4255 N SAUGUS AVE 91403
Certificate Information: 4255 N SAUGUS AVE 91403
- Application / Permit
- 21010-10000-02790
- Plan Check / Job No.
- B21LA10635
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ACCESSORY DWELLING UNIT (ADU). FULLY SPRINKLERED.
- Permit Issued
- Issued on 11/7/2021
- Issuing Office
- Current Status
- CofO Issued on 11/19/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/7/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/24/2021 | JOE VO |
| Corrections Issued | 6/26/2021 | JOE VO |
| Quality Review Completed | 7/1/2021 | MICHAEL PEREZ |
| Plan Check Approved | 9/26/2021 | JOE VO |
| Issued | 11/7/2021 | APPLICANT |
| CofO in Progress | 11/8/2022 | THOMAS FINNILA |
| CofO in Progress | 11/8/2022 | THOMAS FINNILA |
| Permit Finaled | 11/19/2022 | MICHAEL SMITH |
| CofO Issued | 11/19/2022 | MICHAEL SMITH |
| Permit Finaled | 11/19/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 7/2/2021 | LEE GUILBEAUX |
| BHO/Hillside ordinance | Cleared | 7/2/2021 | LEE GUILBEAUX |
| BHO/Hillside ordinance | Cleared | 7/2/2021 | LEE GUILBEAUX |
| BHO/Hillside ordinance | Cleared | 7/2/2021 | LEE GUILBEAUX |
| Street Frontage | Cleared | 7/2/2021 | LEE GUILBEAUX |
| Address approval | Cleared | 7/6/2021 | LEE GUILBEAUX |
| BHO/Hillside ordinance | Cleared | 7/6/2021 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 7/6/2021 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 9/3/2021 | DAGOVERTO GUERRERO |
| Hydrant and Access approval | Cleared | 9/6/2021 | ROBERT DUFF |
| Miscellaneous | Cleared | 9/6/2021 | ROBERT DUFF |
| Sewer availability | Cleared | 9/7/2021 | DAGOVERTO GUERRERO |
| Low Impact Development | Cleared | 9/21/2021 | IDA MEISAMI-FARD |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Andrejic,, Milos M; Lic. No.: NA67443 | , |
Inspector Information
| RAUL OLAGI, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/3/2022 | Approved | JACK KARGODORIAN |
| Footing/Foundation/Slab | 2/3/2022 | Approved | JACK KARGODORIAN |
| PLUMBING-Rough | 2/3/2022 | Partial Approval | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 3/8/2022 | Partial Approval | JACK KARGODORIAN |
| Green Building Rough | 3/8/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| MERV13>=Rough | 3/8/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| PLUMBING-Rough | 3/8/2022 | Partial Approval | JACK KARGODORIAN |
| Verify Sprinkler Sign Off | 3/8/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/15/2022 | Partial Approval | JACK KARGODORIAN |
| Insulation | 3/15/2022 | Partial Approval | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 3/30/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/30/2022 | Partial Approval | JACK KARGODORIAN |
| Green Building Rough | 3/30/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| MERV13>=Rough | 3/30/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Verify Sprinkler Sign Off | 3/30/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/22/2022 | Partial Approval | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 5/6/2022 | Corrections Issued | MATT KELLERMAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/6/2022 | Not Ready for Inspection | MATT KELLERMAN |
| Green Building Rough | 5/6/2022 | Not Ready for Inspection | MATT KELLERMAN |
| MERV13>=Rough | 5/6/2022 | Not Ready for Inspection | MATT KELLERMAN |
| Verify Sprinkler Sign Off | 5/6/2022 | Not Ready for Inspection | MATT KELLERMAN |
| Deputy Wood Construction | 5/9/2022 | Partial Approval | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 5/19/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| ELECTRICAL-Rough | 5/19/2022 | Approved | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/19/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Green Building Rough | 5/19/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| HVAC-Rough | 5/19/2022 | Approved | JACK KARGODORIAN |
| MERV13>=Rough | 5/19/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| PLUMBING-Rough | 5/19/2022 | Approved | JACK KARGODORIAN |
| Verify Sprinkler Sign Off | 5/19/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 5/27/2022 | Partial Approval | JACK KARGODORIAN |
| Green Building Rough | 5/27/2022 | Approved | JACK KARGODORIAN |
| MERV13>=Rough | 5/27/2022 | Approved | JACK KARGODORIAN |
| Verify Sprinkler Sign Off | 5/27/2022 | Approved | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 6/15/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Interior/Exterior Lathing | 6/15/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Shower Pan | 6/15/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Insulation | 6/17/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Shower Pan | 6/17/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Insulation | 6/23/2022 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 6/23/2022 | Partial Approval | JACK KARGODORIAN |
| Shower Pan | 6/23/2022 | Approved | JACK KARGODORIAN |
| Drywall Nailing | 7/6/2022 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 7/6/2022 | Partial Approval | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 9/29/2022 | Approved | CHRISTOPHE COCHRAN |
| ELECTRICAL-Final | 9/29/2022 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Final | 9/29/2022 | Corrections Issued | CHRISTOPHE COCHRAN |
| Green Building Final | 9/29/2022 | Approved | CHRISTOPHE COCHRAN |
| HVAC-Final | 9/29/2022 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| MERV13>=Final | 9/29/2022 | Approved | CHRISTOPHE COCHRAN |
| PLUMBING-Final | 9/29/2022 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| SGSOV-Seismic Gas S/O Valve | 9/29/2022 | SGSOV Not Ready | CHRISTOPHE COCHRAN |
| Service/Power Release | 9/29/2022 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Smoke Detectors | 9/29/2022 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| ELECTRICAL-Final | 10/6/2022 | Corrections Issued | JACK KARGODORIAN |
| HVAC-Final | 10/6/2022 | Approved | JACK KARGODORIAN |
| PLUMBING-Final | 10/6/2022 | Approved | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 10/14/2022 | SGSOV Not Ready | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 10/28/2022 | SGSOV Not Ready | THOMAS FINNILA |
| Final | 11/4/2022 | OK to Issue CofO | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 11/4/2022 | SGSOV Approved | THOMAS FINNILA |
| Service/Power Release | 11/4/2022 | Approved | THOMAS FINNILA |
| Smoke Detectors | 11/4/2022 | Approved | THOMAS FINNILA |