3507 1/2 S BUDLONG AVE 90007
Certificate Information: 3507 1/2 S BUDLONG AVE 90007
- Application / Permit
- 21010-10000-03079
- Plan Check / Job No.
- B21LA11610
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW TWO-STORY (30' X 21'-5") ADU (1048 SF) PER LAMC 12.22 A.33(c)-(d).
- Permit Issued
- Issued on 7/7/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 4/30/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/22/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/29/2021 | VIVIAN LAO |
| Corrections Issued | 8/5/2021 | VIVIAN LAO |
| Quality Review Completed | 8/11/2021 | PRANITA SHAH |
| Applicant returned to address corrections | 3/21/2022 | VIVIAN LAO |
| Building Plans Picked Up | 3/30/2022 | APPLICANT |
| Plan Check Approved | 7/1/2022 | VIVIAN LAO |
| Issued | 7/7/2022 | APPLICANT |
| CofO in Progress | 4/22/2023 | ALEJANDRO DE ARTOLA |
| Permit Finaled | 4/30/2023 | DEROLD HAUFF |
| CofO Issued | 4/30/2023 | DEROLD HAUFF |
| Permit Finaled | 4/30/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 11/5/2021 | AMAAN MALIK |
| ZI | Cleared | 11/15/2021 | KENTON TRINH |
| Sewer availability | Cleared | 1/18/2022 | JEANIE LAM |
| Hydrant and Access approval | Cleared | 1/19/2022 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 2/9/2022 | TA ANH |
| Roof/Waste drainage to street | Cleared | 2/10/2022 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 3/4/2022 | JEANIE LAM |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Singh,, Jasbir; Lic. No.: C38767 | 16194 EASTRIDGE CT CHINO HILLS, CA 91709 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/9/2022 | Approved | SABAS ALONSO |
| Footing/Foundation/Slab | 8/9/2022 | Approved | SABAS ALONSO |
| METHANE-Barrier | 8/9/2022 | Approved | SABAS ALONSO |
| METHANE-Subgrade | 8/9/2022 | Approved | SABAS ALONSO |
| Underground Mechanical | 8/17/2022 | Partial Approval | SABAS ALONSO |
| Wood Frame | 8/17/2022 | Not Ready for Inspection | SABAS ALONSO |
| BUILDING-Rough-Frame | 8/18/2022 | Partial Approval | ALEJANDRO DE ARTOLA |
| Insulation | 8/18/2022 | Partial Approval | ALEJANDRO DE ARTOLA |
| Deputy Wood Construction | 8/19/2022 | Approved | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 8/19/2022 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 8/24/2022 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 10/18/2022 | Partial Approval | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 11/23/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 11/23/2022 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Rough | 11/23/2022 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 11/23/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 11/23/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| METHANE-Rough | 11/23/2022 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 11/23/2022 | Approved | ALEJANDRO DE ARTOLA |
| Insulation | 11/29/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 12/12/2022 | Approved | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 12/12/2022 | Approved | ALEJANDRO DE ARTOLA |
| Gas Test | 2/3/2023 | Partial Approval | ALEJANDRO DE ARTOLA |
| Sewer | 2/3/2023 | Approved | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 2/3/2023 | Approved | ALEJANDRO DE ARTOLA |
| Verify Rec and Parks Fee Memo | 2/3/2023 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 4/11/2023 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 4/11/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 4/11/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Gas Test | 4/11/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 4/11/2023 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 4/11/2023 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 4/11/2023 | Approved | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 4/11/2023 | SGSOV Approved | ALEJANDRO DE ARTOLA |
| Service/Power Release | 4/11/2023 | Approved | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 4/11/2023 | Approved | ALEJANDRO DE ARTOLA |
| Verify Sprinkler Sign Off | 4/11/2023 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 4/13/2023 | Approved | ALEJANDRO DE ARTOLA |
| Final | 4/13/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Gas Test | 4/13/2023 | Approved | ALEJANDRO DE ARTOLA |
| Final | 4/21/2023 | OK to Issue CofO | ALEJANDRO DE ARTOLA |