9504 N GOTHIC AVE 91343
Certificate Information: 9504 N GOTHIC AVE 91343
- Application / Permit
- 21010-10000-02818
- Plan Check / Job No.
- B21LA10778
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ADU PER GCS 65852.2(e)(1)(b) and LAMC 12.22 A.33(c),(d) AND(g) . All work per WFPP
- Permit Issued
- Issued on 4/3/2022
- Issuing Office
- Current Status
- CofO Issued on 10/22/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/8/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/16/2021 | LUKE GONZALES |
| Corrections Issued | 6/16/2021 | LUKE GONZALES |
| Applicant returned to address corrections | 11/10/2021 | SAMUEL GONZALEZ |
| Plan Check Approved | 11/16/2021 | SAMUEL GONZALEZ |
| Building Plans Picked Up | 11/22/2021 | APPLICANT |
| Issued | 4/3/2022 | APPLICANT |
| CofO in Progress | 9/23/2022 | RAUL OLAGI |
| Permit Finaled | 10/22/2022 | MICHAEL SMITH |
| CofO Issued | 10/22/2022 | MICHAEL SMITH |
| Permit Finaled | 10/22/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Construction near power lines | Cleared | 7/28/2021 | WALTER RAMIREZ |
| Address approval | Cleared | 7/31/2021 | ABDULLAH SADOZAI |
| Eng Process Fee Ord 176,300 | Cleared | 8/2/2021 | ABDULLAH SADOZAI |
| Grading Pre-Inspection | Cleared | 8/24/2021 | ALEXANDER ANDREWS |
| Roof/Waste drainage to street | Cleared | 10/7/2021 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 10/7/2021 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Shellmolly Construction; Lic. No.: 911257-B | 8654 STATE ST SOUTH GATE, CA 90280 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/11/2022 | Not Ready for Inspection | RAUL OLAGI |
| PLUMBING-Rough | 4/11/2022 | Corrections Issued | RAUL OLAGI |
| Underground Mechanical | 4/11/2022 | Approved | RAUL OLAGI |
| PLUMBING-Rough | 4/21/2022 | Partial Approval | RAUL OLAGI |
| Sewer | 4/21/2022 | Not Ready for Inspection | RAUL OLAGI |
| Footing/Foundation/Slab | 4/25/2022 | Approved | RAUL OLAGI |
| Sewer | 4/25/2022 | Approved | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 5/3/2022 | Partial Approval | DEANDRE HOFFMAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/13/2022 | Approved | RAUL OLAGI |
| Green Building Rough | 5/13/2022 | Not Ready for Inspection | RAUL OLAGI |
| PLUMBING-Rough | 5/13/2022 | Approved | RAUL OLAGI |
| Verify Sprinkler Sign Off | 5/13/2022 | Approved | RAUL OLAGI |
| BUILDING-Rough-Frame | 5/18/2022 | Partial Approval | RAUL OLAGI |
| ELECTRICAL-Rough | 5/18/2022 | Approved | RAUL OLAGI |
| HVAC-Rough | 5/18/2022 | Approved | RAUL OLAGI |
| Insulation | 5/23/2022 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 5/23/2022 | Partial Approval | RAUL OLAGI |
| Shower Pan | 5/23/2022 | Approved | RAUL OLAGI |
| Drywall Nailing | 5/31/2022 | Approved | RAUL OLAGI |
| Green Building Rough | 5/31/2022 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 5/31/2022 | Approved | RAUL OLAGI |
| BUILDING-Rough-Frame | 6/6/2022 | Approved | ALAN MORELOS |
| Interior/Exterior Lathing | 6/6/2022 | Approved | ALAN MORELOS |
| SGSOV-Seismic Gas S/O Valve | 8/15/2022 | SGSOV Not Ready | RAUL OLAGI |
| ELECTRICAL-Final | 8/23/2022 | Corrections Issued | RAUL OLAGI |
| Final | 8/23/2022 | Corrections Issued | RAUL OLAGI |
| Green Building Final | 8/23/2022 | Approved | RAUL OLAGI |
| HVAC-Final | 8/23/2022 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Final | 8/23/2022 | Corrections Issued | RAUL OLAGI |
| Smoke Detectors | 8/23/2022 | Approved | RAUL OLAGI |
| ELECTRICAL-Final | 9/7/2022 | Approved | RAUL OLAGI |
| Final | 9/7/2022 | Corrections Issued | RAUL OLAGI |
| Gas Test | 9/7/2022 | Approved | RAUL OLAGI |
| HVAC-Final | 9/7/2022 | Approved | RAUL OLAGI |
| PLUMBING-Final | 9/7/2022 | Approved | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 9/7/2022 | SGSOV Approved | RAUL OLAGI |
| Service/Power Release | 9/7/2022 | Partial Inspection | RAUL OLAGI |
| Final | 9/22/2022 | OK to Issue CofO | RAUL OLAGI |
| Service/Power Release | 9/22/2022 | Approved | RAUL OLAGI |