10848 W HESBY ST 91601

Certificate Information: 10848 W HESBY ST 91601

Application / Permit
21010-10000-02835
Plan Check / Job No.
B21LA10866
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 32'-0" X 35'6" ACCESSORY DWELLING UNIT AT REAR OF LOT SEPARATE PERMIT REQUIRED FOR GARAGE DEMO (21019-1000-04531)
Permit Issued
Issued on 1/13/2022
Issuing Office
Current Status
CofO Issued on 10/14/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/14/2021 APPLICANT
Assigned to Plan Check Engineer 6/17/2021 RACHEL BEYENE
Corrections Issued 6/25/2021 RACHEL BEYENE
Applicant returned to address corrections 12/17/2021 GEORGE ALVAREZ
Plan Check Approved 12/20/2021 GEORGE ALVAREZ
Issued 1/13/2022 APPLICANT
Building Plans Picked Up 1/20/2022 APPLICANT
CofO in Progress 9/5/2025 JAVIER RAMOS JR
No Progress 9/5/2025 JAVIER RAMOS JR
CofO in Progress 9/5/2025 JAVIER RAMOS JR
Permit Finaled 10/14/2025 RUBEN SALAS
CofO Issued 10/14/2025 RUBEN SALAS
Permit Finaled 10/14/2025 RUBEN SALAS

Permit Application Clearance Information

Hydrant and Access approval Cleared 10/10/2021 RUEL COLE
Low Impact Development Cleared 12/8/2021 SUNG JOON WON
Address approval Cleared 12/9/2021 CHRISTINE KEUSHGUERIAN
Roof/Waste drainage to street Cleared 12/9/2021 CHRISTINE KEUSHGUERIAN
Eng Process Fee Ord 176,300 Cleared 12/14/2021 CHRISTINE KEUSHGUERIAN
Sewer availability Cleared 12/14/2021 CHRISTINE KEUSHGUERIAN
Public Works-Highway Ded. Cleared 12/14/2021 CHRISTINE KEUSHGUERIAN
Public Works-Sewers Cleared 12/14/2021 CHRISTINE KEUSHGUERIAN

Contact Information

Contractor Owner-Builder       ,
Engineer Khatchadourian,, Vicken; Lic. No.: S3141 1221 N CEDAR ST      GLENDALE, CA 92107

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/22/2022 Partial Approval MISAEL ESPARZA
Footing/Foundation/Slab 4/26/2022 Corrections Issued JACK KARGODORIAN
Footing/Foundation/Slab 4/29/2022 Corrections Issued CHRISTOPHE COCHRAN
Excavation/Setback/Form/Re-Bar 5/3/2022 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 5/26/2022 Partial Approval CALEB MEISTER
ELECTRICAL-Rough 6/13/2022 Approved ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 6/13/2022 Partial Approval ARAM AVEDISIAN
HVAC-Rough 6/13/2022 Approved ARAM AVEDISIAN
PLUMBING-Rough 6/13/2022 Approved ARAM AVEDISIAN
Verify Sprinkler Sign Off 6/13/2022 Approved ARAM AVEDISIAN
Wood Frame 6/17/2022 Partial Approval JOHN HAYES
BUILDING-Rough-Frame 6/30/2022 Approved JOHN HAYES
Green Building Rough 6/30/2022 Approved JOHN HAYES
Interior/Exterior Lathing 6/30/2022 Partial Approval JOHN HAYES
Drywall Nailing 7/8/2022 Approved JOHN HAYES
Interior/Exterior Lathing 7/8/2022 Not Ready for Inspection JOHN HAYES
Gas Test 8/17/2022 Not Ready for Inspection ALAN MORELOS
Interior/Exterior Lathing 8/17/2022 Approved ALAN MORELOS
ELECTRICAL-Final 8/30/2022 Not Ready for Inspection JOHN HAYES
Final 8/30/2022 Not Ready for Inspection JOHN HAYES
Gas Test 8/30/2022 Not Ready for Inspection JOHN HAYES
HVAC-Final 8/30/2022 Not Ready for Inspection JOHN HAYES
PLUMBING-Final 8/30/2022 Not Ready for Inspection JOHN HAYES
ELECTRICAL-Final 9/13/2022 Partial Approval JOHN HAYES
Gas Test 9/13/2022 Partial Approval JOHN HAYES
HVAC-Final 9/13/2022 Partial Approval JOHN HAYES
PLUMBING-Final 9/13/2022 Partial Approval JOHN HAYES
Service/Power Release 9/13/2022 Not Ready for Inspection JOHN HAYES
Smoke Detectors 9/13/2022 Partial Approval JOHN HAYES
Final 4/28/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 4/28/2025 Approved ROBERTO PALACIOS-LOPEZ
Green Building Final 4/28/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 4/28/2025 SGSOV Approved ROBERTO PALACIOS-LOPEZ
Service/Power Release 4/28/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Smoke Detectors 4/28/2025 Approved ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Final 9/4/2025 Approved JAVIER RAMOS JR
Final 9/4/2025 OK to Issue CofO JAVIER RAMOS JR
Green Building Final 9/4/2025 Approved JAVIER RAMOS JR