10924 N WOODWARD AVE 91040
Certificate Information: 10924 N WOODWARD AVE 91040
- Application / Permit
- 21010-10000-02979
- Plan Check / Job No.
- B21LA11262
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSED 1-STORY A.D.U. PER ORDINANCE AT REAR OF LOT. CONSTRUCTION PER WFPP.
- Permit Issued
- Issued on 1/24/2022
- Issuing Office
- Current Status
- CofO Issued on 8/7/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/16/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/22/2021 | LAWRENCE QUIRANTE |
| Corrections Issued | 6/23/2021 | LAWRENCE QUIRANTE |
| Applicant returned to address corrections | 7/23/2021 | RICARDO RAMIREZ |
| Applicant returned to address corrections | 1/11/2022 | LAWRENCE QUIRANTE |
| Plan Check Approved | 1/21/2022 | FERNANDO FLORES |
| Issued | 1/24/2022 | APPLICANT |
| Building Plans Picked Up | 1/25/2022 | APPLICANT |
| CofO in Progress | 8/1/2024 | GREGG CUMMINGS |
| Permit Finaled | 8/7/2024 | RUBEN SALAS |
| CofO Issued | 8/7/2024 | RUBEN SALAS |
| Permit Finaled | 8/7/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 6/30/2021 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 6/30/2021 | DAGOVERTO GUERRERO |
| Roof/Waste drainage to street | Cleared | 6/30/2021 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 6/30/2021 | DAGOVERTO GUERRERO |
| Grading Pre-Inspection | Cleared | 7/9/2021 | TIMOTHY POWELL |
| Low Impact Development | Cleared | 1/3/2022 | ANDRES COVARRUBIAS |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/27/2022 | Partial Inspection | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 2/27/2023 | SGSOV Not Ready | WILLIAM WREN |
| Footing/Foundation/Slab | 3/2/2023 | Partial Approval | MATTHEW NELSON |
| PLUMBING-Rough | 3/9/2023 | Partial Approval | WILLIAM WREN |
| Excavation/Setback/Form/Re-Bar | 3/17/2023 | Approved | WILLIAM WREN |
| ELECTRICAL-Rough | 5/9/2023 | Approved | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 5/9/2023 | Approved | WILLIAM WREN |
| HVAC-Rough | 5/9/2023 | Corrections Issued | WILLIAM WREN |
| PLUMBING-Rough | 5/9/2023 | Approved | WILLIAM WREN |
| BUILDING-Rough-Frame | 6/5/2023 | Approved | WILLIAM WREN |
| ELECTRICAL-Rough | 6/5/2023 | Not Ready for Inspection | WILLIAM WREN |
| Green Building Rough | 6/5/2023 | Approved | WILLIAM WREN |
| HVAC-Rough | 6/5/2023 | Approved | WILLIAM WREN |
| PLUMBING-Rough | 6/5/2023 | Not Ready for Inspection | WILLIAM WREN |
| Verify Sprinkler Sign Off | 6/5/2023 | Approved | WILLIAM WREN |
| Insulation | 6/27/2023 | Approved | WILLIAM WREN |
| Interior/Exterior Lathing | 6/27/2023 | Partial Approval | WILLIAM WREN |
| Drywall Nailing | 7/11/2023 | Approved | MATTHEW NELSON |
| ELECTRICAL-Final | 1/24/2024 | Approved | MATTHEW NELSON |
| Final | 1/24/2024 | Corrections Issued | MATTHEW NELSON |
| Footing/Foundation/Slab | 1/24/2024 | Approved | MATTHEW NELSON |
| Green Building Final | 1/24/2024 | Corrections Issued | MATTHEW NELSON |
| HVAC-Final | 1/24/2024 | Corrections Issued | MATTHEW NELSON |
| PLUMBING-Final | 1/24/2024 | Corrections Issued | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 1/24/2024 | SGSOV Not Ready | MATTHEW NELSON |
| Service/Power Release | 1/24/2024 | Not Ready for Inspection | MATTHEW NELSON |
| Smoke Detectors | 1/24/2024 | Approved | MATTHEW NELSON |
| Final | 4/4/2024 | Corrections Issued | WILLIAM WREN |
| Green Building Final | 4/4/2024 | Approved | WILLIAM WREN |
| SGSOV-Seismic Gas S/O Valve | 4/4/2024 | SGSOV Approved | WILLIAM WREN |
| Service/Power Release | 4/4/2024 | Approved | WILLIAM WREN |
| Final | 6/10/2024 | Corrections Issued | WILLIAM WREN |
| Final | 7/31/2024 | OK to Issue CofO | GREGG CUMMINGS |