600-600 1/2 W 79TH ST 90044
Certificate Information: 600-600 1/2 W 79TH ST 90044
- Application / Permit
- 21010-10000-02969
- Plan Check / Job No.
- B21LA11232
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- TWO NEW 1-STORY ACCESSORY DWELLING UNITS PER GCS 65852.
- Permit Issued
- Issued on 12/29/2021
- Issuing Office
- Current Status
- CofO Issued on 6/24/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/15/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/22/2021 | JOHNNY WU |
| Corrections Issued | 7/29/2021 | JOHNNY WU |
| Quality Review Completed | 8/4/2021 | ALLEN MANALANSAN |
| Applicant returned to address corrections | 12/10/2021 | JOHNNY WU |
| Applicant returned to address corrections | 12/16/2021 | JOHNNY WU |
| Plan Check Approved | 12/17/2021 | JOHNNY WU |
| Issued | 12/29/2021 | APPLICANT |
| Building Plans Picked Up | 12/30/2021 | APPLICANT |
| CofO in Progress | 6/18/2024 | DAVID FEILER |
| Permit Finaled | 6/24/2024 | DEROLD HAUFF |
| CofO Issued | 6/24/2024 | DEROLD HAUFF |
| Permit Finaled | 6/24/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Green Code | Cleared | 7/30/2021 | JOHNNY WU |
| Eng Process Fee Ord 176,300 | Cleared | 8/5/2021 | RENZ SORIANO |
| Address approval | Cleared | 9/7/2021 | RENZ SORIANO |
| Sewer availability | Cleared | 9/8/2021 | RENZ SORIANO |
| Construction near power lines | Cleared | 9/13/2021 | RIDWAN HARDY |
| Hydrant and Access approval | Cleared | 9/25/2021 | RUEL COLE |
| Highway dedication | Cleared | 10/19/2021 | RENZ SORIANO |
| Low Impact Development | Cleared | 11/3/2021 | TA ANH |
| Roof/Waste drainage to street | Cleared | 11/8/2021 | JEANETTE VONG |
Contact Information
| Contractor | Jerahian Araz; Lic. No.: 1045340-B | 250 N COLLEGE PARK DR F36 UPLAND, CA 91786 |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/3/2022 | Approved | HORACE FULTZ |
| PLUMBING-Rough | 6/28/2022 | Conditional Approval | LILIANA PORTILLO |
| Excavation/Setback/Form/Re-Bar | 7/8/2022 | Corrections Issued | LILIANA PORTILLO |
| Footing/Foundation/Slab | 7/14/2022 | Corrections Issued | LILIANA PORTILLO |
| Deputy Wood Construction | 9/27/2022 | Conditional Approval | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 9/30/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| Footing/Foundation/Slab | 9/30/2022 | Approved | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 10/5/2022 | Corrections Issued | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 10/14/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| ELECTRICAL-Rough | 10/25/2022 | Corrections Issued | LILIANA PORTILLO |
| PLUMBING-Rough | 11/8/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 11/18/2022 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Rough | 11/23/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| PLUMBING-Rough | 11/23/2022 | Conditional Approval | LILIANA PORTILLO |
| ELECTRICAL-Rough | 12/16/2022 | Approved | LILIANA PORTILLO |
| Gas Test | 12/16/2022 | Approved | LILIANA PORTILLO |
| PLUMBING-Rough | 12/23/2022 | Approved | LILIANA PORTILLO |
| HVAC-Rough | 12/30/2022 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 1/5/2023 | Corrections Issued | LILIANA PORTILLO |
| Green Building Rough | 1/5/2023 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 1/5/2023 | Partial Approval | LILIANA PORTILLO |
| Verify Sprinkler Sign Off | 1/5/2023 | Approved | LILIANA PORTILLO |
| Insulation | 1/11/2023 | Corrections Issued | LILIANA PORTILLO |
| Sewer | 1/19/2023 | Approved | LILIANA PORTILLO |
| Underground Mechanical | 1/19/2023 | Partial Approval | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 1/26/2023 | Approved | LILIANA PORTILLO |
| Insulation | 1/26/2023 | Conditional Approval | LILIANA PORTILLO |
| MERV13>=Rough | 1/26/2023 | Approved | LILIANA PORTILLO |
| Drywall Nailing | 2/3/2023 | Approved | LILIANA PORTILLO |
| Insulation | 2/3/2023 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Final | 1/30/2024 | Corrections Issued | MICHAEL LEWIS |
| Final | 1/30/2024 | Corrections Issued | MICHAEL LEWIS |
| Green Building Final | 1/30/2024 | Corrections Issued | MICHAEL LEWIS |
| HVAC-Final | 1/30/2024 | Corrections Issued | MICHAEL LEWIS |
| MERV13>=Final | 1/30/2024 | Approved | MICHAEL LEWIS |
| PLUMBING-Final | 1/30/2024 | Corrections Issued | MICHAEL LEWIS |
| SGSOV-Seismic Gas S/O Valve | 1/30/2024 | SGSOV Not Ready | MICHAEL LEWIS |
| Service/Power Release | 1/30/2024 | Not Ready for Inspection | MICHAEL LEWIS |
| Smoke Detectors | 1/30/2024 | Approved | MICHAEL LEWIS |
| Final | 3/15/2024 | Corrections Issued | MICHAEL LEWIS |
| Green Building Final | 3/15/2024 | Approved | MICHAEL LEWIS |
| SGSOV-Seismic Gas S/O Valve | 3/15/2024 | SGSOV Approved | MICHAEL LEWIS |
| Service/Power Release | 3/15/2024 | Not Ready for Inspection | MICHAEL LEWIS |
| Final | 5/15/2024 | Corrections Issued | MICHAEL LEWIS |
| Service/Power Release | 5/15/2024 | Corrections Issued | MICHAEL LEWIS |
| Final | 6/14/2024 | OK to Issue CofO | MICHAEL LEWIS |
| Service/Power Release | 6/14/2024 | Approved | MICHAEL LEWIS |