2631 N BARRANCA ST 90031

Certificate Information: 2631 N BARRANCA ST 90031

Application / Permit
21010-10000-03018
Plan Check / Job No.
B21LA11390
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan Proposed detached accessory dwelling unit per Ordinance
Permit Issued
Issued on 12/17/2021
Issuing Office
Current Status
CofO Issued on 12/5/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/16/2021 APPLICANT
Assigned to Plan Check Engineer 6/17/2021 MONICA RAMIREZ
Corrections Issued 6/18/2021 MONICA RAMIREZ
Applicant returned to address corrections 8/6/2021 MONICA RAMIREZ
Applicant returned to address corrections 10/25/2021 MONICA RAMIREZ
Plan Check Approved 11/24/2021 MONICA RAMIREZ
No Progress 12/2/2021 MONICA RAMIREZ
Plan Check Approved 12/7/2021 MONICA RAMIREZ
Issued 12/17/2021 APPLICANT
CofO in Progress 11/21/2023 OSVALDO PARAMO
CofO in Progress 11/21/2023 OSVALDO PARAMO
CofO Issued 12/5/2023 DEROLD HAUFF
Permit Finaled 12/5/2023 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 7/19/2021 JEANIE LAM
Address approval Cleared 7/23/2021 JEANIE LAM
Sewer availability Cleared 8/2/2021 JEANIE LAM
Hydrant and Access approval Cleared 9/30/2021 KURT CORRAL
Low Impact Development Cleared 11/15/2021 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 11/22/2021 ABEL CASILLAS

Contact Information

Contractor Owner-Builder       ,
Engineer Nagarajan,, Sivaram; Lic. No.: S6349 167 MATISSE CIRCLE      ALISO VIEJO, CA 92656

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/12/2022 Approved OSVALDO PARAMO
Footing/Foundation/Slab 4/12/2022 Corrections Issued OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 4/19/2022 Partial Approval OSVALDO PARAMO
PLUMBING-Rough 4/19/2022 Partial Approval OSVALDO PARAMO
Footing/Foundation/Slab 4/27/2022 Not Ready for Inspection OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 4/28/2022 Approved OSVALDO PARAMO
Footing/Foundation/Slab 4/28/2022 Approved OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 6/20/2022 Corrections Issued OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 7/18/2022 Approved AMY COLIN
ELECTRICAL-Rough 8/16/2022 Approved OSVALDO PARAMO
Insulation 8/16/2022 Not Ready for Inspection OSVALDO PARAMO
PLUMBING-Rough 8/16/2022 Corrections Issued OSVALDO PARAMO
HVAC-Rough 9/8/2022 Approved OSVALDO PARAMO
PLUMBING-Rough 9/8/2022 Approved OSVALDO PARAMO
BUILDING-Rough-Frame 9/13/2022 Approved OSVALDO PARAMO
Green Building Rough 9/13/2022 Approved OSVALDO PARAMO
MERV13>=Rough 9/13/2022 Approved OSVALDO PARAMO
Verify Sprinkler Sign Off 9/13/2022 Approved OSVALDO PARAMO
Interior/Exterior Lathing 9/14/2022 Partial Approval OSVALDO PARAMO
Insulation 9/21/2022 Approved OSVALDO PARAMO
Drywall Nailing 10/13/2022 Approved OSVALDO PARAMO
Interior/Exterior Lathing 10/13/2022 Approved OSVALDO PARAMO
Gas Test 2/23/2023 Approved AMY COLIN
Underground Mechanical 2/23/2023 Partial Approval AMY COLIN
Underground Mechanical 3/8/2023 Approved OSVALDO PARAMO
ELECTRICAL-Final 5/18/2023 Corrections Issued OSVALDO PARAMO
Final 5/18/2023 Not Ready for Inspection OSVALDO PARAMO
Green Building Final 5/18/2023 Approved OSVALDO PARAMO
MERV13>=Final 5/18/2023 Approved OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 5/18/2023 SGSOV Not Ready OSVALDO PARAMO
Service/Power Release 5/18/2023 Not Ready for Inspection OSVALDO PARAMO
Smoke Detectors 5/18/2023 Not Ready for Inspection OSVALDO PARAMO
ELECTRICAL-Final 6/2/2023 Corrections Issued OSVALDO PARAMO
ELECTRICAL-Final 8/16/2023 Not Ready for Inspection OSVALDO PARAMO
ELECTRICAL-Final 9/18/2023 Approved OSVALDO PARAMO
Service/Power Release 9/18/2023 Partial Inspection OSVALDO PARAMO
Final 10/10/2023 Corrections Issued AMY COLIN
SGSOV-Seismic Gas S/O Valve 10/10/2023 SGSOV Not Ready AMY COLIN
Service/Power Release 10/10/2023 Not Ready for Inspection AMY COLIN
Smoke Detectors 10/10/2023 Approved AMY COLIN
Final 11/20/2023 OK to Issue CofO OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 11/20/2023 SGSOV Approved OSVALDO PARAMO
Service/Power Release 11/20/2023 Approved OSVALDO PARAMO