5456-5456 1/2 W BARTON AVE BLDG. A 90038
Certificate Information: 5456-5456 1/2 W BARTON AVE BLDG. A 90038
- Application / Permit
- 21010-10000-02786
- Plan Check / Job No.
- B21LA10619
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW 3-STORY DUPLEX WITH ATTACHED GARAGE.
- Permit Issued
- Issued on 6/15/2022
- Issuing Office
- Current Status
- CofO Issued on 12/22/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/11/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/15/2021 | JOE VO |
| Corrections Issued | 7/21/2021 | JOE VO |
| Quality Review Completed | 8/4/2021 | MICHAEL PEREZ |
| Applicant returned to address corrections | 10/4/2021 | JOE VO |
| Plan Check Approved | 5/18/2022 | JOE VO |
| Issued | 6/15/2022 | APPLICANT |
| Building Plans Picked Up | 6/21/2022 | APPLICANT |
| CofO in Progress | 11/7/2023 | JEFFREY MEAD |
| No Progress | 12/16/2023 | JOAQUIN GREENOUGH |
| CofO in Progress | 12/21/2023 | JOAQUIN GREENOUGH |
| CofO Issued | 12/22/2023 | DEROLD HAUFF |
| Permit Finaled | 12/22/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 8/10/2021 | WALLIE JONG |
| Permit | Cleared | 8/10/2021 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 8/11/2021 | WALLIE JONG |
| Sewer availability | Cleared | 8/11/2021 | WALLIE JONG |
| Hydrant and Access approval | Cleared | 9/19/2021 | JOHN CONNEALLY |
| Construction near power lines | Cleared | 12/3/2021 | RIDWAN HARDY |
| Low Impact Development | Cleared | 3/8/2022 | MARCO SANCHEZ |
| Roof/Waste drainage to street | Cleared | 3/25/2022 | WALLIE JONG |
Contact Information
| Architect | Feagins,, Larry; Lic. No.: C27009 | 669 N THIRD AVENUE UPLAND, CA 91786 |
| Contractor | Inhance Construction Inc; Lic. No.: 1073871-B | 7257 BEVERLY RD STE 205 LOS ANGELES, CA 90036 |
| Engineer | Durand,, Paul H; Lic. No.: C58364 | 611 N G ST OXNARD, CA 93030 |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/1/2022 | Approved | JEFFREY MEAD |
| Underground Mechanical | 9/1/2022 | Approved | JEFFREY MEAD |
| Excavation/Setback/Form/Re-Bar | 9/19/2022 | Approved | JEFFREY MEAD |
| Footing/Foundation/Slab | 9/19/2022 | Approved | JEFFREY MEAD |
| Deputy Reinf. Concrete | 9/23/2022 | Partial Approval | JEFFREY MEAD |
| Footing/Foundation/Slab | 9/29/2022 | Approved | JEFFREY MEAD |
| Sewer | 10/5/2022 | Approved | JEFFREY MEAD |
| Underground Mechanical | 10/5/2022 | Approved | JEFFREY MEAD |
| Deputy Steel/Welding | 10/24/2022 | Partial Approval | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 11/1/2022 | Partial Approval | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 11/17/2022 | Approved | JEFFREY MEAD |
| Deputy Wood Construction | 12/9/2022 | Partial Approval | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 12/9/2022 | Partial Approval | JOSEPH MCGARRY |
| Underground Mechanical | 12/14/2022 | Approved | JEFFREY MEAD |
| Deputy Wood Construction | 12/29/2022 | Approved | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 12/29/2022 | Approved | JEFFREY MEAD |
| PLUMBING-Rough | 1/6/2023 | Approved | JEFFREY MEAD |
| Shower Pan | 1/17/2023 | Approved | JEFFREY MEAD |
| Deputy Wood Construction | 1/18/2023 | Partial Approval | JEFFREY MEAD |
| ELECTRICAL-Rough | 1/18/2023 | Approved | JEFFREY MEAD |
| HVAC-Rough | 1/18/2023 | Approved | JEFFREY MEAD |
| Rough-Elec/Plmb/HVAC | 1/18/2023 | Approved | JEFFREY MEAD |
| Deputy Wood Construction | 1/31/2023 | Partial Approval | JEFFREY MEAD |
| BUILDING-Rough-Frame | 2/6/2023 | Approved | JEFFREY MEAD |
| Green Building Rough | 2/6/2023 | Approved | JEFFREY MEAD |
| Verify Sprinkler Sign Off | 2/6/2023 | Approved | JEFFREY MEAD |
| Insulation | 2/13/2023 | Approved | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 2/13/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| Special/Order Compliance | 2/13/2023 | Approved | CRAIG VAUGHAN |
| Drywall Nailing | 2/17/2023 | Approved | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 2/17/2023 | Approved | ALIZAH MAYAGOITIA |
| Underground Mechanical | 4/12/2023 | Approved | JEFFREY MEAD |
| ELECTRICAL-Final | 8/7/2023 | Approved | JEFFREY MEAD |
| HVAC-Final | 8/7/2023 | Approved | JEFFREY MEAD |
| PLUMBING-Final | 8/7/2023 | Approved | JEFFREY MEAD |
| Service/Power Release | 8/7/2023 | Approved | JEFFREY MEAD |
| ELECTRICAL-Final | 11/7/2023 | Approved | JEFFREY MEAD |
| Final | 11/7/2023 | OK to Issue CofO | JEFFREY MEAD |
| Gas Test | 11/7/2023 | Approved | JEFFREY MEAD |
| Green Building Final | 11/7/2023 | Approved | JEFFREY MEAD |
| HVAC-Final | 11/7/2023 | Approved | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 11/7/2023 | SGSOV Approved | JEFFREY MEAD |
| Smoke Detectors | 11/7/2023 | Approved | JEFFREY MEAD |
| Structural Steel Frame | 11/7/2023 | Approved | JEFFREY MEAD |