6062-6062 1/2 E LA PRADA 90042

Certificate Information: 6062-6062 1/2 E LA PRADA 90042

Application / Permit
21010-10000-03028
Plan Check / Job No.
B21LA11429
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
detached 2 STORY 2 ADU with attached storage
Permit Issued
Issued on 8/21/2023
Issuing Office
Metro
Current Status
CofO Issued on 9/12/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/16/2021 APPLICANT
Assigned to Plan Check Engineer 7/22/2021 ARSALAN SHABESTARI
Corrections Issued 8/5/2021 ARSALAN SHABESTARI
Quality Review Completed 8/11/2021 PRANITA SHAH
Building Plans Picked Up 8/24/2021 APPLICANT
Applicant returned to address corrections 3/22/2022 ARSALAN SHABESTARI
Plan Check Approved 5/5/2022 ARSALAN SHABESTARI
Issued 8/21/2023 APPLICANT
CofO in Progress 6/25/2024 ALIZAH MAYAGOITIA
CofO Issued 9/12/2024 RUBEN SALAS
Permit Finaled 9/12/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 9/9/2021 JEANIE LAM
BHO/Hillside ordinance Cleared 9/9/2021 JEANIE LAM
BHO/Hillside ordinance Cleared 9/9/2021 JEANIE LAM
BHO/Hillside ordinance Cleared 9/9/2021 JEANIE LAM
BHO/Hillside ordinance Cleared 9/9/2021 JEANIE LAM
BHO/Hillside ordinance Cleared 9/9/2021 JEANIE LAM
Highway dedication Cleared 9/9/2021 JEANIE LAM
Construction near power lines Cleared 10/12/2021 RIDWAN HARDY
Construction within easement Cleared 10/12/2021 RIDWAN HARDY
Eng Process Fee Ord 176,300 Cleared 12/15/2021 JEANIE LAM
Low Impact Development Cleared 12/15/2021 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 12/15/2021 JEANIE LAM
Sewer availability Cleared 12/15/2021 JEANIE LAM
Grading Pre-Inspection Cleared 12/22/2021 ROBERT HUGHES
Hydrant and Access approval Cleared 3/1/2022 KURT CORRAL
GPI Written Notices Cleared 5/5/2022 ARSALAN SHABESTARI

Contact Information

Contractor Owner-Builder       ,

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/29/2023 Partial Approval CRAIG VAUGHAN
Sewer 9/26/2023 Approved ROY SPAULDING
Excavation/Setback/Form/Re-Bar 10/26/2023 Corrections Issued ROY SPAULDING
Footing/Foundation/Slab 10/26/2023 Partial Approval ROY SPAULDING
PLUMBING-Rough 10/26/2023 Approved ROY SPAULDING
Excavation/Setback/Form/Re-Bar 10/27/2023 Approved BRENDAN MORELLI
Footing/Foundation/Slab 11/7/2023 Approved ROY SPAULDING
PLUMBING-Rough 11/14/2023 Approved ROY SPAULDING
Underground Mechanical 11/14/2023 Not Ready for Inspection ROY SPAULDING
Floor/Roof Diaphrgm/Shear Wall 12/1/2023 Approved ROY SPAULDING
PLUMBING-Rough 12/26/2023 Approved ROY SPAULDING
ELECTRICAL-Rough 1/5/2024 Approved ROY SPAULDING
Floor/Roof Diaphrgm/Shear Wall 1/5/2024 Approved ROY SPAULDING
HVAC-Rough 1/5/2024 Approved ROY SPAULDING
PLUMBING-Rough 1/5/2024 Corrections Issued ROY SPAULDING
BUILDING-Rough-Frame 1/9/2024 Corrections Issued ROY SPAULDING
Floor/Roof Diaphrgm/Shear Wall 1/9/2024 Approved ROY SPAULDING
Green Building Rough 1/9/2024 Approved ROY SPAULDING
PLUMBING-Rough 1/9/2024 Partial Approval ROY SPAULDING
Verify Sprinkler Sign Off 1/9/2024 Approved ROY SPAULDING
PLUMBING-Rough 1/12/2024 Approved AMY COLIN
Insulation 1/18/2024 Approved ROY SPAULDING
Interior/Exterior Lathing 1/18/2024 Approved ROY SPAULDING
Drywall Nailing 1/30/2024 Approved ARTHUR NEGRETE
Interior/Exterior Lathing 2/15/2024 Approved JOSH MEISTER
PLUMBING-Final 3/6/2024 Approved ALIZAH MAYAGOITIA
PLUMBING-Final 3/7/2024 Approved ALIZAH MAYAGOITIA
Underground Mechanical 3/19/2024 Approved ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 4/30/2024 Approved ALIZAH MAYAGOITIA
ELECTRICAL-Final 4/30/2024 Partial Approval ALIZAH MAYAGOITIA
Final 4/30/2024 Corrections Issued ALIZAH MAYAGOITIA
Green Building Final 4/30/2024 Approved ALIZAH MAYAGOITIA
HVAC-Final 4/30/2024 Approved ALIZAH MAYAGOITIA
PLUMBING-Final 4/30/2024 Approved ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 4/30/2024 SGSOV Not Required ALIZAH MAYAGOITIA
Service/Power Release 4/30/2024 Not Ready for Inspection ALIZAH MAYAGOITIA
Smoke Detectors 4/30/2024 Approved ALIZAH MAYAGOITIA
Final 6/12/2024 Not Ready for Inspection ALIZAH MAYAGOITIA
Service/Power Release 6/12/2024 Not Ready for Inspection ALIZAH MAYAGOITIA
ELECTRICAL-Final 6/17/2024 Approved ALIZAH MAYAGOITIA
Final 6/17/2024 Conditional Approval ALIZAH MAYAGOITIA
Service/Power Release 6/17/2024 Approved ALIZAH MAYAGOITIA
Final 6/24/2024 OK to Issue CofO ALIZAH MAYAGOITIA