1533 1/2 S 4TH AVE 90019
Certificate Information: 1533 1/2 S 4TH AVE 90019
- Application / Permit
- 21010-10000-02971
- Plan Check / Job No.
- B21LA11235
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 1 STORY ADU PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 4/21/2022
- Issuing Office
- Current Status
- CofO Issued on 7/10/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/15/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/22/2021 | KHEDER ALRAZAA |
| Corrections Issued | 7/27/2021 | KHEDER ALRAZAA |
| Quality Review Completed | 8/5/2021 | JASON HEALEY |
| Applicant returned to address corrections | 3/11/2022 | KHEDER ALRAZAA |
| Applicant returned to address corrections | 3/22/2022 | KHEDER ALRAZAA |
| Plan Check Approved | 4/20/2022 | KHEDER ALRAZAA |
| Plan Check Approved | 4/21/2022 | STELLA SARGSYAN |
| Issued | 4/21/2022 | APPLICANT |
| Building Plans Picked Up | 4/27/2022 | APPLICANT |
| CofO in Progress | 4/8/2024 | ARTHUR NEGRETE |
| No Progress | 4/22/2024 | SCOTT FINNILA |
| CofO in Progress | 4/22/2024 | SCOTT FINNILA |
| CofO Issued | 7/10/2024 | DEROLD HAUFF |
| Permit Finaled | 7/10/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 10/20/2021 | AMAAN MALIK |
| Eng Process Fee Ord 176,300 | Cleared | 10/22/2021 | AMAAN MALIK |
| Sewer availability | Cleared | 10/22/2021 | AMAAN MALIK |
| Low Impact Development | Cleared | 1/13/2022 | MARCO SANCHEZ |
| Roof/Waste drainage to street | Cleared | 2/1/2022 | AMAAN MALIK |
| Community Plan Implem. Overlay | Cleared | 3/16/2022 | KYLE WINSTON |
Contact Information
| Contractor | Simcity Construction Inc; Lic. No.: 1027407-B | 3350 W OLYMOIC BLVD #202 LOS ANGELES, CA 90019 |
Inspector Information
| WILLIAM SIERRA, (213) 202-3122 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/30/2022 | Corrections Issued | KATHRYN BUTTERWORTH |
| METHANE-Subgrade | 6/30/2022 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| METHANE-Subgrade | 1/12/2023 | Approved | KATHRYN BUTTERWORTH |
| PLUMBING-Rough | 1/12/2023 | Partial Approval | KATHRYN BUTTERWORTH |
| Excavation/Setback/Form/Re-Bar | 2/7/2023 | Approved | KATHRYN BUTTERWORTH |
| Footing/Foundation/Slab | 2/7/2023 | Approved | KATHRYN BUTTERWORTH |
| METHANE-Barrier | 2/7/2023 | Approved | KATHRYN BUTTERWORTH |
| Floor/Roof Diaphrgm/Shear Wall | 3/7/2023 | Corrections Issued | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 5/2/2023 | Approved | KATHRYN BUTTERWORTH |
| ELECTRICAL-Rough | 5/2/2023 | Partial Approval | KATHRYN BUTTERWORTH |
| Floor/Roof Diaphrgm/Shear Wall | 5/2/2023 | Corrections Issued | KATHRYN BUTTERWORTH |
| Green Building Rough | 5/2/2023 | Approved | KATHRYN BUTTERWORTH |
| HVAC-Rough | 5/2/2023 | Approved | KATHRYN BUTTERWORTH |
| METHANE-Rough | 5/2/2023 | Approved | KATHRYN BUTTERWORTH |
| PLUMBING-Rough | 5/2/2023 | Approved | KATHRYN BUTTERWORTH |
| Deputy Wood Construction | 5/3/2023 | Conditional Approval | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 5/23/2023 | Approved | KATHRYN BUTTERWORTH |
| Floor/Roof Diaphrgm/Shear Wall | 5/23/2023 | Partial Approval | KATHRYN BUTTERWORTH |
| Insulation | 5/23/2023 | Corrections Issued | KATHRYN BUTTERWORTH |
| Interior/Exterior Lathing | 5/23/2023 | Partial Approval | KATHRYN BUTTERWORTH |
| Shower Pan | 5/23/2023 | Approved | KATHRYN BUTTERWORTH |
| Drywall Nailing | 6/2/2023 | Approved | KATHRYN BUTTERWORTH |
| Insulation | 6/2/2023 | Approved | KATHRYN BUTTERWORTH |
| Interior/Exterior Lathing | 6/2/2023 | Partial Approval | KATHRYN BUTTERWORTH |
| Sewer | 9/13/2023 | Approved | KATHRYN BUTTERWORTH |
| Underground Mechanical | 9/13/2023 | Partial Approval | KATHRYN BUTTERWORTH |
| Underground Mechanical | 9/18/2023 | Partial Approval | KATHRYN BUTTERWORTH |
| Final | 12/11/2023 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| ELECTRICAL-Final | 4/5/2024 | Approved | ARTHUR NEGRETE |
| Final | 4/5/2024 | OK to Issue CofO | ARTHUR NEGRETE |
| Green Building Final | 4/5/2024 | Approved | ARTHUR NEGRETE |
| HVAC-Final | 4/5/2024 | Approved | ARTHUR NEGRETE |
| PLUMBING-Final | 4/5/2024 | Approved | ARTHUR NEGRETE |
| SGSOV-Seismic Gas S/O Valve | 4/5/2024 | SGSOV Approved | ARTHUR NEGRETE |
| Service/Power Release | 4/5/2024 | Approved | ARTHUR NEGRETE |
| Smoke Detectors | 4/5/2024 | Approved | ARTHUR NEGRETE |