10924 N WOODWARD AVE 91040

Certificate Information: 10924 N WOODWARD AVE 91040

Application / Permit
21010-10000-02979
Plan Check / Job No.
B21LA11262
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSED 1-STORY A.D.U. PER ORDINANCE AT REAR OF LOT. CONSTRUCTION PER WFPP.
Permit Issued
Issued on 1/24/2022
Issuing Office
Current Status
CofO Issued on 8/7/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/16/2021 APPLICANT
Assigned to Plan Check Engineer 6/22/2021 LAWRENCE QUIRANTE
Corrections Issued 6/23/2021 LAWRENCE QUIRANTE
Applicant returned to address corrections 7/23/2021 RICARDO RAMIREZ
Applicant returned to address corrections 1/11/2022 LAWRENCE QUIRANTE
Plan Check Approved 1/21/2022 FERNANDO FLORES
Issued 1/24/2022 APPLICANT
Building Plans Picked Up 1/25/2022 APPLICANT
CofO in Progress 8/1/2024 GREGG CUMMINGS
Permit Finaled 8/7/2024 RUBEN SALAS
CofO Issued 8/7/2024 RUBEN SALAS
Permit Finaled 8/7/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 6/30/2021 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 6/30/2021 DAGOVERTO GUERRERO
Roof/Waste drainage to street Cleared 6/30/2021 DAGOVERTO GUERRERO
Sewer availability Cleared 6/30/2021 DAGOVERTO GUERRERO
Grading Pre-Inspection Cleared 7/9/2021 TIMOTHY POWELL
Low Impact Development Cleared 1/3/2022 ANDRES COVARRUBIAS

Contact Information

Contractor Owner-Builder       ,

Inspector Information

NICHOLAS TROWBRIDGE, (818) 374-1174 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/27/2022 Partial Inspection MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 2/27/2023 SGSOV Not Ready WILLIAM WREN
Footing/Foundation/Slab 3/2/2023 Partial Approval MATTHEW NELSON
PLUMBING-Rough 3/9/2023 Partial Approval WILLIAM WREN
Excavation/Setback/Form/Re-Bar 3/17/2023 Approved WILLIAM WREN
ELECTRICAL-Rough 5/9/2023 Approved WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 5/9/2023 Approved WILLIAM WREN
HVAC-Rough 5/9/2023 Corrections Issued WILLIAM WREN
PLUMBING-Rough 5/9/2023 Approved WILLIAM WREN
BUILDING-Rough-Frame 6/5/2023 Approved WILLIAM WREN
ELECTRICAL-Rough 6/5/2023 Not Ready for Inspection WILLIAM WREN
Green Building Rough 6/5/2023 Approved WILLIAM WREN
HVAC-Rough 6/5/2023 Approved WILLIAM WREN
PLUMBING-Rough 6/5/2023 Not Ready for Inspection WILLIAM WREN
Verify Sprinkler Sign Off 6/5/2023 Approved WILLIAM WREN
Insulation 6/27/2023 Approved WILLIAM WREN
Interior/Exterior Lathing 6/27/2023 Partial Approval WILLIAM WREN
Drywall Nailing 7/11/2023 Approved MATTHEW NELSON
ELECTRICAL-Final 1/24/2024 Approved MATTHEW NELSON
Final 1/24/2024 Corrections Issued MATTHEW NELSON
Footing/Foundation/Slab 1/24/2024 Approved MATTHEW NELSON
Green Building Final 1/24/2024 Corrections Issued MATTHEW NELSON
HVAC-Final 1/24/2024 Corrections Issued MATTHEW NELSON
PLUMBING-Final 1/24/2024 Corrections Issued MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 1/24/2024 SGSOV Not Ready MATTHEW NELSON
Service/Power Release 1/24/2024 Not Ready for Inspection MATTHEW NELSON
Smoke Detectors 1/24/2024 Approved MATTHEW NELSON
Final 4/4/2024 Corrections Issued WILLIAM WREN
Green Building Final 4/4/2024 Approved WILLIAM WREN
SGSOV-Seismic Gas S/O Valve 4/4/2024 SGSOV Approved WILLIAM WREN
Service/Power Release 4/4/2024 Approved WILLIAM WREN
Final 6/10/2024 Corrections Issued WILLIAM WREN
Final 7/31/2024 OK to Issue CofO GREGG CUMMINGS