1211 N EL PASO DR 90065

Certificate Information: 1211 N EL PASO DR 90065

Application / Permit
21010-10000-02832
Plan Check / Job No.
B21LA10838
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
***ePlan - Convert existing detached garage to ADU 20'x20'
Permit Issued
Issued on 7/1/2021
Issuing Office
Current Status
CofO Issued on 4/25/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/14/2021 APPLICANT
Assigned to Plan Check Engineer 6/15/2021 JOE VO
Corrections Issued 6/15/2021 JOE VO
Plan Check Approved 6/29/2021 JOE VO
Issued 7/1/2021 APPLICANT
CofO in Progress 4/18/2022 HAMIK HARTOUNIAN
CofO Issued 4/25/2022 DEROLD HAUFF
Permit Finaled 4/25/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 6/23/2021 CELINA MORENO
Sewer availability Cleared 6/23/2021 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 6/28/2021 CELINA MORENO

Contact Information

Contractor Kafe Design & Construction; Lic. No.: 977712-B       ,

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/2/2021 Corrections Issued HAMIK HARTOUNIAN
Rough-Elec/Plmb/HVAC 8/2/2021 Not Ready for Inspection HAMIK HARTOUNIAN
PLUMBING-Rough 8/3/2021 Not Ready for Inspection HAMIK HARTOUNIAN
Pre-Inspection 8/3/2021 Corrections Issued HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 10/12/2021 Corrections Issued HAMIK HARTOUNIAN
BUILDING-Rough-Frame 10/15/2021 Not Ready for Inspection HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 10/15/2021 Corrections Issued HAMIK HARTOUNIAN
Rough-Elec/Plmb/HVAC 10/15/2021 Not Ready for Inspection HAMIK HARTOUNIAN
Deputy Drilled-In Anchors 10/20/2021 Approved HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 10/20/2021 Conditional Approval HAMIK HARTOUNIAN
PLUMBING-Rough 10/20/2021 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 10/27/2021 Not Ready for Inspection HAMIK HARTOUNIAN
Rough-Elec/Plmb/HVAC 10/27/2021 Partial Approval HAMIK HARTOUNIAN
Rough-Elec/Plmb/HVAC 11/2/2021 Not Ready for Inspection HAMIK HARTOUNIAN
Rough-Elec/Plmb/HVAC 11/5/2021 Approved HAMIK HARTOUNIAN
Special/Order Compliance 11/5/2021 Partial Inspection ALIZAH MAYAGOITIA
Insulation 11/9/2021 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 11/15/2021 Approved HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 11/15/2021 Approved HAMIK HARTOUNIAN
Drywall Nailing 11/18/2021 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 11/18/2021 Partial Approval HAMIK HARTOUNIAN
Interior/Exterior Lathing 12/3/2021 Approved HAMIK HARTOUNIAN
ELECTRICAL-Final 4/5/2022 Approved HAMIK HARTOUNIAN
Final 4/5/2022 Not Ready for Inspection HAMIK HARTOUNIAN
HVAC-Final 4/5/2022 Corrections Issued HAMIK HARTOUNIAN
PLUMBING-Final 4/5/2022 Approved HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 4/5/2022 SGSOV Approved HAMIK HARTOUNIAN
Smoke Detectors 4/5/2022 Approved HAMIK HARTOUNIAN
Final 4/18/2022 OK to Issue CofO HAMIK HARTOUNIAN