2215 S BUNDY DR 104-860 90064

Certificate Information: 2215 S BUNDY DR 104-860 90064

Application / Permit
21010-10000-03137
Plan Check / Job No.
B21LA11834
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
New 8-Story, 290 unit ( ELI (32)) affordable housing apartment to include 5-story Type IIIA apartment over -story Type IA apartments over 1-story Type IA ground floor apartments, parking and amenity space over 2-level Type IA parking basement using TOC Tier 4 incentives.
Permit Issued
Issued on 2/13/2026
Issuing Office
Metro
Current Status
Issued on 2/13/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/6/2021 APPLICANT
Assigned to Plan Check Engineer 7/15/2021 RODOLFO ARIAS
Corrections Issued 7/23/2021 RODOLFO ARIAS
Quality Review Completed 7/27/2021 ALLEN MANALANSAN
Applicant returned to address corrections 8/24/2021 RODOLFO ARIAS
Applicant returned to address corrections 9/14/2021 RODOLFO ARIAS
Applicant returned to address corrections 10/4/2021 RODOLFO ARIAS
Applicant returned to address corrections 10/13/2021 RODOLFO ARIAS
Plan Check Approved 2/11/2026 KEVIN MORALES
Issued 2/13/2026 APPLICANT

Permit Application Clearance Information

Hydrant and Access approval Cleared 1/9/2022 ROBERT DUFF
Trees in Parkway Cleared 8/30/2023 ADALBERTO VERA
Address approval Cleared 9/15/2023 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 9/27/2023 DINAH GARIN
Miscellaneous Cleared 12/6/2023 WALLIE JONG
Permit Cleared 1/26/2024 DINAH GARIN
Encroachment in public way Cleared 1/31/2024 SAUL GARCIA
Low Impact Development (LID) Cleared 9/25/2024 MARTIN FRAGOSO
CPC Cleared 10/9/2024 YINGSHI HUANG
Miscellaneous Cleared 10/9/2024 YINGSHI HUANG
Miscellaneous Cleared 10/9/2024 YINGSHI HUANG
Miscellaneous Cleared 10/9/2024 YINGSHI HUANG
Miscellaneous Cleared 10/9/2024 YINGSHI HUANG
Fire Marshal Fire Life Safety Cleared 10/10/2024 MENOA AGHAJANI
Specific Plan Cleared 10/27/2024 PEDRO AYALA
Specific Plan Cleared 10/27/2024 PEDRO AYALA
Density Bonus 12.22.A.31 Cleared 1/8/2025 ALYSSA FLORES
Construction near power lines Cleared 2/21/2025 RIDWAN HARDY
Work Adjacent to Public Way Cleared 2/25/2025 LARRY LEE
Building over 36-ft Cleared 3/5/2025 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 3/5/2025 CALOSHA APPROVED
Highway dedication Cleared 3/12/2025 KIMBERLY HERNANDEZ
Green Code Cleared 3/14/2025 RODOLFO ARIAS
DAS Clearance Cleared 3/24/2025 ELIZABETH TOMS
Roof/Waste drainage to street Cleared 4/2/2025 DIANA RENTERIA
Sewer availability Cleared 7/9/2025 CELINA MORENO
Specific Plan Cleared 1/15/2026 JULISSA LOPEZ-HODOYAN
Miscellaneous Cleared 2/4/2026 FIPE LEILUA
Miscellaneous Cleared 2/4/2026 FIPE LEILUA
Miscellaneous Cleared 2/4/2026 FIPE LEILUA
Miscellaneous Cleared 2/4/2026 FIPE LEILUA
Site Plan review Cleared 2/4/2026 FIPE LEILUA
ZI Cleared 2/4/2026 FIPE LEILUA

Contact Information

Architect Loh,, Radziah M; Lic. No.: C29367 7411 TERRACE DRIVE      EL CERRITO, CA 94530
Contractor Carmel Construction West Llc; Lic. No.: 1070377-B 1000 SANSOME STREET 1ST FLOOR      SAN FRANCISCO, CA 94111
Engineer Aden,, Mark; Lic. No.: S4779 1224 W. RIVERSIDE AVE., #208      SPOKANE, WA 99201

Inspector Information

DANIEL VARNUM, (310) 914-3914 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

Wood Frame 6/9/2026   
Drywall Nailing 6/9/2026   
Floor/Roof Diaphrgm/Shear Wall 6/9/2026   

Inspection Request History

Light Gage Steel Frame 2/18/2026 Partial Approval DANIEL VARNUM
Deputy Wood Construction 2/24/2026 Conditional Approval DANIEL VARNUM
Deputy Wood Construction 2/25/2026 Conditional Approval DANIEL VARNUM
Deputy Wood Construction 2/26/2026 Conditional Approval DANIEL VARNUM
Deputy Wood Construction 2/27/2026 Conditional Approval DANIEL VARNUM
Deputy Wood Construction 3/2/2026 Conditional Approval DANIEL VARNUM
Deputy Wood Construction 3/3/2026 Conditional Approval DANIEL VARNUM
Deputy Wood Construction 3/4/2026 Conditional Approval DANIEL VARNUM
Deputy Wood Construction 3/5/2026 Conditional Approval DANIEL VARNUM
Drywall Nailing 3/5/2026 Partial Approval DANIEL VARNUM
Deputy Wood Construction 3/6/2026 Conditional Approval DANIEL VARNUM
Deputy Wood Construction 3/9/2026 Conditional Approval PAUL DAVIDSON
Deputy Wood Construction 3/10/2026 Conditional Approval PAUL DAVIDSON
Deputy Wood Construction 3/11/2026 Conditional Approval DANIEL VARNUM
Drywall Nailing 3/11/2026 Partial Approval DANIEL VARNUM
Floor/Roof Diaphrgm/Shear Wall 3/11/2026 Partial Approval DANIEL VARNUM
Deputy Wood Construction 3/12/2026 Conditional Approval DANIEL VARNUM
Deputy Wood Construction 3/13/2026 Conditional Approval DANIEL VARNUM
Deputy Wood Construction 3/17/2026 Conditional Approval DANIEL VARNUM
Deputy Wood Construction 3/18/2026 Conditional Approval DANIEL VARNUM
Deputy Wood Construction 3/19/2026 Conditional Approval DANIEL VARNUM
Deputy Wood Construction 3/20/2026 Conditional Approval DANIEL VARNUM
Deputy Wood Construction 3/24/2026 Conditional Approval DANIEL VARNUM
Drywall Nailing 3/24/2026 Partial Approval DANIEL VARNUM
Floor/Roof Diaphrgm/Shear Wall 3/24/2026 Partial Approval DANIEL VARNUM
Light Gage Steel Frame 3/24/2026 Partial Inspection DANIEL VARNUM
Deputy Wood Construction 3/25/2026 Conditional Approval DANIEL VARNUM
Deputy Wood Construction 3/26/2026 Conditional Approval PAUL DAVIDSON
Drywall Nailing 3/26/2026 Partial Approval PAUL DAVIDSON
Floor/Roof Diaphrgm/Shear Wall 3/26/2026 Partial Approval PAUL DAVIDSON
Deputy Wood Construction 3/27/2026 Conditional Approval PAUL DAVIDSON
Deputy Wood Construction 3/31/2026 Conditional Approval DANIEL VARNUM
Deputy Wood Construction 4/1/2026 Conditional Approval DANIEL VARNUM
Deputy Wood Construction 4/2/2026 Conditional Approval DANIEL VARNUM
Deputy Wood Construction 4/3/2026 Conditional Approval DANIEL VARNUM
Deputy Wood Construction 4/7/2026 Conditional Approval DANIEL VARNUM
Drywall Nailing 4/7/2026 Partial Approval DANIEL VARNUM
Floor/Roof Diaphrgm/Shear Wall 4/7/2026 Partial Approval DANIEL VARNUM
Light Gage Steel Frame 4/7/2026 Not Ready for Inspection DANIEL VARNUM
Deputy Wood Construction 4/8/2026 Conditional Approval DANIEL VARNUM
Deputy Wood Construction 4/9/2026 Conditional Approval DANIEL VARNUM
Deputy Wood Construction 4/10/2026 Conditional Approval DANIEL VARNUM
Deputy Wood Construction 4/13/2026 Conditional Approval DANIEL VARNUM
Deputy Wood Construction 4/14/2026 Conditional Approval DANIEL VARNUM
Deputy Wood Construction 4/15/2026 Conditional Approval DANIEL VARNUM
Deputy Wood Construction 4/16/2026 Conditional Approval DANIEL VARNUM
Deputy Wood Construction 4/17/2026 Conditional Approval DANIEL VARNUM
Drywall Nailing 4/17/2026 Partial Approval DANIEL VARNUM
Light Gage Steel Frame 4/17/2026 Partial Approval DANIEL VARNUM
Wood Frame 4/17/2026 Partial Approval DANIEL VARNUM
Deputy Wood Construction 4/20/2026 Conditional Approval DANIEL VARNUM
Deputy Wood Construction 4/21/2026 Conditional Approval DANIEL VARNUM
Deputy Wood Construction 4/22/2026 Conditional Approval DANIEL VARNUM
Deputy Wood Construction 4/23/2026 Conditional Approval DANIEL VARNUM
Floor/Roof Diaphrgm/Shear Wall 4/23/2026 Partial Approval DANIEL VARNUM
Wood Frame 4/23/2026 Partial Approval DANIEL VARNUM
Deputy Wood Construction 4/24/2026 Conditional Approval PAUL DAVIDSON
Deputy Wood Construction 4/27/2026 Conditional Approval DANIEL VARNUM
Floor/Roof Diaphrgm/Shear Wall 4/27/2026 Partial Approval DANIEL VARNUM
Wood Frame 4/27/2026 Partial Approval DANIEL VARNUM
Deputy Wood Construction 4/28/2026 Conditional Approval DANIEL VARNUM
Deputy Wood Construction 4/29/2026 Conditional Approval DANIEL VARNUM
Deputy Wood Construction 4/30/2026 Conditional Approval DANIEL VARNUM
Deputy Wood Construction 5/1/2026 Conditional Approval DANIEL VARNUM
Deputy Wood Construction 5/4/2026 Conditional Approval DANIEL VARNUM
Drywall Nailing 5/4/2026 Not Ready for Inspection DANIEL VARNUM
Floor/Roof Diaphrgm/Shear Wall 5/4/2026 Partial Approval DANIEL VARNUM
Structural Steel Frame 5/4/2026 Not Ready for Inspection DANIEL VARNUM
Deputy Wood Construction 5/5/2026 Conditional Approval DANIEL VARNUM
Deputy Wood Construction 5/6/2026 Conditional Approval DANIEL VARNUM
Deputy Wood Construction 5/7/2026 Conditional Approval DANIEL VARNUM
Deputy Wood Construction 5/8/2026 Conditional Approval PAUL DAVIDSON
Drywall Nailing 5/8/2026 Partial Approval PAUL DAVIDSON
Deputy Wood Construction 5/11/2026 Conditional Approval DANIEL VARNUM
Drywall Nailing 5/11/2026 Not Ready for Inspection DANIEL VARNUM
Floor/Roof Diaphrgm/Shear Wall 5/11/2026 Partial Approval DANIEL VARNUM
Light Gage Steel Frame 5/11/2026 Not Ready for Inspection DANIEL VARNUM
Deputy Wood Construction 5/12/2026 Conditional Approval DANIEL VARNUM
Deputy Wood Construction 5/13/2026 Conditional Approval DANIEL VARNUM
Deputy Wood Construction 5/14/2026 Conditional Approval DANIEL VARNUM
Drywall Nailing 5/14/2026 Not Ready for Inspection DANIEL VARNUM
Floor/Roof Diaphrgm/Shear Wall 5/14/2026 Partial Approval DANIEL VARNUM
Insulation 5/14/2026 Not Ready for Inspection DANIEL VARNUM
Deputy Wood Construction 5/15/2026 Conditional Approval DANIEL VARNUM
Deputy Wood Construction 5/18/2026 Conditional Approval DANIEL VARNUM
Drywall Nailing 5/18/2026 Partial Approval DANIEL VARNUM
Floor/Roof Diaphrgm/Shear Wall 5/18/2026 Partial Approval DANIEL VARNUM
Wood Frame 5/18/2026 Not Ready for Inspection DANIEL VARNUM
Deputy Wood Construction 5/19/2026 Conditional Approval DANIEL VARNUM
Insulation 5/19/2026 Partial Approval DANIEL VARNUM
Deputy Wood Construction 5/20/2026 Conditional Approval DANIEL VARNUM
Drywall Nailing 5/20/2026 Partial Approval DANIEL VARNUM
Insulation 5/20/2026 Not Ready for Inspection DANIEL VARNUM
Light Gage Steel Frame 5/20/2026 Partial Approval DANIEL VARNUM
Wood Frame 5/20/2026 Partial Approval DANIEL VARNUM
Deputy Wood Construction 5/21/2026 Conditional Approval DANIEL VARNUM
Insulation 5/21/2026 Not Ready for Inspection DANIEL VARNUM
Light Gage Steel Frame 5/21/2026 Partial Approval DANIEL VARNUM
Wood Frame 5/21/2026 Partial Approval DANIEL VARNUM
Deputy Wood Construction 5/22/2026 Conditional Approval PAUL DAVIDSON
Deputy Wood Construction 5/26/2026 Conditional Approval DANIEL VARNUM
Drywall Nailing 5/26/2026 Partial Approval DANIEL VARNUM
Insulation 5/26/2026 Not Ready for Inspection DANIEL VARNUM
Wood Frame 5/26/2026 Partial Approval DANIEL VARNUM
Deputy Wood Construction 5/27/2026 Conditional Approval DANIEL VARNUM
Deputy Wood Construction 5/28/2026 Conditional Approval DANIEL VARNUM
Floor/Roof Diaphrgm/Shear Wall 5/28/2026 Not Ready for Inspection DANIEL VARNUM
Insulation 5/28/2026 Partial Approval DANIEL VARNUM
Wood Frame 5/28/2026 Partial Approval DANIEL VARNUM
Deputy Wood Construction 5/29/2026 Conditional Approval DANIEL VARNUM
Deputy Wood Construction 6/1/2026 Conditional Approval DANIEL ARMENTA
Deputy Wood Construction 6/2/2026 Conditional Approval DANIEL VARNUM
Deputy Wood Construction 6/3/2026 Conditional Approval DANIEL VARNUM
Drywall Nailing 6/3/2026 Not Ready for Inspection DANIEL VARNUM
Floor/Roof Diaphrgm/Shear Wall 6/3/2026 Partial Approval DANIEL VARNUM
Wood Frame 6/3/2026 Not Ready for Inspection DANIEL VARNUM
Deputy Wood Construction 6/4/2026 Conditional Approval DANIEL VARNUM
Deputy Wood Construction 6/5/2026 Conditional Approval PAUL DAVIDSON