804-806 E 76TH PL 90001

Certificate Information: 804-806 E 76TH PL 90001

Application / Permit
21010-10000-02978
Plan Check / Job No.
B21LA11249
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW 2-STORY DUPLEX WITH ATTACHED 1-CAR GARAGE AT FRONT AND 2-CAR GARAGE AT REAR
Permit Issued
Issued on 11/11/2021
Issuing Office
Current Status
CofO Issued on 5/24/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/29/2021 APPLICANT
Assigned to Plan Check Engineer 7/22/2021 DANIEL YIP
Corrections Issued 7/26/2021 DANIEL YIP
Quality Review Completed 8/3/2021 JASON HEALEY
Plan Check Approved 10/28/2021 DANIEL YIP
Issued 11/11/2021 APPLICANT
Building Plans Picked Up 11/12/2021 APPLICANT
CofO in Progress 5/17/2022 LILIANA PORTILLO
CofO in Progress 5/19/2022 JOAQUIN GREENOUGH
CofO in Progress 5/20/2022 LILIANA PORTILLO
Permit Finaled 5/24/2022 DEROLD HAUFF
CofO Issued 5/24/2022 DEROLD HAUFF
Permit Finaled 5/24/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/23/2021 STEVE MELGAR
Permit Cleared 8/23/2021 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 8/31/2021 STEVE MELGAR
Sewer availability Cleared 8/31/2021 STEVE MELGAR
Trees in Parkway Cleared 9/2/2021 JOHN KIM
Low Impact Development Cleared 9/22/2021 MARCO SANCHEZ
Roof/Waste drainage to street Cleared 9/23/2021 CELINA MORENO
Hydrant and Access approval Cleared 10/14/2021 ROBERT DUFF

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B P O BOX 410      SUNSET BEACH, CA 90742

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/20/2021 Partial Approval ALEJANDRO DE ARTOLA
Deputy Reinf. Concrete 12/22/2021 Conditional Approval JOAQUIN GREENOUGH
PLUMBING-Rough 1/4/2022 Corrections Issued ALEJANDRO DE ARTOLA
Sewer 1/4/2022 Corrections Issued ALEJANDRO DE ARTOLA
Underground Mechanical 1/4/2022 Corrections Issued ALEJANDRO DE ARTOLA
Wood Frame 1/4/2022 Corrections Issued ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 1/10/2022 Partial Approval ALEJANDRO DE ARTOLA
PLUMBING-Rough 1/10/2022 Partial Approval ALEJANDRO DE ARTOLA
Sewer 1/10/2022 Approved ALEJANDRO DE ARTOLA
Underground Mechanical 1/10/2022 Approved ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 1/13/2022 Partial Approval ALEJANDRO DE ARTOLA
Insulation 1/13/2022 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 1/21/2022 Partial Approval ALEJANDRO DE ARTOLA
Deputy Wood Construction 2/9/2022 No Access for Inspection ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 2/11/2022 Approved ALIZAH MAYAGOITIA
HVAC-Rough 2/22/2022 Approved LILIANA PORTILLO
PLUMBING-Rough 2/22/2022 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 2/23/2022 Corrections Issued LILIANA PORTILLO
ELECTRICAL-Rough 2/23/2022 Approved LILIANA PORTILLO
Green Building Rough 2/23/2022 Approved LILIANA PORTILLO
Verify Sprinkler Sign Off 2/23/2022 Corrections Issued LILIANA PORTILLO
Insulation 3/1/2022 Approved LILIANA PORTILLO
Interior/Exterior Lathing 3/1/2022 Partial Approval LILIANA PORTILLO
Drywall Nailing 3/9/2022 Approved LILIANA PORTILLO
Interior/Exterior Lathing 3/29/2022 Partial Approval ALEJANDRO DE ARTOLA
ELECTRICAL-Final 4/21/2022 Corrections Issued LILIANA PORTILLO
ELECTRICAL-Final 5/3/2022 Partial Approval LILIANA PORTILLO
BUILDING-Rough-Frame 5/12/2022 Approved LILIANA PORTILLO
ELECTRICAL-Final 5/12/2022 Approved LILIANA PORTILLO
Final 5/12/2022 Corrections Issued LILIANA PORTILLO
Footing/Foundation/Slab 5/12/2022 Approved LILIANA PORTILLO
Gas Test 5/12/2022 Approved LILIANA PORTILLO
Green Building Final 5/12/2022 Approved LILIANA PORTILLO
HVAC-Final 5/12/2022 Approved LILIANA PORTILLO
PLUMBING-Final 5/12/2022 Approved LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 5/12/2022 SGSOV Approved LILIANA PORTILLO
Service/Power Release 5/12/2022 Not Ready for Inspection LILIANA PORTILLO
Smoke Detectors 5/12/2022 Approved LILIANA PORTILLO
Verify Sprinkler Sign Off 5/12/2022 Approved LILIANA PORTILLO
Final 5/16/2022 Conditional Approval LILIANA PORTILLO
Service/Power Release 5/16/2022 Approved LILIANA PORTILLO
Final 5/19/2022 OK to Issue CofO LILIANA PORTILLO
Service/Power Release 5/19/2022 Approved LILIANA PORTILLO