894-896 E 35TH ST 90011

Certificate Information: 894-896 E 35TH ST 90011

Application / Permit
21010-10000-02960
Plan Check / Job No.
B21LA11216
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW 2-STORY DUPLEX WITH ATTACHED 1-CAR GARAGE AT FRONT AND 2-CAR GARAGE AT REAR ****SEE COMMENTS
Permit Issued
Issued on 11/4/2021
Issuing Office
Current Status
CofO Issued on 6/29/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/15/2021 APPLICANT
Assigned to Plan Check Engineer 7/8/2021 CARLOS MONTES
Corrections Issued 7/12/2021 CARLOS MONTES
Quality Review Completed 7/28/2021 WING SUEN
Building Plans Picked Up 7/30/2021 APPLICANT
Plan Check Approved 10/6/2021 CARLOS MONTES
Issued 11/4/2021 APPLICANT
CofO in Progress 6/21/2022 JOAQUIN GREENOUGH
Permit Finaled 6/29/2022 DEROLD HAUFF
CofO Issued 6/29/2022 DEROLD HAUFF
Permit Finaled 6/29/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/16/2021 STEVE MELGAR
Highway dedication Cleared 8/16/2021 STEVE MELGAR
Hydrant and Access approval Cleared 8/16/2021 ROBERT DUFF
Permit Cleared 8/16/2021 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 8/17/2021 STEVE MELGAR
Sewer availability Cleared 8/17/2021 STEVE MELGAR
Tenant Habitability Plan Cleared 8/23/2021 PHILLIP MUNGUIA
Trees in Parkway Cleared 8/26/2021 JOHN KIM
Frnt yard landscape/Water mgmt Cleared 8/31/2021 DENZEL HENDERSON
Low Impact Development Cleared 9/22/2021 MARCO SANCHEZ
Roof/Waste drainage to street Cleared 9/23/2021 CELINA MORENO

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B P O BOX 410      SUNSET BEACH, CA 90742
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/16/2021 Approved JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 1/13/2022 Not Ready for Inspection JOAQUIN GREENOUGH
Underground Mechanical 1/13/2022 Partial Approval JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 1/14/2022 Not Ready for Inspection SHAVONNE ESPINOZA
Insulation 1/14/2022 Partial Approval SHAVONNE ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 1/18/2022 Approved FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 1/25/2022 Partial Approval HORACE FULTZ
Floor/Roof Diaphrgm/Shear Wall 2/17/2022 Partial Approval ALEJANDRO DE ARTOLA
HVAC-Rough 3/4/2022 Corrections Issued JOAQUIN GREENOUGH
PLUMBING-Rough 3/4/2022 Corrections Issued JOAQUIN GREENOUGH
BUILDING-Rough-Frame 3/7/2022 Not Ready for Inspection JOAQUIN GREENOUGH
ELECTRICAL-Rough 3/7/2022 Not Ready for Inspection JOAQUIN GREENOUGH
HVAC-Rough 3/7/2022 Approved JOAQUIN GREENOUGH
PLUMBING-Rough 3/7/2022 Approved JOAQUIN GREENOUGH
BUILDING-Rough-Frame 3/8/2022 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 3/8/2022 Approved ALEJANDRO DE ARTOLA
Green Building Rough 3/8/2022 Corrections Issued ALEJANDRO DE ARTOLA
Verify Sprinkler Sign Off 3/8/2022 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 3/9/2022 Approved ALEJANDRO DE ARTOLA
Green Building Rough 3/9/2022 Approved ALEJANDRO DE ARTOLA
Insulation 3/9/2022 Corrections Issued ALEJANDRO DE ARTOLA
Insulation 3/10/2022 Approved JOAQUIN GREENOUGH
Drywall Nailing 4/5/2022 Corrections Issued JOAQUIN GREENOUGH
Interior/Exterior Lathing 4/5/2022 Partial Approval JOAQUIN GREENOUGH
Drywall Nailing 4/18/2022 Approved JOAQUIN GREENOUGH
Interior/Exterior Lathing 4/18/2022 Approved JOAQUIN GREENOUGH
ELECTRICAL-Final 5/19/2022 Partial Approval JOAQUIN GREENOUGH
ELECTRICAL-Final 6/15/2022 Approved JOAQUIN GREENOUGH
Final 6/15/2022 Partial Inspection JOAQUIN GREENOUGH
Green Building Final 6/15/2022 Approved JOAQUIN GREENOUGH
HVAC-Final 6/15/2022 Approved JOAQUIN GREENOUGH
PLUMBING-Final 6/15/2022 Approved JOAQUIN GREENOUGH
SGSOV-Seismic Gas S/O Valve 6/15/2022 SGSOV Approved JOAQUIN GREENOUGH
Service/Power Release 6/15/2022 Approved JOAQUIN GREENOUGH
Smoke Detectors 6/15/2022 Approved JOAQUIN GREENOUGH
Final 6/16/2022 OK to Issue CofO JOAQUIN GREENOUGH
Service/Power Release 6/16/2022 Approved JOAQUIN GREENOUGH