804-806 E 76TH PL 90001
Certificate Information: 804-806 E 76TH PL 90001
- Application / Permit
- 21010-10000-02978
- Plan Check / Job No.
- B21LA11249
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW 2-STORY DUPLEX WITH ATTACHED 1-CAR GARAGE AT FRONT AND 2-CAR GARAGE AT REAR
- Permit Issued
- Issued on 11/11/2021
- Issuing Office
- Current Status
- CofO Issued on 5/24/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/29/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/22/2021 | DANIEL YIP |
| Corrections Issued | 7/26/2021 | DANIEL YIP |
| Quality Review Completed | 8/3/2021 | JASON HEALEY |
| Plan Check Approved | 10/28/2021 | DANIEL YIP |
| Issued | 11/11/2021 | APPLICANT |
| Building Plans Picked Up | 11/12/2021 | APPLICANT |
| CofO in Progress | 5/17/2022 | LILIANA PORTILLO |
| CofO in Progress | 5/19/2022 | JOAQUIN GREENOUGH |
| CofO in Progress | 5/20/2022 | LILIANA PORTILLO |
| Permit Finaled | 5/24/2022 | DEROLD HAUFF |
| CofO Issued | 5/24/2022 | DEROLD HAUFF |
| Permit Finaled | 5/24/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 8/23/2021 | STEVE MELGAR |
| Permit | Cleared | 8/23/2021 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 8/31/2021 | STEVE MELGAR |
| Sewer availability | Cleared | 8/31/2021 | STEVE MELGAR |
| Trees in Parkway | Cleared | 9/2/2021 | JOHN KIM |
| Low Impact Development | Cleared | 9/22/2021 | MARCO SANCHEZ |
| Roof/Waste drainage to street | Cleared | 9/23/2021 | CELINA MORENO |
| Hydrant and Access approval | Cleared | 10/14/2021 | ROBERT DUFF |
Contact Information
| Contractor | K N Consulting Inc; Lic. No.: 993102-B | P O BOX 410 SUNSET BEACH, CA 90742 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/20/2021 | Partial Approval | ALEJANDRO DE ARTOLA |
| Deputy Reinf. Concrete | 12/22/2021 | Conditional Approval | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 1/4/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Sewer | 1/4/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 1/4/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Wood Frame | 1/4/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 1/10/2022 | Partial Approval | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 1/10/2022 | Partial Approval | ALEJANDRO DE ARTOLA |
| Sewer | 1/10/2022 | Approved | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 1/10/2022 | Approved | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 1/13/2022 | Partial Approval | ALEJANDRO DE ARTOLA |
| Insulation | 1/13/2022 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 1/21/2022 | Partial Approval | ALEJANDRO DE ARTOLA |
| Deputy Wood Construction | 2/9/2022 | No Access for Inspection | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 2/11/2022 | Approved | ALIZAH MAYAGOITIA |
| HVAC-Rough | 2/22/2022 | Approved | LILIANA PORTILLO |
| PLUMBING-Rough | 2/22/2022 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 2/23/2022 | Corrections Issued | LILIANA PORTILLO |
| ELECTRICAL-Rough | 2/23/2022 | Approved | LILIANA PORTILLO |
| Green Building Rough | 2/23/2022 | Approved | LILIANA PORTILLO |
| Verify Sprinkler Sign Off | 2/23/2022 | Corrections Issued | LILIANA PORTILLO |
| Insulation | 3/1/2022 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 3/1/2022 | Partial Approval | LILIANA PORTILLO |
| Drywall Nailing | 3/9/2022 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 3/29/2022 | Partial Approval | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 4/21/2022 | Corrections Issued | LILIANA PORTILLO |
| ELECTRICAL-Final | 5/3/2022 | Partial Approval | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 5/12/2022 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Final | 5/12/2022 | Approved | LILIANA PORTILLO |
| Final | 5/12/2022 | Corrections Issued | LILIANA PORTILLO |
| Footing/Foundation/Slab | 5/12/2022 | Approved | LILIANA PORTILLO |
| Gas Test | 5/12/2022 | Approved | LILIANA PORTILLO |
| Green Building Final | 5/12/2022 | Approved | LILIANA PORTILLO |
| HVAC-Final | 5/12/2022 | Approved | LILIANA PORTILLO |
| PLUMBING-Final | 5/12/2022 | Approved | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 5/12/2022 | SGSOV Approved | LILIANA PORTILLO |
| Service/Power Release | 5/12/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| Smoke Detectors | 5/12/2022 | Approved | LILIANA PORTILLO |
| Verify Sprinkler Sign Off | 5/12/2022 | Approved | LILIANA PORTILLO |
| Final | 5/16/2022 | Conditional Approval | LILIANA PORTILLO |
| Service/Power Release | 5/16/2022 | Approved | LILIANA PORTILLO |
| Final | 5/19/2022 | OK to Issue CofO | LILIANA PORTILLO |
| Service/Power Release | 5/19/2022 | Approved | LILIANA PORTILLO |