215-217 E 103RD ST 90003
Certificate Information: 215-217 E 103RD ST 90003
- Application / Permit
- 21010-10000-02934
- Plan Check / Job No.
- B21LA11150
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- New 2-story duplex with attached 1-car garage at front and 2-car garage at rear.
- Permit Issued
- Issued on 10/22/2021
- Issuing Office
- Current Status
- CofO Issued on 5/20/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/14/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/8/2021 | HELEN NGUYEN |
| Corrections Issued | 7/15/2021 | HELEN NGUYEN |
| Quality Review Completed | 7/29/2021 | MICHAEL PEREZ |
| Building Plans Picked Up | 7/30/2021 | APPLICANT |
| Applicant returned to address corrections | 10/6/2021 | HELEN NGUYEN |
| Plan Check Approved | 10/14/2021 | HELEN NGUYEN |
| Issued | 10/22/2021 | APPLICANT |
| CofO in Progress | 5/6/2022 | EUGENE CASSIDY |
| Permit Finaled | 5/20/2022 | DEROLD HAUFF |
| CofO Issued | 5/20/2022 | DEROLD HAUFF |
| Permit Finaled | 5/20/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Low Impact Development | Cleared | 8/11/2021 | MARCO SANCHEZ |
| Address approval | Cleared | 8/16/2021 | STEVE MELGAR |
| Hydrant and Access approval | Cleared | 8/16/2021 | ROBERT DUFF |
| Permit | Cleared | 8/16/2021 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 8/25/2021 | STEVE MELGAR |
| Roof/Waste drainage to street | Cleared | 8/27/2021 | CELINA MORENO |
| Sewer availability | Cleared | 8/31/2021 | STEVE MELGAR |
Contact Information
| Contractor | K N Consulting Inc; Lic. No.: 993102-B | P O BOX 410 SUNSET BEACH, CA 90742 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/2/2021 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 12/23/2021 | Partial Approval | JOHN KLARIN |
| Sewer | 12/23/2021 | Approved | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 12/29/2021 | Partial Approval | EUGENE CASSIDY |
| Insulation | 12/29/2021 | Partial Approval | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 1/13/2022 | Partial Approval | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 1/31/2022 | Partial Approval | AMY COLIN |
| BUILDING-Rough-Frame | 2/17/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 2/17/2022 | Approved | ALIZAH MAYAGOITIA |
| Green Building Rough | 2/17/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| HVAC-Rough | 2/17/2022 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 2/17/2022 | Approved | ALIZAH MAYAGOITIA |
| Rough-Elec/Plmb/HVAC | 2/17/2022 | Approved | ALIZAH MAYAGOITIA |
| Verify Sprinkler Sign Off | 2/17/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 2/18/2022 | Partial Approval | JOHN KLARIN |
| Insulation | 2/22/2022 | Approved | JOHN KLARIN |
| Drywall Nailing | 3/3/2022 | Approved | JOHN KLARIN |
| Green Building Rough | 3/3/2022 | Approved | JOHN KLARIN |
| Interior/Exterior Lathing | 3/3/2022 | Approved | JOHN KLARIN |
| ELECTRICAL-Final | 4/27/2022 | Partial Approval | JOHN KLARIN |
| BUILDING-Rough-Frame | 4/29/2022 | Approved | JOHN KLARIN |
| ELECTRICAL-Final | 4/29/2022 | Approved | JOHN KLARIN |
| Final | 4/29/2022 | Corrections Issued | JOHN KLARIN |
| Green Building Final | 4/29/2022 | Approved | JOHN KLARIN |
| HVAC-Final | 4/29/2022 | Approved | JOHN KLARIN |
| PLUMBING-Final | 4/29/2022 | Approved | JOHN KLARIN |
| SGSOV-Seismic Gas S/O Valve | 4/29/2022 | SGSOV Approved | JOHN KLARIN |
| Service/Power Release | 4/29/2022 | Not Ready for Inspection | JOHN KLARIN |
| Smoke Detectors | 4/29/2022 | Approved | JOHN KLARIN |
| Verify Sprinkler Sign Off | 4/29/2022 | Approved | JOHN KLARIN |
| Final | 5/6/2022 | OK to Issue CofO | EUGENE CASSIDY |
| Service/Power Release | 5/6/2022 | Approved | EUGENE CASSIDY |
| Service/Power Release | 5/10/2022 | Approved | EUGENE CASSIDY |