211 S VETERAN AVE 90024
Certificate Information: 211 S VETERAN AVE 90024
- Application / Permit
- 21010-10000-02820
- Plan Check / Job No.
- B21LA07577
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Recreation Room
- Work Description
- New detached recreation room and shower for the swimming pool.
- Permit Issued
- Issued on 12/15/2021
- Issuing Office
- Current Status
- CofO Issued on 10/3/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/22/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/26/2021 | HELEN NGUYEN |
| Corrections Issued | 6/8/2021 | HELEN NGUYEN |
| Quality Review Completed | 6/17/2021 | MICHAEL PEREZ |
| Building Plans Picked Up | 6/18/2021 | APPLICANT |
| Applicant returned to address corrections | 11/8/2021 | HELEN NGUYEN |
| Plan Check Approved | 12/15/2021 | HELEN NGUYEN |
| Issued | 12/15/2021 | APPLICANT |
| CofO in Progress | 9/30/2022 | RICHARD STEINBACH |
| Permit Finaled | 10/3/2022 | DANIEL ORRANTE |
| CofO Issued | 10/3/2022 | DANIEL ORRANTE |
| Permit Finaled | 10/3/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 7/26/2021 | ANTHONY MAINEZ |
| Specific Plan | Cleared | 10/13/2021 | VALERIA CEJA |
| Low Impact Development | Cleared | 10/15/2021 | SUNG JOON WON |
| Roof/Waste drainage to street | Cleared | 10/25/2021 | ANTHONY MAINEZ |
| GPI Written Notices | Cleared | 11/8/2021 | HELEN NGUYEN |
| Grading Pre-Inspection | Cleared | 11/8/2021 | HELEN NGUYEN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Basma,, Ali J; Lic. No.: C53080 | 21500 WYANDOTTE ST 106 CANOGA PARK, CA 91303 |
Inspector Information
| EVAN COOPER, (310) 914-3861 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/22/2021 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Underground Mechanical | 1/26/2022 | Corrections Issued | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 1/31/2022 | Approved | CARLOS MATAMOROS |
| PLUMBING-Rough | 1/31/2022 | Partial Approval | CARLOS MATAMOROS |
| Wood Frame | 2/22/2022 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Rough | 3/18/2022 | Corrections Issued | CHRISTOPHER WILSON |
| Pre-Inspection | 3/18/2022 | Partial Approval | CHRISTOPHER WILSON |
| ELECTRICAL-Rough | 3/22/2022 | Corrections Issued | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 3/24/2022 | Approved | CHRISTOPHER WILSON |
| Floor/Roof Diaphrgm/Shear Wall | 3/24/2022 | Corrections Issued | CHRISTOPHER WILSON |
| Shower Pan | 3/24/2022 | Approved | CHRISTOPHER WILSON |
| BUILDING-Rough-Frame | 4/5/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
| FLOOD-Proofing Certificate | 4/5/2022 | Approved | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 4/5/2022 | Approved | CARLOS MATAMOROS |
| Green Building Rough | 4/5/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
| HVAC-Rough | 4/5/2022 | Approved | CARLOS MATAMOROS |
| PLUMBING-Rough | 4/5/2022 | Approved | CARLOS MATAMOROS |
| Verify Sprinkler Sign Off | 4/5/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 4/27/2022 | Approved | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 4/27/2022 | Approved | CARLOS MATAMOROS |
| Insulation | 5/10/2022 | Approved | CLAYTON GRAHAM |
| Drywall Nailing | 5/23/2022 | Approved | BRENDAN LOONEY |
| Green Building Rough | 5/23/2022 | Approved | BRENDAN LOONEY |
| PLUMBING-Final | 9/1/2022 | Approved | CHRISTOPHER WILSON |
| ELECTRICAL-Final | 9/2/2022 | Approved | CARLOS MATAMOROS |
| HVAC-Final | 9/2/2022 | Approved | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 9/28/2022 | Approved | CARLOS MATAMOROS |
| Final | 9/28/2022 | Partial Approval | CARLOS MATAMOROS |
| Green Building Final | 9/28/2022 | Approved | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 9/28/2022 | SGSOV Approved | CARLOS MATAMOROS |
| Service/Power Release | 9/28/2022 | Approved | CARLOS MATAMOROS |
| Smoke Detectors | 9/28/2022 | Approved | CARLOS MATAMOROS |
| Verify Sprinkler Sign Off | 9/28/2022 | Approved | CARLOS MATAMOROS |
| Final | 9/30/2022 | OK to Issue CofO | MICHAEL PELHAM |