2907 E ELM ST 90065

Certificate Information: 2907 E ELM ST 90065

Application / Permit
21010-10000-03134
Plan Check / Job No.
B21LA11822
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 2-STORY (29.5' X 36') DETACHED ADU (929 SF) WITH AN OPEN COURT (133 SF) PER LAMC 12.22 A.33(c)-(d). NO NEW LANDSCAPE OR SITE WORK IS PART OF THIS SCOPE. LID REQUIRED BEFORE C OF O AND/OR FINAL OF PERMIT.
Permit Issued
Issued on 1/4/2022
Issuing Office
Current Status
CofO Issued on 6/3/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/29/2021 APPLICANT
Assigned to Plan Check Engineer 8/5/2021 VIVIAN LAO
Corrections Issued 8/17/2021 VIVIAN LAO
Quality Review Completed 8/25/2021 MICHAEL PEREZ
Applicant returned to address corrections 11/17/2021 VIVIAN LAO
Plan Check Approved 12/13/2021 VIVIAN LAO
Issued 1/4/2022 APPLICANT
Building Plans Picked Up 1/7/2022 APPLICANT
CofO in Progress 5/28/2025 ALIZAH MAYAGOITIA
Permit Finaled 6/3/2025 DEROLD HAUFF
CofO Issued 6/3/2025 DEROLD HAUFF
Permit Finaled 6/3/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 9/2/2021 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 9/7/2021 WALLIE JONG
Sewer availability Cleared 9/7/2021 WALLIE JONG
Specific Plan Cleared 9/22/2021 NASHYA JENSEN
Hydrant and Access approval Cleared 10/13/2021 KURT CORRAL
Supp. Use District POD/CDO/TDO Cleared 11/1/2021 NICOLE SANCHEZ
Roof/Waste drainage to street Cleared 11/8/2021 WALLIE JONG
GPI Written Notices Cleared 12/13/2021 VIVIAN LAO
Grading Pre-Inspection Cleared 12/13/2021 VIVIAN LAO

Contact Information

Contractor Owner-Builder       ,
Engineer Behshid,, Farshid; Lic. No.: S4585 10866 WIMER COUNTRY ROAD      SUNLAND, CA 91040

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/25/2022 Approved OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 2/10/2022 Partial Inspection OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 3/4/2022 Approved OSVALDO PARAMO
Footing/Foundation/Slab 3/4/2022 Approved OSVALDO PARAMO
PLUMBING-Rough 3/4/2022 Partial Approval OSVALDO PARAMO
Wood Frame 4/15/2022 Partial Inspection OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 4/22/2022 Approved OSVALDO PARAMO
ELECTRICAL-Rough 12/21/2022 Partial Approval OSVALDO PARAMO
PLUMBING-Rough 12/21/2022 Not Ready for Inspection OSVALDO PARAMO
ELECTRICAL-Rough 3/30/2023 Approved OSVALDO PARAMO
PLUMBING-Rough 3/30/2023 Approved OSVALDO PARAMO
BUILDING-Rough-Frame 4/26/2023 Approved OSVALDO PARAMO
Green Building Rough 4/26/2023 Approved OSVALDO PARAMO
Interior/Exterior Lathing 4/26/2023 Partial Approval OSVALDO PARAMO
Verify Sprinkler Sign Off 4/26/2023 Approved OSVALDO PARAMO
Insulation 6/7/2023 Corrections Issued ALIZAH MAYAGOITIA
Interior/Exterior Lathing 6/7/2023 Partial Approval ALIZAH MAYAGOITIA
Drywall Nailing 8/7/2023 No Access for Inspection OSVALDO PARAMO
Shower Pan 8/7/2023 No Access for Inspection OSVALDO PARAMO
Drywall Nailing 8/11/2023 Approved JOSH MEISTER
Shower Pan 8/11/2023 Approved JOSH MEISTER
ELECTRICAL-Final 5/9/2025 Approved ALIZAH MAYAGOITIA
HVAC-Final 5/9/2025 Approved ALIZAH MAYAGOITIA
PLUMBING-Final 5/9/2025 Approved ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 5/9/2025 SGSOV Approved ALIZAH MAYAGOITIA
Smoke Detectors 5/9/2025 Approved ALIZAH MAYAGOITIA
Final 5/27/2025 OK to Issue CofO ALIZAH MAYAGOITIA
Green Building Final 5/27/2025 Approved ALIZAH MAYAGOITIA
Service/Power Release 5/27/2025 Approved ALIZAH MAYAGOITIA