11600 W PICO BLVD 90064
Certificate Information: 11600 W PICO BLVD 90064
- Application / Permit
- 21010-10000-02941
- Plan Check / Job No.
- B21LA11164
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (7) Carport
- Work Description
- NEW FREE STANDING CARPORT/ SOLAR STRUCTURE.
- Permit Issued
- Issued on 10/3/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 4/12/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/18/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/8/2021 | LARRY LEE |
| Corrections Issued | 7/15/2021 | LARRY LEE |
| Quality Review Completed | 7/22/2021 | SAI KHUM |
| Disabled Access Plans Picked Up | 9/21/2021 | APPLICANT |
| Building Plans Picked Up | 11/15/2021 | APPLICANT |
| Applicant returned to address corrections | 2/10/2022 | LARRY LEE |
| Applicant returned to address corrections | 2/14/2022 | LARRY LEE |
| Applicant returned to address corrections | 4/6/2022 | LARRY LEE |
| Applicant returned to address corrections | 9/13/2022 | SERGIO GUTIERREZ |
| Plan Check Approved | 10/3/2022 | SERGIO GUTIERREZ |
| Issued | 10/3/2022 | APPLICANT |
| CofO in Progress | 4/12/2023 | DERRICK SPENCER |
| Permit Finaled | 4/12/2023 | DAVID TSAU |
| CofO Issued | 4/12/2023 | DAVID TSAU |
| Permit Finaled | 4/12/2023 | DAVID TSAU |
Permit Application Clearance Information
| Address approval | Cleared | 2/16/2022 | JENSON LEE |
| Specific Plan | Cleared | 3/3/2022 | VALERIA CEJA |
| Comm Cor/Mini-Mall | Cleared | 3/11/2022 | DANG NGUYEN |
| Specific Plan | Cleared | 3/22/2022 | DYLAN SITTIG |
| Supp. Use District POD/CDO/TDO | Cleared | 3/22/2022 | DYLAN SITTIG |
| Comm Cor/Mini-Mall | Cleared | 3/31/2022 | DANG NGUYEN |
| Prkng lot landscape/Water mgmt | Cleared | 3/31/2022 | DANG NGUYEN |
| Specific Plan | Cleared | 4/5/2022 | VALERIA CEJA |
| Eng Process Fee Ord 176,300 | Cleared | 4/25/2022 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 4/25/2022 | JEANIE LAM |
| Sewer availability | Cleared | 4/25/2022 | JEANIE LAM |
| Hydrant and Access approval | Cleared | 6/17/2022 | KURT CORRAL |
| DAS Clearance | Cleared | 9/29/2022 | LARRY LEE |
Contact Information
| Contractor | Green Home Systems Inc; Lic. No.: 1054222-B | 15021 VENTURA BLVD SHERMAN OAKS, CA 91403 |
| Engineer | Alexander,, Bruce Christopher; Lic. No.: C41690 | 16126 CREEKSIDE DR COTTONWOOD, CA 96022 |
| Engineer | Truong,, Phong; Lic. No.: C70784 | 20439 E CRESTLINE DRIVE WALNUT, CA 91789 |
Inspector Information
| PAUL DAVIDSON, (310) 914-3914 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/4/2022 | Approved | DERRICK SPENCER |
| Footing/Foundation/Slab | 10/4/2022 | Approved | DERRICK SPENCER |
| Final | 11/4/2022 | Not Ready for Inspection | DERRICK SPENCER |
| Green Building Final | 11/4/2022 | Not Ready for Inspection | DERRICK SPENCER |
| Green Building Rough | 11/4/2022 | Not Ready for Inspection | DERRICK SPENCER |
| SGSOV-Seismic Gas S/O Valve | 11/4/2022 | SGSOV Not Ready | DERRICK SPENCER |
| Smoke Detectors | 11/4/2022 | Approved | DERRICK SPENCER |
| Wood Frame | 11/4/2022 | Partial Approval | DERRICK SPENCER |
| Final | 12/1/2022 | OK to Issue CofO | DERRICK SPENCER |
| Green Building Final | 12/1/2022 | Approved | DERRICK SPENCER |
| Green Building Rough | 12/1/2022 | Approved | DERRICK SPENCER |
| SGSOV-Seismic Gas S/O Valve | 12/1/2022 | SGSOV Approved | DERRICK SPENCER |
| Wood Frame | 12/1/2022 | Approved | DERRICK SPENCER |
| Pre-Inspection | 3/10/2023 | Approved | DERRICK SPENCER |