923 1/2-3/4 N BEAUDRY AVE 90012
Certificate Information: 923 1/2-3/4 N BEAUDRY AVE 90012
- Application / Permit
- 21010-10000-02953
- Plan Check / Job No.
- B21LA11207
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW 2-STORY DUPLEX (ZC: 2434 SF) AT FRONT 1 OF 2
- Permit Issued
- Issued on 12/30/2021
- Issuing Office
- Current Status
- CofO Issued on 8/10/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/15/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/8/2021 | VIVIAN LAO |
| Corrections Issued | 7/16/2021 | VIVIAN LAO |
| Quality Review Completed | 7/29/2021 | MICHAEL PEREZ |
| Applicant returned to address corrections | 11/19/2021 | VIVIAN LAO |
| Plan Check Approved | 12/13/2021 | VIVIAN LAO |
| Plan Check Approved | 12/13/2021 | KEAVEN SHAW |
| Issued | 12/30/2021 | APPLICANT |
| Building Plans Picked Up | 1/10/2022 | APPLICANT |
| CofO in Progress | 7/25/2023 | THOMAS LOGRASSO |
| CofO Issued | 8/10/2023 | DEROLD HAUFF |
| Permit Finaled | 8/10/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 8/26/2021 | NAZILA NOORIFAR |
| Permit | Cleared | 8/26/2021 | NAZILA NOORIFAR |
| Sewer availability | Cleared | 8/26/2021 | NAZILA NOORIFAR |
| Eng Process Fee Ord 176,300 | Cleared | 8/27/2021 | NAZILA NOORIFAR |
| Low Impact Development | Cleared | 9/15/2021 | KHAING AYE |
| Roof/Waste drainage to street | Cleared | 9/16/2021 | NAZILA NOORIFAR |
| Hydrant and Access approval | Cleared | 10/1/2021 | KURT CORRAL |
| GPI Written Notices | Cleared | 11/19/2021 | VIVIAN LAO |
| Grading Pre-Inspection | Cleared | 11/19/2021 | VIVIAN LAO |
| Historic Resource Verification | Cleared | 11/24/2021 | GRACIELA ACOSTA |
| Redevelopment Project Area | Cleared | 11/24/2021 | GRACIELA ACOSTA |
| Frnt yard landscape/Water mgmt | Cleared | 12/13/2021 | KENTON TRINH |
Contact Information
| Contractor | Rios William A; Lic. No.: 866335-B | P O BOX 1061 DOWNEY, CA 90240 |
| Engineer | Salto,, Alvaro; Lic. No.: C83859 | 2543 E NORMAN AVE WEST COVINA, CA 91791 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/15/2022 | Approved | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 2/15/2022 | Approved | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 3/3/2022 | Partial Approval | RUBEN SALAS |
| PLUMBING-Rough | 3/3/2022 | Partial Approval | RUBEN SALAS |
| Floor/Roof Diaphrgm/Shear Wall | 3/8/2022 | Partial Approval | RUBEN SALAS |
| Insulation | 3/8/2022 | Partial Approval | RUBEN SALAS |
| Floor/Roof Diaphrgm/Shear Wall | 4/5/2022 | Approved | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 5/13/2022 | Corrections Issued | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 7/1/2022 | Corrections Issued | HAMIK HARTOUNIAN |
| HVAC-Rough | 7/1/2022 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 7/1/2022 | Partial Approval | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 7/11/2022 | Corrections Issued | THOMAS LOGRASSO |
| Verify Sprinkler Sign Off | 7/11/2022 | Approved | THOMAS LOGRASSO |
| Insulation | 7/21/2022 | Conditional Approval | THOMAS LOGRASSO |
| Drywall Nailing | 8/2/2022 | Conditional Approval | THOMAS LOGRASSO |
| Green Building Rough | 8/2/2022 | Conditional Approval | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 8/2/2022 | Conditional Approval | THOMAS LOGRASSO |
| Pre-Inspection | 5/15/2023 | Partial Inspection | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 6/27/2023 | Approved | THOMAS LOGRASSO |
| Drywall Nailing | 6/27/2023 | Approved | THOMAS LOGRASSO |
| Final | 6/27/2023 | Corrections Issued | THOMAS LOGRASSO |
| Green Building Final | 6/27/2023 | Approved | THOMAS LOGRASSO |
| Green Building Rough | 6/27/2023 | Approved | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 6/27/2023 | SGSOV Approved | THOMAS LOGRASSO |
| Service/Power Release | 6/27/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Smoke Detectors | 6/27/2023 | Approved | THOMAS LOGRASSO |
| Final | 7/21/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Service/Power Release | 7/21/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Final | 7/24/2023 | OK to Issue CofO | THOMAS LOGRASSO |
| Service/Power Release | 7/24/2023 | Approved | THOMAS LOGRASSO |