1575 W 46TH ST 90062
Certificate Information: 1575 W 46TH ST 90062
- Application / Permit
- 21010-10000-02843
- Plan Check / Job No.
- B21LA10909
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED 2 STORY ADU
- Permit Issued
- Issued on 3/23/2022
- Issuing Office
- Current Status
- Issued on 3/23/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/10/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/15/2021 | JOE VO |
| Corrections Issued | 7/20/2021 | JOE VO |
| Quality Review Completed | 7/25/2021 | PRANITA SHAH |
| Applicant returned to address corrections | 3/1/2022 | JOE VO |
| Plan Check Approved | 3/16/2022 | JOE VO |
| Issued | 3/23/2022 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 10/21/2021 | WALLIE JONG |
| Sewer availability | Cleared | 10/21/2021 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 11/18/2021 | WALLIE JONG |
| Hydrant and Access approval | Cleared | 2/7/2022 | DWAYNE LAURENT |
| Low Impact Development | Cleared | 3/3/2022 | TA ANH |
| Roof/Waste drainage to street | Cleared | 3/8/2022 | WALLIE JONG |
Contact Information
| Contractor | J B Builders Fire Protection Inc; Lic. No.: 923970-B | , |
| Contractor | J B New Construction Inc; Lic. No.: 923970-B | , |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 7/12/2022 | Partial Approval | SABAS ALONSO |
| Footing/Foundation/Slab | 7/26/2022 | Approved | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 8/5/2022 | Partial Approval | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 9/22/2022 | Approved | SABAS ALONSO |
| Green Building Rough | 10/20/2022 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 10/20/2022 | Partial Approval | SABAS ALONSO |
| PLUMBING-Rough | 11/1/2022 | Partial Approval | SABAS ALONSO |
| BUILDING-Rough-Frame | 11/9/2022 | Corrections Issued | SABAS ALONSO |
| ELECTRICAL-Rough | 11/9/2022 | Approved | SABAS ALONSO |
| HVAC-Rough | 11/9/2022 | Corrections Issued | SABAS ALONSO |
| PLUMBING-Rough | 11/9/2022 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 11/17/2022 | Approved | SABAS ALONSO |
| HVAC-Rough | 11/17/2022 | Approved | SABAS ALONSO |
| Insulation | 11/17/2022 | Approved | SABAS ALONSO |
| Verify Sprinkler Sign Off | 11/17/2022 | Approved | SABAS ALONSO |
| Drywall Nailing | 11/30/2022 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 12/30/2022 | Partial Approval | SABAS ALONSO |
| Shower Pan | 12/30/2022 | Corrections Issued | SABAS ALONSO |
| Interior/Exterior Lathing | 1/4/2023 | Approved | SABAS ALONSO |
| Shower Pan | 1/4/2023 | Approved | SABAS ALONSO |
| Rough-Elec/Plmb/HVAC | 1/27/2023 | Approved | SABAS ALONSO |
| Underground Mechanical | 1/27/2023 | Approved | SABAS ALONSO |
| Service/Power Release | 3/29/2023 | Corrections Issued | SABAS ALONSO |
| Final | 7/11/2023 | Corrections Issued | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 7/11/2023 | SGSOV Not Ready | SABAS ALONSO |
| Service/Power Release | 7/11/2023 | Not Ready for Inspection | SABAS ALONSO |
| Smoke Detectors | 7/11/2023 | Approved | SABAS ALONSO |
| Final | 10/31/2023 | Not Ready for Inspection | CRAIG DAVIS |
| SGSOV-Seismic Gas S/O Valve | 10/31/2023 | SGSOV Approved | CRAIG DAVIS |
| Service/Power Release | 10/31/2023 | Not Ready for Inspection | CRAIG DAVIS |
| Final | 12/19/2023 | Corrections Issued | SABAS ALONSO |
| Service/Power Release | 12/19/2023 | Not Ready for Inspection | SABAS ALONSO |