228 N SOTO ST 90033

Certificate Information: 228 N SOTO ST 90033

Application / Permit
21010-10000-02845
Plan Check / Job No.
B21LA10932
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
NEW 4 STORY TYPE VA 42 UNITS (1 MANAGER, 1 ELI + 1 VLI + 39 LI = 100%) AFFORDABLE HOUSING APARTMENT, TOC TIER 3 WITH ADDITIONAL INCENTIVES
Permit Issued
Issued on 5/16/2023
Issuing Office
Valley
Current Status
CofO Issued on 11/18/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Plan Check Approved 12/13/2022 KEVIN MORALES
Issued 5/16/2023 APPLICANT
TCO Issued (Expire Date: 04-21-2026) 10/23/2025 RAFAEL ESPINOZA
CofO in Progress 11/18/2025 RAFAEL CORTES
Permit Finaled 11/18/2025 ERNESTO CORRAL
CofO Issued 11/18/2025 ERNESTO CORRAL
Permit Finaled 11/18/2025 ERNESTO CORRAL

Permit Application Clearance Information

Green Code Cleared 2/15/2022 AARON COSTA
Hydrant and Access approval Cleared 3/5/2022 GILBERT URREA
Address approval Cleared 3/18/2022 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 3/18/2022 JEANETTE VONG
Sewer availability Cleared 3/18/2022 JEANETTE VONG
Grading Pre-Inspection Cleared 3/29/2022 KEVIN MORALES
Metro Rail approval Cleared 4/8/2022 SHINE LING
Historic Resource Verification Cleared 8/11/2022 MAX LODER
GPI Written Notices Cleared 8/12/2022 KEVIN MORALES
Building over 36-ft Cleared 8/19/2022 CALOSHA APPROVED
Density Bonus 12.22.A.31 Cleared 8/23/2022 NICHOLAS KAWAZOE
Highway dedication Cleared 10/17/2022 ABEL CASILLAS
Low Impact Development Cleared 11/7/2022 AMMAR ELTAWIL
Roof/Waste drainage to street Cleared 11/8/2022 ABEL CASILLAS
DAS Clearance Cleared 11/14/2022 KEVIN MORALES
Fire Marshal Fire Life Safety Cleared 11/22/2022 MENOA AGHAJANI
Clean Up Green Up Cleared 12/12/2022 JAZMIN ROQUE
Frnt yard landscape/Water mgmt Cleared 12/12/2022 JAZMIN ROQUE
Miscellaneous Cleared 12/12/2022 JAZMIN ROQUE
Miscellaneous Cleared 12/12/2022 JAZMIN ROQUE
Opn space landscape/Water mgmt Cleared 12/12/2022 JAZMIN ROQUE
Redevelopment Project Area Cleared 12/12/2022 DAVID URITA

Contact Information

Architect Hefner,, Charles David; Lic. No.: C23963 6320 VAN NUYS BOULEVARD #225      VAN NUYS, CA 91401
Contractor Mid Construction Group; Lic. No.: 1030925-B 5850 W 3RD STREET #160      LOS ANGELES, CA 90036
Engineer Berkoz,, Ertunga; Lic. No.: S2504 4665 ELLENITA AVE      TARZANA, CA 91356
Engineer Doss,, Richard; Lic. No.: C48987 30141 AGOURA RD 200      AGOURA HILLS, CA 91301
Engineer Lee,, Allen C; Lic. No.: GE2781 11823 SLAUSON AVE STE 46      SANTA FE SPRINGS, CA 90670

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/30/2023 Approved RAFAEL ESPINOZA
Deputy Grading 6/2/2023 Conditional Approval LARRY ARNICK
Deputy Grading 6/5/2023 Conditional Approval MICHAEL ROSENBERG
Footing/Foundation/Slab 7/17/2023 Not Ready for Inspection RAFAEL ESPINOZA
METHANE-Barrier 7/17/2023 Approved RAFAEL ESPINOZA
METHANE-Subgrade 7/17/2023 Approved RAFAEL ESPINOZA
Footing/Foundation/Slab 8/18/2023 Partial Approval LARRY ARNICK
Excavation/Setback/Form/Re-Bar 8/25/2023 Partial Inspection RAFAEL ESPINOZA
Footing/Foundation/Slab 8/25/2023 Partial Approval RAFAEL ESPINOZA
Excavation/Setback/Form/Re-Bar 8/29/2023 Not Ready for Inspection LARRY ARNICK
Footing/Foundation/Slab 8/29/2023 Not Ready for Inspection LARRY ARNICK
Masonry Wall/Backfill 8/29/2023 Partial Approval LARRY ARNICK
Reinforced Masonry Frame 8/29/2023 Partial Approval LARRY ARNICK
Excavation/Setback/Form/Re-Bar 8/31/2023 Partial Approval LARRY ARNICK
Reinforced Concrete Frame 8/31/2023 Partial Approval LARRY ARNICK
Green Building Rough 10/2/2023 Not Ready for Inspection RAFAEL ESPINOZA
METHANE-Rough 10/2/2023 Approved RAFAEL ESPINOZA
Structural Steel Frame 10/2/2023 Partial Inspection RAFAEL ESPINOZA
Verify Sprinkler Sign Off 10/2/2023 Not Ready for Inspection RAFAEL ESPINOZA
Wood Frame 10/2/2023 Partial Inspection RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 10/6/2023 Partial Approval RAFAEL ESPINOZA
Green Building Rough 10/6/2023 Not Ready for Inspection RAFAEL ESPINOZA
Structural Steel Frame 10/6/2023 Partial Approval RAFAEL ESPINOZA
Verify Sprinkler Sign Off 10/6/2023 Not Ready for Inspection RAFAEL ESPINOZA
Deputy Wood Construction 10/13/2023 Conditional Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 10/13/2023 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 10/24/2023 Partial Approval RAFAEL ESPINOZA
Green Building Rough 10/24/2023 Approved RAFAEL ESPINOZA
Verify Sprinkler Sign Off 10/24/2023 Not Ready for Inspection RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 11/2/2023 Partial Approval RAFAEL ESPINOZA
Verify Sprinkler Sign Off 11/22/2023 Not Ready for Inspection NICK DANERI
Wood Frame 11/22/2023 Partial Approval NICK DANERI
Pre-Inspection 12/21/2023 Partial Inspection NICK DANERI
Wood Frame 1/3/2024 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 1/17/2024 Partial Approval RONALD JIMENEZ
Pre-Inspection 1/24/2024 Corrections Issued RAFAEL ESPINOZA
Insulation 3/6/2024 Partial Approval RAFAEL ESPINOZA
Wood Frame 3/6/2024 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 3/15/2024 Partial Approval RAFAEL ESPINOZA
Insulation 3/15/2024 Partial Approval RAFAEL ESPINOZA
Verify Sprinkler Sign Off 3/15/2024 Partial Inspection RAFAEL ESPINOZA
Wood Frame 3/15/2024 Partial Approval RAFAEL ESPINOZA
Verify Sprinkler Sign Off 3/21/2024 Partial Inspection RAFAEL ESPINOZA
Wood Frame 3/21/2024 Partial Approval RAFAEL ESPINOZA
Deputy Wood Construction 3/22/2024 Conditional Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 3/22/2024 Approved RAFAEL ESPINOZA
Insulation 4/2/2024 Partial Approval RAFAEL ESPINOZA
Verify Sprinkler Sign Off 4/2/2024 Not Ready for Inspection RAFAEL ESPINOZA
Wood Frame 4/2/2024 Not Ready for Inspection RAFAEL ESPINOZA
Verify Sprinkler Sign Off 4/5/2024 Not Ready for Inspection LARRY ARNICK
Wood Frame 4/5/2024 Not Ready for Inspection LARRY ARNICK
Drywall Nailing 4/12/2024 Partial Approval RAFAEL ESPINOZA
Insulation 4/12/2024 Partial Approval RAFAEL ESPINOZA
Insulation 4/25/2024 Partial Approval RAFAEL ESPINOZA
T-Bar Ceiling 4/25/2024 Not Ready for Inspection RAFAEL ESPINOZA
Insulation 5/2/2024 Partial Inspection RAFAEL ESPINOZA
Drywall Nailing 5/10/2024 Partial Inspection JEFFREY FULTON
Wood Frame 5/10/2024 Partial Inspection JEFFREY FULTON
Insulation 5/13/2024 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 5/29/2024 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 6/4/2024 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 6/11/2024 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 6/17/2024 Corrections Issued RAFAEL ESPINOZA
Drywall Nailing 6/21/2024 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 7/5/2024 Not Ready for Inspection RAFAEL ESPINOZA
Structural Steel Frame 7/17/2024 Not Ready for Inspection RAFAEL ESPINOZA
Verify Sprinkler Sign Off 7/17/2024 Not Ready for Inspection RAFAEL ESPINOZA
Wood Frame 7/17/2024 No Access for Inspection RAFAEL ESPINOZA
Light Gage Steel Frame 7/18/2024 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 7/22/2024 Corrections Issued RAFAEL ESPINOZA
Drywall Nailing 7/30/2024 Partial Approval LARRY ARNICK
Interior/Exterior Lathing 7/31/2024 Approved RONALD JIMENEZ
Light Gage Steel Frame 8/5/2024 Partial Inspection JEFFREY FULTON
Light Gage Steel Frame 8/9/2024 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 8/15/2024 Not Ready for Inspection RONALD JIMENEZ
Drywall Nailing 8/19/2024 Not Ready for Inspection RONALD JIMENEZ
Drywall Nailing 8/20/2024 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 9/18/2024 Partial Approval RAFAEL CORTES
Excavation/Setback/Form/Re-Bar 10/29/2024 Partial Approval RAFAEL CORTES
Masonry Wall/Backfill 11/13/2024 Partial Approval RAFAEL CORTES
Masonry Wall/Backfill 11/15/2024 Not Ready for Inspection RAFAEL CORTES
Masonry Wall/Backfill 11/18/2024 Not Ready for Inspection RAFAEL CORTES
Masonry Wall/Backfill 11/20/2024 Not Ready for Inspection RAFAEL CORTES
Masonry Wall/Backfill 11/27/2024 Not Ready for Inspection RAFAEL CORTES
Masonry Wall/Backfill 12/2/2024 Partial Approval RAFAEL CORTES
Light Gage Steel Frame 12/23/2024 Partial Approval RAFAEL ESPINOZA
Verify Sprinkler Sign Off 12/23/2024 Partial Inspection RAFAEL ESPINOZA
Wood Frame 12/23/2024 Partial Inspection RAFAEL ESPINOZA
Light Gage Steel Frame 1/16/2025 Partial Approval RONALD JIMENEZ
Drywall Nailing 1/28/2025 Corrections Issued RAFAEL CORTES
Light Gage Steel Frame 2/3/2025 Partial Approval RAFAEL CORTES
Light Gage Steel Frame 2/5/2025 Partial Approval RAFAEL CORTES
Light Gage Steel Frame 2/6/2025 Partial Approval RAFAEL CORTES
Drywall Nailing 2/10/2025 Partial Approval RONALD JIMENEZ
Light Gage Steel Frame 2/25/2025 Approved RONALD JIMENEZ
Drywall Nailing 3/4/2025 Partial Approval RAFAEL CORTES
Light Gage Steel Frame 3/7/2025 No Access for Inspection RAFAEL CORTES
Light Gage Steel Frame 3/27/2025 No Access for Inspection RAFAEL CORTES
Light Gage Steel Frame 3/28/2025 Partial Approval RAFAEL CORTES
Final 4/4/2025 Not Ready for Inspection RAFAEL CORTES
Footing/Foundation/Slab 4/4/2025 Not Ready for Inspection RAFAEL CORTES
Green Building Final 4/4/2025 Not Ready for Inspection RAFAEL CORTES
SGSOV-Seismic Gas S/O Valve 4/4/2025 SGSOV Not Ready RAFAEL CORTES
Smoke Detectors 4/4/2025 Not Ready for Inspection RAFAEL CORTES
Verify Sprinkler Sign Off 4/4/2025 Not Ready for Inspection RAFAEL CORTES
Wood Frame 4/4/2025 Not Ready for Inspection RAFAEL CORTES
Excavation/Setback/Form/Re-Bar 5/5/2025 Partial Approval RAFAEL CORTES
Masonry Wall/Backfill 5/5/2025 Partial Approval RAFAEL CORTES
Masonry Wall/Backfill 5/13/2025 Approved RONALD JIMENEZ
Light Gage Steel Frame 6/2/2025 Corrections Issued RAFAEL CORTES
Special/Order Compliance 6/13/2025 Approved RONALD JIMENEZ
Final 9/18/2025 Corrections Issued RAFAEL CORTES
Footing/Foundation/Slab 9/18/2025 Not Ready for Inspection RAFAEL CORTES
Green Building Final 9/18/2025 Not Ready for Inspection RAFAEL CORTES
SGSOV-Seismic Gas S/O Valve 9/18/2025 SGSOV Approved RAFAEL CORTES
Smoke Detectors 9/18/2025 Not Ready for Inspection RAFAEL CORTES
Verify Sprinkler Sign Off 9/18/2025 Approved RAFAEL CORTES
Wood Frame 9/18/2025 Not Ready for Inspection RAFAEL CORTES
Final 9/26/2025 Not Ready for Inspection RAFAEL CORTES
Footing/Foundation/Slab 9/26/2025 Not Ready for Inspection RAFAEL CORTES
Green Building Final 9/26/2025 Not Ready for Inspection RAFAEL CORTES
Smoke Detectors 9/26/2025 Not Ready for Inspection RAFAEL CORTES
Wood Frame 9/26/2025 Not Ready for Inspection RAFAEL CORTES
Special/Order Compliance 9/29/2025 No Access for Inspection RAFAEL CORTES
Final 10/14/2025 Not Ready for Inspection RAFAEL CORTES
Footing/Foundation/Slab 10/14/2025 Not Ready for Inspection RAFAEL CORTES
Green Building Final 10/14/2025 Approved RAFAEL CORTES
Smoke Detectors 10/14/2025 Approved RAFAEL CORTES
Wood Frame 10/14/2025 Not Ready for Inspection RAFAEL CORTES
Final 10/22/2025 OK for TCO RAFAEL CORTES
Footing/Foundation/Slab 10/22/2025 Approved RAFAEL CORTES
Wood Frame 10/22/2025 Approved RAFAEL CORTES
Final 11/13/2025 Not Ready for Inspection RAFAEL CORTES
Special/Order Compliance 11/13/2025 Partial Approval SCOTT SOBEL
Final 11/14/2025 OK to Issue CofO RAFAEL CORTES