894-896 E 35TH ST 90011
Certificate Information: 894-896 E 35TH ST 90011
- Application / Permit
- 21010-10000-02960
- Plan Check / Job No.
- B21LA11216
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW 2-STORY DUPLEX WITH ATTACHED 1-CAR GARAGE AT FRONT AND 2-CAR GARAGE AT REAR ****SEE COMMENTS
- Permit Issued
- Issued on 11/4/2021
- Issuing Office
- Current Status
- CofO Issued on 6/29/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/15/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/8/2021 | CARLOS MONTES |
| Corrections Issued | 7/12/2021 | CARLOS MONTES |
| Quality Review Completed | 7/28/2021 | WING SUEN |
| Building Plans Picked Up | 7/30/2021 | APPLICANT |
| Plan Check Approved | 10/6/2021 | CARLOS MONTES |
| Issued | 11/4/2021 | APPLICANT |
| CofO in Progress | 6/21/2022 | JOAQUIN GREENOUGH |
| Permit Finaled | 6/29/2022 | DEROLD HAUFF |
| CofO Issued | 6/29/2022 | DEROLD HAUFF |
| Permit Finaled | 6/29/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 8/16/2021 | STEVE MELGAR |
| Highway dedication | Cleared | 8/16/2021 | STEVE MELGAR |
| Hydrant and Access approval | Cleared | 8/16/2021 | ROBERT DUFF |
| Permit | Cleared | 8/16/2021 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 8/17/2021 | STEVE MELGAR |
| Sewer availability | Cleared | 8/17/2021 | STEVE MELGAR |
| Tenant Habitability Plan | Cleared | 8/23/2021 | PHILLIP MUNGUIA |
| Trees in Parkway | Cleared | 8/26/2021 | JOHN KIM |
| Frnt yard landscape/Water mgmt | Cleared | 8/31/2021 | DENZEL HENDERSON |
| Low Impact Development | Cleared | 9/22/2021 | MARCO SANCHEZ |
| Roof/Waste drainage to street | Cleared | 9/23/2021 | CELINA MORENO |
Contact Information
| Contractor | K N Consulting Inc; Lic. No.: 993102-B | P O BOX 410 SUNSET BEACH, CA 90742 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/16/2021 | Approved | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 1/13/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Underground Mechanical | 1/13/2022 | Partial Approval | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 1/14/2022 | Not Ready for Inspection | SHAVONNE ESPINOZA |
| Insulation | 1/14/2022 | Partial Approval | SHAVONNE ESPINOZA |
| Floor/Roof Diaphrgm/Shear Wall | 1/18/2022 | Approved | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 1/25/2022 | Partial Approval | HORACE FULTZ |
| Floor/Roof Diaphrgm/Shear Wall | 2/17/2022 | Partial Approval | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 3/4/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 3/4/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 3/7/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 3/7/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| HVAC-Rough | 3/7/2022 | Approved | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 3/7/2022 | Approved | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 3/8/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 3/8/2022 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Rough | 3/8/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Verify Sprinkler Sign Off | 3/8/2022 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 3/9/2022 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Rough | 3/9/2022 | Approved | ALEJANDRO DE ARTOLA |
| Insulation | 3/9/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Insulation | 3/10/2022 | Approved | JOAQUIN GREENOUGH |
| Drywall Nailing | 4/5/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Interior/Exterior Lathing | 4/5/2022 | Partial Approval | JOAQUIN GREENOUGH |
| Drywall Nailing | 4/18/2022 | Approved | JOAQUIN GREENOUGH |
| Interior/Exterior Lathing | 4/18/2022 | Approved | JOAQUIN GREENOUGH |
| ELECTRICAL-Final | 5/19/2022 | Partial Approval | JOAQUIN GREENOUGH |
| ELECTRICAL-Final | 6/15/2022 | Approved | JOAQUIN GREENOUGH |
| Final | 6/15/2022 | Partial Inspection | JOAQUIN GREENOUGH |
| Green Building Final | 6/15/2022 | Approved | JOAQUIN GREENOUGH |
| HVAC-Final | 6/15/2022 | Approved | JOAQUIN GREENOUGH |
| PLUMBING-Final | 6/15/2022 | Approved | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 6/15/2022 | SGSOV Approved | JOAQUIN GREENOUGH |
| Service/Power Release | 6/15/2022 | Approved | JOAQUIN GREENOUGH |
| Smoke Detectors | 6/15/2022 | Approved | JOAQUIN GREENOUGH |
| Final | 6/16/2022 | OK to Issue CofO | JOAQUIN GREENOUGH |
| Service/Power Release | 6/16/2022 | Approved | JOAQUIN GREENOUGH |