4289 E SAN RAFAEL AVE 90065
Certificate Information: 4289 E SAN RAFAEL AVE 90065
- Application / Permit
- 21010-10000-02854
- Plan Check / Job No.
- B21LA10947
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) 32'-6"x14'-9" DETACHED ACCESSORY DWELLING UNIT PER( LAMC 12.22 A33 C AND D)
- Permit Issued
- Issued on 5/3/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 5/9/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/14/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/22/2021 | MINA HABIB |
| Corrections Issued | 7/29/2021 | MINA HABIB |
| Quality Review Completed | 8/4/2021 | ALLEN MANALANSAN |
| Building Plans Picked Up | 8/17/2021 | APPLICANT |
| Applicant returned to address corrections | 2/1/2022 | MINA HABIB |
| Applicant returned to address corrections | 2/4/2022 | MINA HABIB |
| Applicant returned to address corrections | 2/14/2022 | MINA HABIB |
| Applicant returned to address corrections | 2/15/2022 | MINA HABIB |
| Applicant returned to address corrections | 4/22/2022 | MINA HABIB |
| Plan Check Approved | 5/2/2022 | MINA HABIB |
| Issued | 5/3/2022 | APPLICANT |
| CofO in Progress | 5/6/2024 | OSVALDO PARAMO |
| Permit Finaled | 5/9/2024 | DEROLD HAUFF |
| CofO Issued | 5/9/2024 | DEROLD HAUFF |
| Permit Finaled | 5/9/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 9/16/2021 | RENZ SORIANO |
| BHO/Hillside ordinance | Cleared | 9/16/2021 | RENZ SORIANO |
| BHO/Hillside ordinance | Cleared | 9/16/2021 | RENZ SORIANO |
| BHO/Hillside ordinance | Cleared | 9/16/2021 | RENZ SORIANO |
| BHO/Hillside ordinance | Cleared | 9/16/2021 | RENZ SORIANO |
| Street Frontage | Cleared | 9/16/2021 | RENZ SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 9/22/2021 | RENZ SORIANO |
| Sewer availability | Cleared | 9/22/2021 | RENZ SORIANO |
| Roof/Waste drainage to street | Cleared | 9/27/2021 | RENZ SORIANO |
| Grading Pre-Inspection | Cleared | 10/19/2021 | PATRICK MISCHLICH |
| Specific Plan | Cleared | 12/8/2021 | NASHYA JENSEN |
| Hydrant and Access approval | Cleared | 12/14/2021 | ROBERT DUFF |
| Miscellaneous | Cleared | 12/14/2021 | MAYELA VILLA |
| GPI Written Notices | Cleared | 4/22/2022 | MINA HABIB |
| Green Code | Cleared | 4/22/2022 | MINA HABIB |
Contact Information
| Contractor | Gettler Construction Inc; Lic. No.: 1030066-B | 16458 BOLSA CHICA ST #502 HUNTINGTON BEACH, CA 92649 |
| Engineer | Mahn,, Jonathan Edward; Lic. No.: C60293 | 12848 FOOTHILL BLVD SYLMAR, CA 91381 |
| Engineer | Phillips,, Craig Richard; Lic. No.: C69673 | 2123 VESTAL AVE LOS ANGELES, CA 90026 |
| Geologist | Triebold,, Mark John; Lic. No.: EG1796 | 6906 QUITO COURT CAMARILLO, CA 93012 |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/1/2022 | Approved | OSVALDO PARAMO |
| Deputy Reinf. Concrete | 8/1/2022 | Conditional Approval | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 8/4/2022 | Partial Approval | OSVALDO PARAMO |
| Piling/Pier/Caisson | 8/4/2022 | Partial Approval | OSVALDO PARAMO |
| Sewer | 9/7/2022 | Partial Approval | OSVALDO PARAMO |
| Deputy Reinf. Concrete | 9/22/2022 | Conditional Approval | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 9/23/2022 | Not Ready for Inspection | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 9/26/2022 | Corrections Issued | OSVALDO PARAMO |
| Footing/Foundation/Slab | 9/26/2022 | Not Ready for Inspection | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 9/29/2022 | Partial Approval | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 12/1/2022 | Not Ready for Inspection | OSVALDO PARAMO |
| Wood Frame | 12/1/2022 | Not Ready for Inspection | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 12/6/2022 | Partial Approval | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 1/11/2023 | Corrections Issued | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 1/11/2023 | Partial Approval | ALIZAH MAYAGOITIA |
| Green Building Rough | 1/11/2023 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Verify Sprinkler Sign Off | 1/11/2023 | Corrections Issued | ALIZAH MAYAGOITIA |
| Underground Mechanical | 2/2/2023 | Partial Approval | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 4/18/2023 | Corrections Issued | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 4/18/2023 | Approved | OSVALDO PARAMO |
| Gas Test | 4/18/2023 | Not Ready for Inspection | OSVALDO PARAMO |
| HVAC-Rough | 4/18/2023 | Approved | OSVALDO PARAMO |
| PLUMBING-Rough | 4/18/2023 | Corrections Issued | OSVALDO PARAMO |
| ELECTRICAL-Rough | 5/1/2023 | Approved | OSVALDO PARAMO |
| PLUMBING-Rough | 5/1/2023 | Approved | OSVALDO PARAMO |
| HVAC-Rough | 5/4/2023 | Approved | OSVALDO PARAMO |
| Interior/Exterior Lathing | 5/4/2023 | Partial Approval | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 5/9/2023 | Approved | OSVALDO PARAMO |
| Green Building Rough | 5/9/2023 | Approved | OSVALDO PARAMO |
| Verify Sprinkler Sign Off | 5/9/2023 | Approved | OSVALDO PARAMO |
| Insulation | 5/15/2023 | Approved | OSVALDO PARAMO |
| Drywall Nailing | 6/14/2023 | Approved | OSVALDO PARAMO |
| PLUMBING-Rough | 6/14/2023 | Approved | OSVALDO PARAMO |
| Shower Pan | 8/28/2023 | Approved | JOSH MEISTER |
| Interior/Exterior Lathing | 9/14/2023 | Approved | JOSH MEISTER |
| Final | 11/9/2023 | Corrections Issued | OSVALDO PARAMO |
| Footing/Foundation/Slab | 11/9/2023 | Approved | OSVALDO PARAMO |
| Green Building Final | 11/9/2023 | Approved | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 11/9/2023 | SGSOV Approved | OSVALDO PARAMO |
| Service/Power Release | 11/9/2023 | Not Ready for Inspection | OSVALDO PARAMO |
| Smoke Detectors | 11/9/2023 | Not Ready for Inspection | OSVALDO PARAMO |
| ELECTRICAL-Final | 12/19/2023 | Approved | OSVALDO PARAMO |
| Gas Test | 12/19/2023 | Approved | OSVALDO PARAMO |
| HVAC-Final | 12/19/2023 | Approved | OSVALDO PARAMO |
| PLUMBING-Final | 12/19/2023 | Approved | OSVALDO PARAMO |
| Service/Power Release | 12/19/2023 | Not Ready for Inspection | OSVALDO PARAMO |
| Smoke Detectors | 12/19/2023 | Approved | OSVALDO PARAMO |
| Final | 5/2/2024 | OK to Issue CofO | OSVALDO PARAMO |
| Service/Power Release | 5/2/2024 | Approved | OSVALDO PARAMO |