7709 S BUDLONG AVE 90044

Certificate Information: 7709 S BUDLONG AVE 90044

Application / Permit
21010-10000-03091
Plan Check / Job No.
B21LA11650
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ACCESSORY DWELLING UNIT
Permit Issued
Issued on 2/7/2022
Issuing Office
Current Status
CofO Issued on 3/8/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/22/2021 APPLICANT
Assigned to Plan Check Engineer 6/30/2021 SINA KHOSRAVI
Corrections Issued 7/1/2021 SINA KHOSRAVI
Applicant returned to address corrections 8/25/2021 SINA KHOSRAVI
Applicant returned to address corrections 10/29/2021 RICARDO RAMIREZ
Applicant returned to address corrections 1/8/2022 SAMUEL GONZALEZ
Plan Check Approved 1/11/2022 SAMUEL GONZALEZ
Building Plans Picked Up 1/13/2022 APPLICANT
Issued 2/7/2022 APPLICANT
CofO in Progress 3/7/2023 LILIANA PORTILLO
Permit Finaled 3/8/2023 DEROLD HAUFF
CofO Issued 3/8/2023 DEROLD HAUFF
Permit Finaled 3/8/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/5/2021 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 8/10/2021 STEVE MELGAR
Sewer availability Cleared 8/10/2021 STEVE MELGAR
Low Impact Development Cleared 12/22/2021 JULIAN SUNG
Roof/Waste drainage to street Cleared 12/29/2021 TREVOR QUAN

Contact Information

Contractor Owner-Builder       ,
Engineer Carrillo,, Jesus Eduardo; Lic. No.: C77737 8207 BROOKGREEN RD      DOWNEY, CA 90240

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/14/2022 Corrections Issued LILIANA PORTILLO
Footing/Foundation/Slab 4/25/2022 Corrections Issued LILIANA PORTILLO
Footing/Foundation/Slab 5/2/2022 Approved LILIANA PORTILLO
PLUMBING-Rough 6/27/2022 Corrections Issued LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 6/30/2022 Corrections Issued LILIANA PORTILLO
PLUMBING-Rough 6/30/2022 Approved LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 7/6/2022 Approved LILIANA PORTILLO
Underground Mechanical 7/13/2022 Partial Approval LILIANA PORTILLO
Pre-Inspection 7/28/2022 Partial Inspection LILIANA PORTILLO
Wood Frame 8/5/2022 Partial Inspection LILIANA PORTILLO
ELECTRICAL-Rough 8/9/2022 Corrections Issued LILIANA PORTILLO
HVAC-Rough 8/9/2022 Corrections Issued LILIANA PORTILLO
BUILDING-Rough-Frame 8/22/2022 Corrections Issued LILIANA PORTILLO
ELECTRICAL-Rough 8/22/2022 Conditional Approval LILIANA PORTILLO
HVAC-Rough 8/22/2022 Conditional Approval LILIANA PORTILLO
BUILDING-Rough-Frame 8/30/2022 Approved LILIANA PORTILLO
Green Building Rough 8/30/2022 Approved LILIANA PORTILLO
Verify Sprinkler Sign Off 8/30/2022 Approved LILIANA PORTILLO
Insulation 9/6/2022 Approved LILIANA PORTILLO
Interior/Exterior Lathing 9/6/2022 Partial Approval LILIANA PORTILLO
Drywall Nailing 9/21/2022 Approved LILIANA PORTILLO
Interior/Exterior Lathing 9/21/2022 Approved LILIANA PORTILLO
Shower Pan 9/21/2022 Approved LILIANA PORTILLO
ELECTRICAL-Rough 10/21/2022 Partial Approval JOSEPH MCGARRY
Gas Test 10/21/2022 Partial Approval JOSEPH MCGARRY
Sewer 10/21/2022 Approved JOSEPH MCGARRY
Underground Mechanical 10/21/2022 Approved JOSEPH MCGARRY
Final 12/20/2022 Corrections Issued LILIANA PORTILLO
Green Building Final 12/20/2022 Corrections Issued LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 12/20/2022 SGSOV Not Ready LILIANA PORTILLO
Service/Power Release 12/20/2022 Not Ready for Inspection LILIANA PORTILLO
Smoke Detectors 12/20/2022 Approved LILIANA PORTILLO
ELECTRICAL-Final 1/6/2023 Corrections Issued LILIANA PORTILLO
Final 1/6/2023 Not Ready for Inspection LILIANA PORTILLO
Green Building Final 1/6/2023 Approved LILIANA PORTILLO
HVAC-Final 1/6/2023 Corrections Issued LILIANA PORTILLO
PLUMBING-Final 1/6/2023 Corrections Issued LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 1/6/2023 SGSOV Not Ready LILIANA PORTILLO
Service/Power Release 1/6/2023 Not Ready for Inspection LILIANA PORTILLO
ELECTRICAL-Final 1/24/2023 Corrections Issued LILIANA PORTILLO
Final 1/24/2023 Not Ready for Inspection LILIANA PORTILLO
HVAC-Final 1/24/2023 Not Ready for Inspection LILIANA PORTILLO
PLUMBING-Final 1/24/2023 Approved LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 1/24/2023 SGSOV Approved LILIANA PORTILLO
Service/Power Release 1/24/2023 Not Ready for Inspection LILIANA PORTILLO
ELECTRICAL-Final 1/31/2023 Corrections Issued LILIANA PORTILLO
Final 1/31/2023 Not Ready for Inspection LILIANA PORTILLO
HVAC-Final 1/31/2023 Approved LILIANA PORTILLO
Service/Power Release 1/31/2023 Not Ready for Inspection LILIANA PORTILLO
ELECTRICAL-Final 3/6/2023 Approved LILIANA PORTILLO
Final 3/6/2023 OK to Issue CofO LILIANA PORTILLO
Service/Power Release 3/6/2023 Approved LILIANA PORTILLO