8327 N WHEATLAND AVE 91352
Certificate Information: 8327 N WHEATLAND AVE 91352
- Application / Permit
- 21010-10000-03097
- Plan Check / Job No.
- B21LA11698
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW ONE STORY ADU WITH (1) BEDROOM/(1) BATH/ (1) KITCHEN AND (1) LIVING ROOM. SEE COMMENT.
- Permit Issued
- Issued on 4/4/2022
- Issuing Office
- Current Status
- CofO Issued on 11/19/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/24/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/2/2021 | TSE MING HUANG |
| Corrections Issued | 7/3/2021 | TSE MING HUANG |
| Applicant returned to address corrections | 8/23/2021 | ADAM HEGAZI |
| Plan Check Approved | 2/24/2022 | JOSEPH RAFOLS |
| Issued | 4/4/2022 | APPLICANT |
| Building Plans Picked Up | 4/6/2022 | APPLICANT |
| CofO in Progress | 10/21/2022 | DAVID ANDERSON |
| Permit Finaled | 11/19/2022 | MICHAEL SMITH |
| CofO Issued | 11/19/2022 | MICHAEL SMITH |
| Permit Finaled | 11/19/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 7/31/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 8/4/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 8/4/2021 | GABRIEL ROBLES |
| Clean Up Green Up | Cleared | 8/31/2021 | TERRI OSBORNE |
| Hydrant and Access approval | Cleared | 10/19/2021 | KURT CORRAL |
| Low Impact Development | Cleared | 2/3/2022 | SUNG JOON WON |
| Roof/Waste drainage to street | Cleared | 2/11/2022 | AMAAN MALIK |
Contact Information
| Contractor | Next Generation Builders; Lic. No.: 1069728-B | 1858 ECHO PARK AVE LOS ANGELES, CA 90026 |
Inspector Information
| DAVID ANDERSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 4/14/2022 | Approved | MATTHEW NELSON |
| Footing/Foundation/Slab | 4/18/2022 | Approved | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 5/3/2022 | Approved | MATTHEW NELSON |
| ELECTRICAL-Rough | 5/3/2022 | Approved | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 5/3/2022 | Partial Approval | MATTHEW NELSON |
| Green Building Rough | 5/3/2022 | Approved | MATTHEW NELSON |
| HVAC-Rough | 5/3/2022 | Approved | MATTHEW NELSON |
| MERV13>=Rough | 5/3/2022 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 5/3/2022 | Approved | MATTHEW NELSON |
| Verify Sprinkler Sign Off | 5/3/2022 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 5/6/2022 | Conditional Approval | CHRISTOPHER DELLEFIELD |
| Insulation | 5/10/2022 | Approved | DONALD CRICHLOW |
| Drywall Nailing | 5/13/2022 | Approved | WILLIAM WREN |
| Final | 7/18/2022 | Corrections Issued | DAVID ANDERSON |
| Green Building Final | 7/18/2022 | Approved | DAVID ANDERSON |
| MERV13>=Final | 7/18/2022 | Approved | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 7/18/2022 | SGSOV Approved | DAVID ANDERSON |
| Service/Power Release | 7/18/2022 | Not Ready for Inspection | DAVID ANDERSON |
| Smoke Detectors | 7/18/2022 | Approved | DAVID ANDERSON |
| Pre-Inspection | 8/16/2022 | Not Ready for Inspection | DAVID ANDERSON |
| Final | 8/30/2022 | Not Ready for Inspection | DAVID ANDERSON |
| Service/Power Release | 8/30/2022 | Not Ready for Inspection | DAVID ANDERSON |
| Final | 10/20/2022 | OK to Issue CofO | DAVID ANDERSON |
| Service/Power Release | 10/20/2022 | Approved | DAVID ANDERSON |