4563-4563 1/2 W 18TH ST 90019
Certificate Information: 4563-4563 1/2 W 18TH ST 90019
- Application / Permit
- 21010-10000-03076
- Plan Check / Job No.
- B21LA11602
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW 3-STORY DUPLEX WITH ATTACHED 2 CAR GARAGE AT THE FRONT OF THE LOT. 1 OF 2
- Permit Issued
- Issued on 1/6/2022
- Issuing Office
- Current Status
- CofO Issued on 7/18/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/21/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/14/2021 | ZAW HAN |
| Corrections Issued | 8/3/2021 | ZAW HAN |
| Quality Review Completed | 8/4/2021 | KEN GILL |
| Applicant returned to address corrections | 11/22/2021 | ZAW HAN |
| Applicant returned to address corrections | 11/24/2021 | ZAW HAN |
| Applicant returned to address corrections | 11/30/2021 | ZAW HAN |
| Plan Check Approved | 12/15/2021 | ZAW HAN |
| Issued | 1/6/2022 | APPLICANT |
| Building Plans Picked Up | 1/7/2022 | APPLICANT |
| CofO in Progress | 7/7/2023 | CALEB MEISTER |
| Permit Finaled | 7/18/2023 | DEROLD HAUFF |
| CofO Issued | 7/18/2023 | DEROLD HAUFF |
| Permit Finaled | 7/18/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 8/16/2021 | RENZ SORIANO |
| Address approval | Cleared | 8/16/2021 | RENZ SORIANO |
| Highway dedication | Cleared | 8/16/2021 | RENZ SORIANO |
| Permit | Cleared | 8/16/2021 | RENZ SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 8/17/2021 | RENZ SORIANO |
| Sewer availability | Cleared | 8/17/2021 | RENZ SORIANO |
| Low Impact Development | Cleared | 10/25/2021 | MARCO SANCHEZ |
| Roof/Waste drainage to street | Cleared | 10/28/2021 | THAN WIN |
| Frnt yard landscape/Water mgmt | Cleared | 11/17/2021 | DANIEL CORONADO |
| Abandoned oil well | Cleared | 11/18/2021 | RUEL COLE |
| Hydrant and Access approval | Cleared | 11/18/2021 | RUEL COLE |
| Green Code | Cleared | 12/15/2021 | ZAW HAN |
Contact Information
| Contractor | Advanced Construction; Lic. No.: 801955-B | 18841 PASADERO DRIVE TARZANA, CA 91356 |
| Engineer | Mansuri,, Mehran; Lic. No.: C78614 | 14944 HESBY ST SHERMAN OAKS, CA 91403 |
| Engineer | Moughraby,, Ousama; Lic. No.: C91595 | 9744 MAPLE ST BELLFLOWER, CA 90706 |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 2/2/2022 | Partial Approval | STUART CHAPMAN |
| Footing/Foundation/Slab | 3/2/2022 | Corrections Issued | STUART CHAPMAN |
| METHANE-Barrier | 3/2/2022 | Not Ready for Inspection | STUART CHAPMAN |
| METHANE-Subgrade | 3/2/2022 | Corrections Issued | STUART CHAPMAN |
| Footing/Foundation/Slab | 3/16/2022 | Corrections Issued | STUART CHAPMAN |
| METHANE-Barrier | 3/16/2022 | Not Ready for Inspection | STUART CHAPMAN |
| METHANE-Subgrade | 3/16/2022 | Not Ready for Inspection | STUART CHAPMAN |
| Excavation/Setback/Form/Re-Bar | 3/18/2022 | Corrections Issued | STUART CHAPMAN |
| Footing/Foundation/Slab | 4/14/2022 | Approved | STUART CHAPMAN |
| METHANE-Barrier | 4/14/2022 | Approved | STUART CHAPMAN |
| METHANE-Subgrade | 4/14/2022 | Approved | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/2/2022 | Corrections Issued | STUART CHAPMAN |
| Deputy Wood Construction | 6/24/2022 | Approved | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/24/2022 | Partial Approval | STUART CHAPMAN |
| Green Building Rough | 6/24/2022 | Not Ready for Inspection | STUART CHAPMAN |
| METHANE-Rough | 6/24/2022 | Not Ready for Inspection | STUART CHAPMAN |
| Verify Sprinkler Sign Off | 6/24/2022 | Not Ready for Inspection | STUART CHAPMAN |
| Deputy Wood Construction | 8/5/2022 | Approved | STUART CHAPMAN |
| Deputy Wood Construction | 8/9/2022 | Approved | STUART CHAPMAN |
| BUILDING-Rough-Frame | 9/27/2022 | Corrections Issued | STUART CHAPMAN |
| ELECTRICAL-Rough | 9/27/2022 | Corrections Issued | STUART CHAPMAN |
| Green Building Rough | 9/27/2022 | Not Ready for Inspection | STUART CHAPMAN |
| HVAC-Rough | 9/27/2022 | Approved | STUART CHAPMAN |
| METHANE-Rough | 9/27/2022 | Approved | STUART CHAPMAN |
| PLUMBING-Rough | 9/27/2022 | Approved | STUART CHAPMAN |
| Verify Sprinkler Sign Off | 9/27/2022 | Approved | STUART CHAPMAN |
| BUILDING-Rough-Frame | 10/3/2022 | Approved | STUART CHAPMAN |
| ELECTRICAL-Rough | 10/3/2022 | Approved | STUART CHAPMAN |
| HVAC-Rough | 10/3/2022 | Approved | STUART CHAPMAN |
| PLUMBING-Rough | 10/3/2022 | Approved | STUART CHAPMAN |
| BUILDING-Rough-Frame | 10/11/2022 | Approved | STUART CHAPMAN |
| Green Building Rough | 10/11/2022 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 10/11/2022 | Partial Approval | STUART CHAPMAN |
| Drywall Nailing | 10/17/2022 | Not Ready for Inspection | STUART CHAPMAN |
| Green Building Rough | 10/17/2022 | Approved | STUART CHAPMAN |
| Drywall Nailing | 10/18/2022 | Approved | STUART CHAPMAN |
| Green Building Rough | 10/18/2022 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 11/16/2022 | Approved | STUART CHAPMAN |
| Sewer | 2/9/2023 | Approved | CALEB MEISTER |
| Gas Test | 2/17/2023 | Partial Approval | CALEB MEISTER |
| Verify Rec and Parks Fee Memo | 2/17/2023 | Not Ready for Inspection | CALEB MEISTER |
| ELECTRICAL-Final | 3/1/2023 | Not Ready for Inspection | CALEB MEISTER |
| PLUMBING-Final | 3/1/2023 | Not Ready for Inspection | CALEB MEISTER |
| ELECTRICAL-Final | 4/24/2023 | Corrections Issued | JEFFREY MEAD |
| HVAC-Final | 4/24/2023 | Corrections Issued | JEFFREY MEAD |
| PLUMBING-Final | 4/24/2023 | Approved | JEFFREY MEAD |
| Verify Rec and Parks Fee Memo | 4/24/2023 | Corrections Issued | JEFFREY MEAD |
| Final | 5/15/2023 | No Access for Inspection | CALEB MEISTER |
| SGSOV-Seismic Gas S/O Valve | 5/22/2023 | SGSOV Not Ready | CALEB MEISTER |
| Service/Power Release | 7/5/2023 | Approved | CALEB MEISTER |
| Final | 7/7/2023 | OK to Issue CofO | CALEB MEISTER |
| Green Building Final | 7/7/2023 | Approved | CALEB MEISTER |
| SGSOV-Seismic Gas S/O Valve | 7/7/2023 | SGSOV Approved | CALEB MEISTER |
| Smoke Detectors | 7/7/2023 | Approved | CALEB MEISTER |
| Service/Power Release | 7/12/2023 | Approved | CALEB MEISTER |