Deputy Reinf. Concrete
|
7/27/2022
|
Conditional Approval
|
ANDREW NAVE
|
|
Footing/Foundation/Slab
|
7/27/2022
|
Not Ready for Inspection
|
CARLOS MATAMOROS
|
|
Excavation/Setback/Form/Re-Bar
|
7/28/2022
|
Partial Approval
|
ANDREW NAVE
|
|
Deputy Reinf. Concrete
|
8/1/2022
|
Conditional Approval
|
ANDREW NAVE
|
|
Footing/Foundation/Slab
|
8/30/2022
|
Not Ready for Inspection
|
JUAN VALENZUELA
|
|
Footing/Foundation/Slab
|
9/1/2022
|
Partial Approval
|
JUAN VALENZUELA
|
|
Underground Mechanical
|
9/13/2022
|
Partial Approval
|
JUAN VALENZUELA
|
|
ELECTRICAL-Rough
|
9/16/2022
|
Partial Inspection
|
JUAN VALENZUELA
|
|
Footing/Foundation/Slab
|
9/27/2022
|
Partial Approval
|
JUAN VALENZUELA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/3/2022
|
Corrections Issued
|
JUAN VALENZUELA
|
|
Deputy Wood Construction
|
11/9/2022
|
Conditional Approval
|
JUAN VALENZUELA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/14/2022
|
Partial Approval
|
KENNETH NAGLE
|
|
Footing/Foundation/Slab
|
4/10/2023
|
Partial Approval
|
KEVIN SARGSYAN
|
|
Excavation/Setback/Form/Re-Bar
|
4/20/2023
|
Partial Approval
|
KEVIN SARGSYAN
|
|
Footing/Foundation/Slab
|
4/20/2023
|
Partial Approval
|
KEVIN SARGSYAN
|
|
Footing/Foundation/Slab
|
5/3/2023
|
Partial Approval
|
KEVIN SARGSYAN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/7/2023
|
Corrections Issued
|
KEVIN SARGSYAN
|
|
Underground Mechanical
|
7/10/2023
|
Partial Approval
|
JEREMY TODD
|
|
Footing/Foundation/Slab
|
7/17/2023
|
Corrections Issued
|
KEVIN SARGSYAN
|
|
Footing/Foundation/Slab
|
7/19/2023
|
Corrections Issued
|
KEVIN SARGSYAN
|
|
Excavation/Setback/Form/Re-Bar
|
7/20/2023
|
Partial Approval
|
KEVIN SARGSYAN
|
|
Footing/Foundation/Slab
|
7/25/2023
|
No Access for Inspection
|
KEVIN SARGSYAN
|
|
Excavation/Setback/Form/Re-Bar
|
7/26/2023
|
Partial Approval
|
KEVIN SARGSYAN
|
|
Footing/Foundation/Slab
|
7/28/2023
|
Not Ready for Inspection
|
KEVIN SARGSYAN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/2/2023
|
Partial Approval
|
KEVIN SARGSYAN
|
|
Footing/Foundation/Slab
|
8/10/2023
|
Partial Approval
|
KEVIN SARGSYAN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
9/1/2023
|
Partial Approval
|
KEVIN SARGSYAN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
9/12/2023
|
Not Ready for Inspection
|
ARAM AVEDISIAN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
9/15/2023
|
Partial Approval
|
ARAM AVEDISIAN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
10/13/2023
|
Corrections Issued
|
KEVIN SARGSYAN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
10/17/2023
|
Not Ready for Inspection
|
KEVIN SARGSYAN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
10/18/2023
|
Corrections Issued
|
ARAM AVEDISIAN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
10/20/2023
|
Partial Approval
|
ARAM AVEDISIAN
|
|
Pre-Inspection
|
11/2/2023
|
Partial Inspection
|
ARAM AVEDISIAN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/8/2023
|
Not Ready for Inspection
|
CARLOS MATAMOROS
|
|
Structural Steel Frame
|
11/8/2023
|
Not Ready for Inspection
|
CARLOS MATAMOROS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/13/2023
|
Corrections Issued
|
BRENDAN LOONEY
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/14/2023
|
Approved
|
KEVIN SARGSYAN
|
|
Interior/Exterior Lathing
|
11/20/2023
|
Not Ready for Inspection
|
KEVIN SARGSYAN
|
|
Interior/Exterior Lathing
|
11/21/2023
|
Not Ready for Inspection
|
KEVIN SARGSYAN
|
|
Interior/Exterior Lathing
|
11/22/2023
|
Partial Approval
|
KENNETH NAGLE
|
|
ELECTRICAL-Rough
|
12/8/2023
|
Not Ready for Inspection
|
KEVIN SARGSYAN
|
|
ELECTRICAL-Rough
|
12/20/2023
|
Partial Approval
|
KEVIN SARGSYAN
|
|
Footing/Foundation/Slab
|
3/8/2024
|
Partial Approval
|
ARAM AVEDISIAN
|
|
PLUMBING-Rough
|
4/2/2024
|
Approved
|
ARAM AVEDISIAN
|
|
HVAC-Rough
|
4/5/2024
|
Corrections Issued
|
KEVIN SARGSYAN
|
|
HVAC-Rough
|
4/8/2024
|
Not Ready for Inspection
|
KEVIN SARGSYAN
|
|
HVAC-Rough
|
4/10/2024
|
Approved
|
EVAN COOPER
|
|
BUILDING-Rough-Frame
|
4/26/2024
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Deputy Wood Construction
|
4/26/2024
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
FLOOD-Proofing Certificate
|
4/26/2024
|
Approved
|
CHRISTOPHER WILSON
|
|
Green Building Rough
|
4/26/2024
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
Verify Sprinkler Sign Off
|
4/26/2024
|
Approved
|
CHRISTOPHER WILSON
|
|
BUILDING-Rough-Frame
|
4/29/2024
|
Approved
|
ARAM AVEDISIAN
|
|
ELECTRICAL-Rough
|
4/29/2024
|
Approved
|
ARAM AVEDISIAN
|
|
Green Building Rough
|
4/29/2024
|
Approved
|
ARAM AVEDISIAN
|
|
Insulation
|
5/9/2024
|
Corrections Issued
|
KEVIN SARGSYAN
|
|
Insulation
|
5/13/2024
|
Approved
|
SEAN HAUPT
|
|
Interior/Exterior Lathing
|
5/20/2024
|
Approved
|
KEVIN SARGSYAN
|
|
Drywall Nailing
|
5/28/2024
|
Partial Approval
|
KEVIN SARGSYAN
|
|
Drywall Nailing
|
5/30/2024
|
Approved
|
KENNETH NAGLE
|
|
Sewer
|
7/15/2024
|
Approved
|
ARAM AVEDISIAN
|
|
ELECTRICAL-Final
|
11/1/2024
|
Not Ready for Inspection
|
ARAM AVEDISIAN
|
|
Gas Test
|
11/4/2024
|
Not Ready for Inspection
|
ARAM AVEDISIAN
|
|
PLUMBING-Rough
|
11/4/2024
|
Not Ready for Inspection
|
ARAM AVEDISIAN
|
|
Underground Mechanical
|
11/8/2024
|
Corrections Issued
|
BOBBY KEY
|
|
Underground Mechanical
|
11/12/2024
|
Approved
|
JESUS RODRIGUEZ
|
|
ELECTRICAL-Final
|
2/6/2025
|
Corrections Issued
|
KEVIN SARGSYAN
|
|
HVAC-Final
|
2/7/2025
|
Not Ready for Inspection
|
KEVIN SARGSYAN
|
|
PLUMBING-Final
|
2/7/2025
|
Not Ready for Inspection
|
KEVIN SARGSYAN
|
|
ELECTRICAL-Final
|
2/10/2025
|
Approved
|
KEVIN SARGSYAN
|
|
HVAC-Final
|
2/10/2025
|
Corrections Issued
|
KEVIN SARGSYAN
|
|
Footing/Foundation/Slab
|
2/12/2025
|
Approved
|
KEVIN SARGSYAN
|
|
Green Building Final
|
2/12/2025
|
Approved
|
KEVIN SARGSYAN
|
|
HVAC-Final
|
2/12/2025
|
Not Ready for Inspection
|
KEVIN SARGSYAN
|
|
SGSOV-Seismic Gas S/O Valve
|
2/12/2025
|
SGSOV Approved
|
KEVIN SARGSYAN
|
|
Smoke Detectors
|
2/12/2025
|
Approved
|
KEVIN SARGSYAN
|
|
HVAC-Final
|
2/14/2025
|
Approved
|
KEVIN SARGSYAN
|
|
PLUMBING-Final
|
2/14/2025
|
Not Ready for Inspection
|
KEVIN SARGSYAN
|
|
Final
|
2/18/2025
|
Corrections Issued
|
JESUS RODRIGUEZ
|
|
PLUMBING-Final
|
2/18/2025
|
Approved
|
JESUS RODRIGUEZ
|
|
Service/Power Release
|
2/18/2025
|
Approved
|
JESUS RODRIGUEZ
|
|
Final
|
2/28/2025
|
Not Ready for Inspection
|
KEVIN SARGSYAN
|
|
Final
|
3/5/2025
|
OK to Issue CofO
|
KEVIN SARGSYAN
|