1542 W 84TH ST 1-3 90047

Certificate Information: 1542 W 84TH ST 1-3 90047

Application / Permit
21010-10000-02958
Plan Check / Job No.
B21LA11213
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
NEW 2 STORY 3 UNITS APARTEMNT (NFPA 13R THROUGH OUT)
Permit Issued
Issued on 3/23/2023
Issuing Office
Metro
Current Status
CofO Issued on 12/17/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/22/2021 APPLICANT
Assigned to Plan Check Engineer 7/29/2021 AUNG SOE
Corrections Issued 8/13/2021 AUNG SOE
Quality Review Completed 8/17/2021 EUGENE BARBEAU
Building Plans Picked Up 8/23/2021 APPLICANT
Applicant returned to address corrections 4/7/2022 AUNG SOE
Plan Check Approved 6/16/2022 AUNG SOE
Issued 3/23/2023 APPLICANT
CofO in Progress 12/17/2024 JAMES POWERS
CofO Issued 12/17/2024 ERNESTO CORRAL
Permit Finaled 12/17/2024 ERNESTO CORRAL

Permit Application Clearance Information

Address approval Cleared 10/28/2021 CHRISTOPHER ROCHA
DAS Clearance Cleared 2/8/2022 OLLIE CARTER
Low Impact Development Cleared 3/3/2022 TA ANH
Eng Process Fee Ord 176,300 Cleared 3/9/2022 CINDY QI
Roof/Waste drainage to street Cleared 3/9/2022 CINDY QI
Sewer availability Cleared 3/9/2022 CINDY QI
Frnt yard landscape/Water mgmt Cleared 3/11/2022 MAXFIELD VERMY
Hydrant and Access approval Cleared 5/14/2022 GILBERT URREA
Green Code Cleared 5/26/2022 AARON COSTA

Contact Information

Architect Victor, M Fressie; Lic. No.: C36724 801 S HOPE STREET   SUITE 917    LOS ANGELES, CA 90017
Contractor Owner-Builder       ,
Engineer Garcia,, Francisco Javier; Lic. No.: C76510 2705 S FREMONT AVE APT D      ALHAMBRA, CA 91803

Inspector Information

ALFREDO LOPEZ, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI
JAMES POWERS, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/17/2023 Approved LARRY ARNICK
Footing/Foundation/Slab 7/17/2023 Approved LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 7/31/2023 Partial Approval ALAN MORELOS
Green Building Rough 7/31/2023 Not Ready for Inspection ALAN MORELOS
Verify Sprinkler Sign Off 7/31/2023 Not Ready for Inspection ALAN MORELOS
Deputy Wood Construction 9/14/2023 Conditional Approval MICHAEL ROSENBERG
Floor/Roof Diaphrgm/Shear Wall 9/15/2023 Partial Approval JAMES POWERS
Green Building Rough 9/15/2023 Approved JAMES POWERS
Verify Rec and Parks Fee Memo 9/15/2023 Not Ready for Inspection JAMES POWERS
Verify Sprinkler Sign Off 9/15/2023 Not Ready for Inspection JAMES POWERS
Verify Sprinkler Sign Off 9/22/2023 Not Ready for Inspection LARRY ARNICK
Wood Frame 9/22/2023 Not Ready for Inspection LARRY ARNICK
Green Building Rough 9/25/2023 Approved LARRY ARNICK
Verify Rec and Parks Fee Memo 9/26/2023 No Access for Inspection LARRY ARNICK
Verify Sprinkler Sign Off 9/26/2023 Approved LARRY ARNICK
Wood Frame 9/26/2023 Approved LARRY ARNICK
Insulation 9/29/2023 Approved JAMES POWERS
Drywall Nailing 10/3/2023 Approved JAMES POWERS
Interior/Exterior Lathing 10/17/2023 Partial Approval JAMES POWERS
Pre-Inspection 12/15/2023 Not Ready for Inspection JAMES POWERS
Pre-Inspection 1/3/2024 Not Ready for Inspection JAMES POWERS
Excavation/Setback/Form/Re-Bar 1/4/2024 Not Ready for Inspection JAMES POWERS
Excavation/Setback/Form/Re-Bar 1/10/2024 Partial Approval JAMES POWERS
Pre-Inspection 1/17/2024 Partial Approval JAMES POWERS
Final 8/29/2024 OK for TCO JAMES POWERS
Green Building Final 8/29/2024 Approved JAMES POWERS
SGSOV-Seismic Gas S/O Valve 8/29/2024 SGSOV Approved JAMES POWERS
Smoke Detectors 8/29/2024 Approved JAMES POWERS
Final 11/27/2024 Not Ready for Inspection JAMES POWERS
Final 12/3/2024 OK to Issue CofO JAMES POWERS