9504 N GOTHIC AVE 91343

Certificate Information: 9504 N GOTHIC AVE 91343

Application / Permit
21010-10000-02818
Plan Check / Job No.
B21LA10778
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ADU PER GCS 65852.2(e)(1)(b) and LAMC 12.22 A.33(c),(d) AND(g) . All work per WFPP
Permit Issued
Issued on 4/3/2022
Issuing Office
Current Status
CofO Issued on 10/22/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/8/2021 APPLICANT
Assigned to Plan Check Engineer 6/16/2021 LUKE GONZALES
Corrections Issued 6/16/2021 LUKE GONZALES
Applicant returned to address corrections 11/10/2021 SAMUEL GONZALEZ
Plan Check Approved 11/16/2021 SAMUEL GONZALEZ
Building Plans Picked Up 11/22/2021 APPLICANT
Issued 4/3/2022 APPLICANT
CofO in Progress 9/23/2022 RAUL OLAGI
Permit Finaled 10/22/2022 MICHAEL SMITH
CofO Issued 10/22/2022 MICHAEL SMITH
Permit Finaled 10/22/2022 MICHAEL SMITH

Permit Application Clearance Information

Construction near power lines Cleared 7/28/2021 WALTER RAMIREZ
Address approval Cleared 7/31/2021 ABDULLAH SADOZAI
Eng Process Fee Ord 176,300 Cleared 8/2/2021 ABDULLAH SADOZAI
Grading Pre-Inspection Cleared 8/24/2021 ALEXANDER ANDREWS
Roof/Waste drainage to street Cleared 10/7/2021 DAGOVERTO GUERRERO
Sewer availability Cleared 10/7/2021 DAGOVERTO GUERRERO

Contact Information

Contractor Shellmolly Construction; Lic. No.: 911257-B 8654 STATE ST      SOUTH GATE, CA 90280

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/11/2022 Not Ready for Inspection RAUL OLAGI
PLUMBING-Rough 4/11/2022 Corrections Issued RAUL OLAGI
Underground Mechanical 4/11/2022 Approved RAUL OLAGI
PLUMBING-Rough 4/21/2022 Partial Approval RAUL OLAGI
Sewer 4/21/2022 Not Ready for Inspection RAUL OLAGI
Footing/Foundation/Slab 4/25/2022 Approved RAUL OLAGI
Sewer 4/25/2022 Approved RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 5/3/2022 Partial Approval DEANDRE HOFFMAN
Floor/Roof Diaphrgm/Shear Wall 5/13/2022 Approved RAUL OLAGI
Green Building Rough 5/13/2022 Not Ready for Inspection RAUL OLAGI
PLUMBING-Rough 5/13/2022 Approved RAUL OLAGI
Verify Sprinkler Sign Off 5/13/2022 Approved RAUL OLAGI
BUILDING-Rough-Frame 5/18/2022 Partial Approval RAUL OLAGI
ELECTRICAL-Rough 5/18/2022 Approved RAUL OLAGI
HVAC-Rough 5/18/2022 Approved RAUL OLAGI
Insulation 5/23/2022 Approved RAUL OLAGI
Interior/Exterior Lathing 5/23/2022 Partial Approval RAUL OLAGI
Shower Pan 5/23/2022 Approved RAUL OLAGI
Drywall Nailing 5/31/2022 Approved RAUL OLAGI
Green Building Rough 5/31/2022 Approved RAUL OLAGI
Interior/Exterior Lathing 5/31/2022 Approved RAUL OLAGI
BUILDING-Rough-Frame 6/6/2022 Approved ALAN MORELOS
Interior/Exterior Lathing 6/6/2022 Approved ALAN MORELOS
SGSOV-Seismic Gas S/O Valve 8/15/2022 SGSOV Not Ready RAUL OLAGI
ELECTRICAL-Final 8/23/2022 Corrections Issued RAUL OLAGI
Final 8/23/2022 Corrections Issued RAUL OLAGI
Green Building Final 8/23/2022 Approved RAUL OLAGI
HVAC-Final 8/23/2022 Corrections Issued RAUL OLAGI
PLUMBING-Final 8/23/2022 Corrections Issued RAUL OLAGI
Smoke Detectors 8/23/2022 Approved RAUL OLAGI
ELECTRICAL-Final 9/7/2022 Approved RAUL OLAGI
Final 9/7/2022 Corrections Issued RAUL OLAGI
Gas Test 9/7/2022 Approved RAUL OLAGI
HVAC-Final 9/7/2022 Approved RAUL OLAGI
PLUMBING-Final 9/7/2022 Approved RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 9/7/2022 SGSOV Approved RAUL OLAGI
Service/Power Release 9/7/2022 Partial Inspection RAUL OLAGI
Final 9/22/2022 OK to Issue CofO RAUL OLAGI
Service/Power Release 9/22/2022 Approved RAUL OLAGI