3828 S EDGEHILL DR 90008

Certificate Information: 3828 S EDGEHILL DR 90008

Application / Permit
21010-10000-02929
Plan Check / Job No.
B21LA11137
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan Convert existing Garage into an accessory dwelling unit per state law GSC 65852.2(e)(1)(A).
Permit Issued
Issued on 12/23/2021
Issuing Office
Current Status
CofO Issued on 2/5/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/14/2021 APPLICANT
Assigned to Plan Check Engineer 6/15/2021 MICHAEL LOPEZ
Corrections Issued 6/21/2021 MICHAEL LOPEZ
Applicant returned to address corrections 11/17/2021 MICHAEL LOPEZ
Plan Check Approved 11/24/2021 MICHAEL LOPEZ
Issued 12/23/2021 APPLICANT
CofO in Progress 1/25/2024 ANTHONY EGSON
Permit Finaled 2/5/2024 DEROLD HAUFF
Permit Finaled 2/5/2024 DEROLD HAUFF
CofO Issued 2/5/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/25/2021 WALLIE JONG
Sewer availability Cleared 8/25/2021 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 8/26/2021 WALLIE JONG
Construction within easement Cleared 11/13/2021 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/14/2022 Not Ready for Inspection ANTHONY EGSON
Sewer 9/14/2022 Not Ready for Inspection ANTHONY EGSON
ELECTRICAL-Rough 12/30/2022 Not Ready for Inspection ANTHONY EGSON
Sewer 12/30/2022 Corrections Issued ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 1/24/2023 Partial Approval ANTHONY EGSON
PLUMBING-Rough 1/24/2023 Approved ANTHONY EGSON
Sewer 1/24/2023 Approved ANTHONY EGSON
Underground Mechanical 1/24/2023 Partial Approval ANTHONY EGSON
Footing/Foundation/Slab 1/27/2023 Approved ANTHONY EGSON
BUILDING-Rough-Frame 3/13/2023 Not Ready for Inspection ANTHONY EGSON
ELECTRICAL-Rough 3/13/2023 Corrections Issued ANTHONY EGSON
Green Building Rough 3/13/2023 Approved ANTHONY EGSON
PLUMBING-Rough 3/13/2023 Corrections Issued ANTHONY EGSON
ELECTRICAL-Rough 3/17/2023 Approved ANTHONY EGSON
Interior/Exterior Lathing 3/17/2023 Approved ANTHONY EGSON
PLUMBING-Rough 4/24/2023 Approved ANTHONY EGSON
Wood Frame 4/28/2023 Partial Approval ANTHONY EGSON
Deputy Drilled-In Anchors 5/2/2023 Approved ANTHONY EGSON
Insulation 5/11/2023 Corrections Issued ANTHONY EGSON
Insulation 5/24/2023 Approved ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 6/8/2023 Approved ANTHONY EGSON
Drywall Nailing 6/27/2023 Approved ANTHONY EGSON
BUILDING-Rough-Frame 9/27/2023 Approved ANTHONY EGSON
Final 9/27/2023 Corrections Issued ANTHONY EGSON
Green Building Final 9/27/2023 Not Ready for Inspection ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 9/27/2023 SGSOV Not Required ANTHONY EGSON
Smoke Detectors 9/27/2023 Approved ANTHONY EGSON
ELECTRICAL-Final 11/16/2023 Approved ANTHONY EGSON
Final 11/16/2023 Corrections Issued ANTHONY EGSON
Green Building Final 11/16/2023 Approved ANTHONY EGSON
HVAC-Final 11/16/2023 Approved ANTHONY EGSON
PLUMBING-Final 11/16/2023 Approved ANTHONY EGSON
Final 1/25/2024 OK to Issue CofO ANTHONY EGSON