1533 1/2 S 4TH AVE 90019

Certificate Information: 1533 1/2 S 4TH AVE 90019

Application / Permit
21010-10000-02971
Plan Check / Job No.
B21LA11235
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 1 STORY ADU PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 4/21/2022
Issuing Office
Current Status
CofO Issued on 7/10/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/15/2021 APPLICANT
Assigned to Plan Check Engineer 7/22/2021 KHEDER ALRAZAA
Corrections Issued 7/27/2021 KHEDER ALRAZAA
Quality Review Completed 8/5/2021 JASON HEALEY
Applicant returned to address corrections 3/11/2022 KHEDER ALRAZAA
Applicant returned to address corrections 3/22/2022 KHEDER ALRAZAA
Plan Check Approved 4/20/2022 KHEDER ALRAZAA
Plan Check Approved 4/21/2022 STELLA SARGSYAN
Issued 4/21/2022 APPLICANT
Building Plans Picked Up 4/27/2022 APPLICANT
CofO in Progress 4/8/2024 ARTHUR NEGRETE
No Progress 4/22/2024 SCOTT FINNILA
CofO in Progress 4/22/2024 SCOTT FINNILA
CofO Issued 7/10/2024 DEROLD HAUFF
Permit Finaled 7/10/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 10/20/2021 AMAAN MALIK
Eng Process Fee Ord 176,300 Cleared 10/22/2021 AMAAN MALIK
Sewer availability Cleared 10/22/2021 AMAAN MALIK
Low Impact Development Cleared 1/13/2022 MARCO SANCHEZ
Roof/Waste drainage to street Cleared 2/1/2022 AMAAN MALIK
Community Plan Implem. Overlay Cleared 3/16/2022 KYLE WINSTON

Contact Information

Contractor Simcity Construction Inc; Lic. No.: 1027407-B 3350 W OLYMOIC BLVD #202      LOS ANGELES, CA 90019

Inspector Information

WILLIAM SIERRA, (213) 202-3122 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/30/2022 Corrections Issued KATHRYN BUTTERWORTH
METHANE-Subgrade 6/30/2022 Not Ready for Inspection KATHRYN BUTTERWORTH
METHANE-Subgrade 1/12/2023 Approved KATHRYN BUTTERWORTH
PLUMBING-Rough 1/12/2023 Partial Approval KATHRYN BUTTERWORTH
Excavation/Setback/Form/Re-Bar 2/7/2023 Approved KATHRYN BUTTERWORTH
Footing/Foundation/Slab 2/7/2023 Approved KATHRYN BUTTERWORTH
METHANE-Barrier 2/7/2023 Approved KATHRYN BUTTERWORTH
Floor/Roof Diaphrgm/Shear Wall 3/7/2023 Corrections Issued KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 5/2/2023 Approved KATHRYN BUTTERWORTH
ELECTRICAL-Rough 5/2/2023 Partial Approval KATHRYN BUTTERWORTH
Floor/Roof Diaphrgm/Shear Wall 5/2/2023 Corrections Issued KATHRYN BUTTERWORTH
Green Building Rough 5/2/2023 Approved KATHRYN BUTTERWORTH
HVAC-Rough 5/2/2023 Approved KATHRYN BUTTERWORTH
METHANE-Rough 5/2/2023 Approved KATHRYN BUTTERWORTH
PLUMBING-Rough 5/2/2023 Approved KATHRYN BUTTERWORTH
Deputy Wood Construction 5/3/2023 Conditional Approval KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 5/23/2023 Approved KATHRYN BUTTERWORTH
Floor/Roof Diaphrgm/Shear Wall 5/23/2023 Partial Approval KATHRYN BUTTERWORTH
Insulation 5/23/2023 Corrections Issued KATHRYN BUTTERWORTH
Interior/Exterior Lathing 5/23/2023 Partial Approval KATHRYN BUTTERWORTH
Shower Pan 5/23/2023 Approved KATHRYN BUTTERWORTH
Drywall Nailing 6/2/2023 Approved KATHRYN BUTTERWORTH
Insulation 6/2/2023 Approved KATHRYN BUTTERWORTH
Interior/Exterior Lathing 6/2/2023 Partial Approval KATHRYN BUTTERWORTH
Sewer 9/13/2023 Approved KATHRYN BUTTERWORTH
Underground Mechanical 9/13/2023 Partial Approval KATHRYN BUTTERWORTH
Underground Mechanical 9/18/2023 Partial Approval KATHRYN BUTTERWORTH
Final 12/11/2023 Not Ready for Inspection KATHRYN BUTTERWORTH
ELECTRICAL-Final 4/5/2024 Approved ARTHUR NEGRETE
Final 4/5/2024 OK to Issue CofO ARTHUR NEGRETE
Green Building Final 4/5/2024 Approved ARTHUR NEGRETE
HVAC-Final 4/5/2024 Approved ARTHUR NEGRETE
PLUMBING-Final 4/5/2024 Approved ARTHUR NEGRETE
SGSOV-Seismic Gas S/O Valve 4/5/2024 SGSOV Approved ARTHUR NEGRETE
Service/Power Release 4/5/2024 Approved ARTHUR NEGRETE
Smoke Detectors 4/5/2024 Approved ARTHUR NEGRETE