7420 S HOBART BLVD 90047
Certificate Information: 7420 S HOBART BLVD 90047
- Application / Permit
- 21010-10000-02792
- Plan Check / Job No.
- B21LA10664
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSED A.D.U. 3 BEDROOM / 2 BATHROOM, 1,200 SQ. FT. (30' X 40')
- Permit Issued
- Issued on 11/8/2021
- Issuing Office
- Current Status
- CofO Issued on 4/13/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/17/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/22/2021 | JOE VO |
| Corrections Issued | 7/25/2021 | JOE VO |
| Quality Review Completed | 8/2/2021 | MICHAEL PEREZ |
| Applicant returned to address corrections | 10/25/2021 | JOE VO |
| Plan Check Approved | 11/1/2021 | JOE VO |
| Issued | 11/8/2021 | APPLICANT |
| CofO in Progress | 4/6/2022 | ENRIQUE MIRELES |
| CofO in Progress | 4/6/2022 | ENRIQUE MIRELES |
| Permit Finaled | 4/13/2022 | DEROLD HAUFF |
| CofO Issued | 4/13/2022 | DEROLD HAUFF |
| Permit Finaled | 4/13/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 8/9/2021 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 8/24/2021 | JEANIE LAM |
| Sewer availability | Cleared | 8/24/2021 | JEANIE LAM |
| Hydrant and Access approval | Cleared | 10/1/2021 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 10/5/2021 | LONDY ALVARADO |
| Roof/Waste drainage to street | Cleared | 10/19/2021 | STEVE MELGAR |
Contact Information
| Contractor | Arrow Construction Co; Lic. No.: 573067-B | 18729 CLARK DALE AVE #C ARTESIA, CA 90701 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/3/2021 | Corrections Issued | FREDDIE RIVERA |
| Footing/Foundation/Slab | 12/7/2021 | Approved | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 12/22/2021 | Corrections Issued | FREDDIE RIVERA |
| ELECTRICAL-Rough | 1/10/2022 | Not Ready for Inspection | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 1/10/2022 | No Access for Inspection | FREDDIE RIVERA |
| HVAC-Rough | 1/10/2022 | Not Ready for Inspection | FREDDIE RIVERA |
| PLUMBING-Rough | 1/10/2022 | Corrections Issued | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 1/14/2022 | Approved | FREDDIE RIVERA |
| ELECTRICAL-Rough | 1/14/2022 | Approved | FREDDIE RIVERA |
| HVAC-Rough | 1/14/2022 | Approved | FREDDIE RIVERA |
| PLUMBING-Rough | 1/14/2022 | Approved | FREDDIE RIVERA |
| Verify Sprinkler Sign Off | 1/14/2022 | Approved | FREDDIE RIVERA |
| Insulation | 1/19/2022 | Conditional Approval | FREDDIE RIVERA |
| Drywall Nailing | 1/21/2022 | Corrections Issued | LILIANA PORTILLO |
| Interior/Exterior Lathing | 1/21/2022 | Approved | LILIANA PORTILLO |
| Drywall Nailing | 1/26/2022 | Approved | FREDDIE RIVERA |
| Pre-Inspection | 1/26/2022 | Not Ready for Inspection | FREDDIE RIVERA |
| Final | 3/9/2022 | Corrections Issued | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 3/9/2022 | SGSOV Not Ready | FREDDIE RIVERA |
| Service/Power Release | 3/9/2022 | Not Ready for Inspection | FREDDIE RIVERA |
| Smoke Detectors | 3/9/2022 | Approved | FREDDIE RIVERA |
| Final | 3/21/2022 | Corrections Issued | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 3/21/2022 | SGSOV Approved | ENRIQUE MIRELES |
| Final | 3/29/2022 | Corrections Issued | HORACE FULTZ |
| Service/Power Release | 3/29/2022 | Approved | HORACE FULTZ |
| Final | 4/4/2022 | OK to Issue CofO | ENRIQUE MIRELES |