection | JAMES POWERS |
| Smoke Detectors | 11/9/2022 | Approved | JAMES POWERS |
| Verify Sprinkler Sign Off | 11/9/2022 | Approved | JAMES POWERS |
| Final | 11/15/2022 | Partial Inspection | RUSSELL BONVOULOIR |
| BUILDING-Rough-Frame | 11/30/2022 | Approved | RUSSELL BONVOULOIR |
| Final | 11/30/2022 | Partial Inspection | RUSSELL BONVOULOIR |
| Footing/Foundation/Slab | 11/30/2022 | Approved | RUSSELL BONVOULOIR |
| METHANE-Barrier | 11/30/2022 | Approved | RUSSELL BONVOULOIR |
| METHANE-Final | 11/30/2022 | Approved | RUSSELL BONVOULOIR |
| METHANE-Rough | 11/30/2022 | Approved | RUSSELL BONVOULOIR |
| METHANE-Subgrade | 11/30/2022 | Approved | RUSSELL BONVOULOIR |
| Service/Power Release | 11/30/2022 | Conditional Approval | RUSSELL BONVOULOIR |
| Final | 2/9/2023 | Partial Inspection | ERNESTO CORRAL |
| Final | 2/10/2023 | OK to Issue CofO | ERNESTO CORRAL |