600-600 1/2 W 79TH ST 90044

Certificate Information: 600-600 1/2 W 79TH ST 90044

Application / Permit
21010-10000-02969
Plan Check / Job No.
B21LA11232
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
TWO NEW 1-STORY ACCESSORY DWELLING UNITS PER GCS 65852.
Permit Issued
Issued on 12/29/2021
Issuing Office
Current Status
CofO Issued on 6/24/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/15/2021 APPLICANT
Assigned to Plan Check Engineer 7/22/2021 JOHNNY WU
Corrections Issued 7/29/2021 JOHNNY WU
Quality Review Completed 8/4/2021 ALLEN MANALANSAN
Applicant returned to address corrections 12/10/2021 JOHNNY WU
Applicant returned to address corrections 12/16/2021 JOHNNY WU
Plan Check Approved 12/17/2021 JOHNNY WU
Issued 12/29/2021 APPLICANT
Building Plans Picked Up 12/30/2021 APPLICANT
CofO in Progress 6/18/2024 DAVID FEILER
Permit Finaled 6/24/2024 DEROLD HAUFF
CofO Issued 6/24/2024 DEROLD HAUFF
Permit Finaled 6/24/2024 DEROLD HAUFF

Permit Application Clearance Information

Green Code Cleared 7/30/2021 JOHNNY WU
Eng Process Fee Ord 176,300 Cleared 8/5/2021 RENZ SORIANO
Address approval Cleared 9/7/2021 RENZ SORIANO
Sewer availability Cleared 9/8/2021 RENZ SORIANO
Construction near power lines Cleared 9/13/2021 RIDWAN HARDY
Hydrant and Access approval Cleared 9/25/2021 RUEL COLE
Highway dedication Cleared 10/19/2021 RENZ SORIANO
Low Impact Development Cleared 11/3/2021 TA ANH
Roof/Waste drainage to street Cleared 11/8/2021 JEANETTE VONG

Contact Information

Contractor Jerahian Araz; Lic. No.: 1045340-B 250 N COLLEGE PARK DR F36      UPLAND, CA 91786
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/3/2022 Approved HORACE FULTZ
PLUMBING-Rough 6/28/2022 Conditional Approval LILIANA PORTILLO
Excavation/Setback/Form/Re-Bar 7/8/2022 Corrections Issued LILIANA PORTILLO
Footing/Foundation/Slab 7/14/2022 Corrections Issued LILIANA PORTILLO
Deputy Wood Construction 9/27/2022 Conditional Approval ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 9/30/2022 Not Ready for Inspection LILIANA PORTILLO
Footing/Foundation/Slab 9/30/2022 Approved LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 10/5/2022 Corrections Issued LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 10/14/2022 Not Ready for Inspection LILIANA PORTILLO
ELECTRICAL-Rough 10/25/2022 Corrections Issued LILIANA PORTILLO
PLUMBING-Rough 11/8/2022 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 11/18/2022 Approved LILIANA PORTILLO
ELECTRICAL-Rough 11/23/2022 Not Ready for Inspection LILIANA PORTILLO
PLUMBING-Rough 11/23/2022 Conditional Approval LILIANA PORTILLO
ELECTRICAL-Rough 12/16/2022 Approved LILIANA PORTILLO
Gas Test 12/16/2022 Approved LILIANA PORTILLO
PLUMBING-Rough 12/23/2022 Approved LILIANA PORTILLO
HVAC-Rough 12/30/2022 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 1/5/2023 Corrections Issued LILIANA PORTILLO
Green Building Rough 1/5/2023 Approved LILIANA PORTILLO
Interior/Exterior Lathing 1/5/2023 Partial Approval LILIANA PORTILLO
Verify Sprinkler Sign Off 1/5/2023 Approved LILIANA PORTILLO
Insulation 1/11/2023 Corrections Issued LILIANA PORTILLO
Sewer 1/19/2023 Approved LILIANA PORTILLO
Underground Mechanical 1/19/2023 Partial Approval LILIANA PORTILLO
BUILDING-Rough-Frame 1/26/2023 Approved LILIANA PORTILLO
Insulation 1/26/2023 Conditional Approval LILIANA PORTILLO
MERV13>=Rough 1/26/2023 Approved LILIANA PORTILLO
Drywall Nailing 2/3/2023 Approved LILIANA PORTILLO
Insulation 2/3/2023 Approved LILIANA PORTILLO
ELECTRICAL-Final 1/30/2024 Corrections Issued MICHAEL LEWIS
Final 1/30/2024 Corrections Issued MICHAEL LEWIS
Green Building Final 1/30/2024 Corrections Issued MICHAEL LEWIS
HVAC-Final 1/30/2024 Corrections Issued MICHAEL LEWIS
MERV13>=Final 1/30/2024 Approved MICHAEL LEWIS
PLUMBING-Final 1/30/2024 Corrections Issued MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 1/30/2024 SGSOV Not Ready MICHAEL LEWIS
Service/Power Release 1/30/2024 Not Ready for Inspection MICHAEL LEWIS
Smoke Detectors 1/30/2024 Approved MICHAEL LEWIS
Final 3/15/2024 Corrections Issued MICHAEL LEWIS
Green Building Final 3/15/2024 Approved MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 3/15/2024 SGSOV Approved MICHAEL LEWIS
Service/Power Release 3/15/2024 Not Ready for Inspection MICHAEL LEWIS
Final 5/15/2024 Corrections Issued MICHAEL LEWIS
Service/Power Release 5/15/2024 Corrections Issued MICHAEL LEWIS
Final 6/14/2024 OK to Issue CofO MICHAEL LEWIS
Service/Power Release 6/14/2024 Approved MICHAEL LEWIS