2301 S BUNDY DR 1-195 90064

Certificate Information: 2301 S BUNDY DR 1-195 90064

Application / Permit
21010-10000-03136
Plan Check / Job No.
B21LA11833
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
New 7-Story and mezzanine (8-story building per Zoning Code), 195 unit (11% ELI (22)) affordable housing apartment to inculde 5-story Type IIIA apartment over 1-story Type IA apartments over 1-story ground floor apartments, parking and amenity space over 2-level Type IA parking basement using TOC Tier 4 incentives.
Permit Issued
Issued on 1/9/2026
Issuing Office
Metro
Current Status
Issued on 1/9/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/6/2021 APPLICANT
Assigned to Plan Check Engineer 7/15/2021 RODOLFO ARIAS
Corrections Issued 7/23/2021 RODOLFO ARIAS
Quality Review Completed 7/27/2021 ALLEN MANALANSAN
Applicant returned to address corrections 8/24/2021 RODOLFO ARIAS
Applicant returned to address corrections 9/14/2021 RODOLFO ARIAS
Applicant returned to address corrections 10/4/2021 RODOLFO ARIAS
Applicant returned to address corrections 10/13/2021 RODOLFO ARIAS
Applicant returned to address corrections 2/8/2022 RODOLFO ARIAS
Plan Check Approved 11/5/2025 JOE VO
No Progress 12/26/2025 JOE VO
Plan Check Approved 12/26/2025 JOE VO
Issued 1/9/2026 APPLICANT

Permit Application Clearance Information

Hydrant and Access approval Cleared 1/9/2022 ROBERT DUFF
Trees in Parkway Cleared 8/30/2023 ADALBERTO VERA
Address approval Cleared 9/15/2023 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 9/27/2023 DINAH GARIN
Miscellaneous Cleared 12/6/2023 WALLIE JONG
Green Code Cleared 12/7/2023 AARON COSTA
Highway dedication Cleared 12/26/2023 DINAH GARIN
Permit Cleared 1/30/2024 DINAH GARIN
Low Impact Development Cleared 9/28/2024 MARTIN FRAGOSO
Fire Marshal Fire Life Safety Cleared 10/11/2024 WILLIAM JOHNS
Encroachment in public way Cleared 10/15/2024 SAUL GARCIA
Public Swimming Pool approval Cleared 10/21/2024 LACDHS APPROVED
Driveway location Cleared 10/27/2024 PEDRO AYALA
Specific Plan Cleared 10/27/2024 PEDRO AYALA
CPC Cleared 10/30/2024 YINGSHI HUANG
Miscellaneous Cleared 10/30/2024 YINGSHI HUANG
Miscellaneous Cleared 10/30/2024 YINGSHI HUANG
Miscellaneous Cleared 10/30/2024 YINGSHI HUANG
Density Bonus 12.22.A.31 Cleared 1/27/2025 BLAKE BOULIGNY
Work Adjacent to Public Way Cleared 2/25/2025 LARRY LEE
DAS Clearance Cleared 3/12/2025 RODOLFO ARIAS
Construction within easement Cleared 3/26/2025 RIDWAN HARDY
Roof/Waste drainage to street Cleared 4/2/2025 DIANA RENTERIA
Building over 36-ft Cleared 4/21/2025 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 4/21/2025 CALOSHA APPROVED
Sewer availability Cleared 7/9/2025 CARLOS AGUILERA
Specific Plan Cleared 11/24/2025 JULISSA LOPEZ-HODOYAN
Frnt yard landscape/Water mgmt Cleared 12/10/2025 FIPE LEILUA
Opn space landscape/Water mgmt Cleared 12/10/2025 FIPE LEILUA
Site Plan review Cleared 12/10/2025 FIPE LEILUA
ZI Cleared 12/10/2025 FIPE LEILUA

Contact Information

Architect Loh,, Radziah M; Lic. No.: C29367 7411 TERRACE DRIVE      EL CERRITO, CA 94530
Contractor Carmel Construction West Llc; Lic. No.: 1070377-B 1000 SANSOME STREET 1ST FLOOR      SAN FRANCISCO, CA 94111
Engineer Aden,, Mark; Lic. No.: S4779 1224 W. RIVERSIDE AVE., #208      SPOKANE, WA 99201

Inspector Information

DANIEL VARNUM, (310) 914-3914 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

Wood Frame 6/8/2026   
Drywall Nailing 6/8/2026   
Insulation 6/8/2026   

Inspection Request History

Light Gage Steel Frame 1/15/2026 Partial Approval DANIEL VARNUM
Drywall Nailing 1/27/2026 Partial Approval DANIEL VARNUM
Floor/Roof Diaphrgm/Shear Wall 1/27/2026 Partial Approval DANIEL VARNUM
Floor/Roof Diaphrgm/Shear Wall 1/30/2026 Partial Approval DANIEL VARNUM
Footing/Foundation/Slab 2/5/2026 Partial Approval DANIEL VARNUM
Drywall Nailing 2/6/2026 Partial Approval DANIEL VARNUM
Floor/Roof Diaphrgm/Shear Wall 2/6/2026 Partial Approval DANIEL VARNUM
Light Gage Steel Frame 2/6/2026 Partial Approval DANIEL VARNUM
Drywall Nailing 2/17/2026 Not Ready for Inspection DANIEL VARNUM
Floor/Roof Diaphrgm/Shear Wall 2/17/2026 Not Ready for Inspection DANIEL VARNUM
Drywall Nailing 2/20/2026 Partial Approval DANIEL VARNUM
Floor/Roof Diaphrgm/Shear Wall 2/20/2026 Partial Approval DANIEL VARNUM
Drywall Nailing 2/24/2026 Partial Approval DANIEL VARNUM
Light Gage Steel Frame 2/24/2026 Partial Approval DANIEL VARNUM
Drywall Nailing 2/25/2026 Partial Approval DANIEL VARNUM
Drywall Nailing 3/4/2026 Partial Approval DANIEL VARNUM
Floor/Roof Diaphrgm/Shear Wall 3/4/2026 Partial Approval DANIEL VARNUM
Floor/Roof Diaphrgm/Shear Wall 3/5/2026 Partial Approval DANIEL VARNUM
Floor/Roof Diaphrgm/Shear Wall 3/10/2026 Partial Approval PAUL DAVIDSON
Floor/Roof Diaphrgm/Shear Wall 3/11/2026 Not Ready for Inspection DANIEL VARNUM
Floor/Roof Diaphrgm/Shear Wall 3/18/2026 Partial Approval DANIEL VARNUM
Light Gage Steel Frame 3/18/2026 Partial Approval DANIEL VARNUM
Structural Steel Frame 3/18/2026 Partial Approval DANIEL VARNUM
Drywall Nailing 3/20/2026 Partial Inspection DANIEL VARNUM
Floor/Roof Diaphrgm/Shear Wall 3/20/2026 Partial Approval DANIEL VARNUM
Light Gage Steel Frame 3/20/2026 Partial Approval DANIEL VARNUM
Structural Steel Frame 3/20/2026 Partial Inspection DANIEL VARNUM
Floor/Roof Diaphrgm/Shear Wall 3/24/2026 Partial Approval DANIEL VARNUM
Wood Frame 3/24/2026 Partial Approval DANIEL VARNUM
Drywall Nailing 3/26/2026 Partial Approval PAUL DAVIDSON
Floor/Roof Diaphrgm/Shear Wall 3/26/2026 Partial Approval PAUL DAVIDSON
Floor/Roof Diaphrgm/Shear Wall 4/7/2026 Not Ready for Inspection DANIEL VARNUM
Insulation 4/7/2026 Partial Approval DANIEL VARNUM
Light Gage Steel Frame 4/7/2026 Partial Approval DANIEL VARNUM
Drywall Nailing 4/9/2026 Partial Approval DANIEL VARNUM
Floor/Roof Diaphrgm/Shear Wall 4/9/2026 Not Ready for Inspection DANIEL VARNUM
Wood Frame 4/9/2026 Partial Approval DANIEL VARNUM
Drywall Nailing 4/13/2026 Partial Approval DANIEL VARNUM
Insulation 4/13/2026 Not Ready for Inspection DANIEL VARNUM
Wood Frame 4/13/2026 Partial Approval DANIEL VARNUM
Drywall Nailing 4/17/2026 Not Ready for Inspection DANIEL VARNUM
Insulation 4/17/2026 Not Ready for Inspection DANIEL VARNUM
Light Gage Steel Frame 4/17/2026 Partial Approval DANIEL VARNUM
Wood Frame 4/17/2026 Not Ready for Inspection DANIEL VARNUM
Drywall Nailing 4/21/2026 Partial Approval DANIEL VARNUM
Floor/Roof Diaphrgm/Shear Wall 4/21/2026 Partial Approval DANIEL VARNUM
Insulation 4/21/2026 Not Ready for Inspection DANIEL VARNUM
Drywall Nailing 4/23/2026 Not Ready for Inspection DANIEL VARNUM
Floor/Roof Diaphrgm/Shear Wall 4/23/2026 Not Ready for Inspection DANIEL VARNUM
Insulation 4/23/2026 Not Ready for Inspection DANIEL VARNUM
Drywall Nailing 4/27/2026 Partial Approval DANIEL VARNUM
Floor/Roof Diaphrgm/Shear Wall 4/27/2026 Partial Approval DANIEL VARNUM
Insulation 4/27/2026 Corrections Issued DANIEL VARNUM
Drywall Nailing 5/4/2026 Not Ready for Inspection DANIEL VARNUM
Insulation 5/4/2026 Partial Approval DANIEL VARNUM
Wood Frame 5/4/2026 Not Ready for Inspection DANIEL VARNUM
Drywall Nailing 5/5/2026 Partial Approval DANIEL VARNUM
Light Gage Steel Frame 5/5/2026 Partial Approval DANIEL VARNUM
Wood Frame 5/5/2026 Partial Approval DANIEL VARNUM
Drywall Nailing 5/6/2026 Partial Inspection DANIEL VARNUM
Insulation 5/6/2026 Not Ready for Inspection DANIEL VARNUM
Light Gage Steel Frame 5/6/2026 Partial Approval DANIEL VARNUM
Drywall Nailing 5/7/2026 Not Ready for Inspection DANIEL VARNUM
Floor/Roof Diaphrgm/Shear Wall 5/7/2026 Partial Approval DANIEL VARNUM
Light Gage Steel Frame 5/7/2026 Partial Approval DANIEL VARNUM
Drywall Nailing 5/11/2026 Partial Approval DANIEL VARNUM
Floor/Roof Diaphrgm/Shear Wall 5/11/2026 Not Ready for Inspection DANIEL VARNUM
Insulation 5/11/2026 Not Ready for Inspection DANIEL VARNUM
Light Gage Steel Frame 5/11/2026 Partial Approval DANIEL VARNUM
Drywall Nailing 5/12/2026 Partial Approval DANIEL VARNUM
Floor/Roof Diaphrgm/Shear Wall 5/12/2026 Partial Approval DANIEL VARNUM
Insulation 5/12/2026 Partial Approval DANIEL VARNUM
Drywall Nailing 5/14/2026 Partial Approval DANIEL VARNUM
Insulation 5/14/2026 Partial Approval DANIEL VARNUM
Wood Frame 5/14/2026 Partial Approval DANIEL VARNUM
Drywall Nailing 5/18/2026 Not Ready for Inspection DANIEL VARNUM
Floor/Roof Diaphrgm/Shear Wall 5/18/2026 Partial Approval DANIEL VARNUM
Insulation 5/18/2026 Partial Approval DANIEL VARNUM
Light Gage Steel Frame 5/18/2026 Not Ready for Inspection DANIEL VARNUM
Drywall Nailing 5/20/2026 Partial Approval DANIEL VARNUM
Insulation 5/20/2026 Not Ready for Inspection DANIEL VARNUM
Wood Frame 5/20/2026 Partial Approval DANIEL VARNUM
Drywall Nailing 5/21/2026 Not Ready for Inspection DANIEL VARNUM
Insulation 5/21/2026 Not Ready for Inspection DANIEL VARNUM
Wood Frame 5/21/2026 Partial Approval DANIEL VARNUM
Drywall Nailing 5/26/2026 Partial Approval DANIEL VARNUM
Insulation 5/26/2026 Partial Approval DANIEL VARNUM
Light Gage Steel Frame 5/26/2026 Not Ready for Inspection DANIEL VARNUM
Drywall Nailing 5/28/2026 Partial Approval DANIEL VARNUM
Insulation 5/28/2026 Partial Approval DANIEL VARNUM
Drywall Nailing 6/3/2026 Partial Approval DANIEL VARNUM
Insulation 6/3/2026 Partial Approval DANIEL VARNUM
Wood Frame 6/3/2026 Not Ready for Inspection DANIEL VARNUM