1625 W DONALDSON ST 90026
Certificate Information: 1625 W DONALDSON ST 90026
- Application / Permit
- 21010-10000-02765
- Plan Check / Job No.
- B21LA10527
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Conversion of a detached recreation room 337 sf into an ADU per ordinance 186,481 with (E) attached covered porch.
- Permit Issued
- Issued on 12/16/2021
- Issuing Office
- Current Status
- CofO Issued on 2/7/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/9/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/11/2021 | HELEN NGUYEN |
| Corrections Issued | 6/11/2021 | HELEN NGUYEN |
| Plan Check Approved | 8/18/2021 | HELEN NGUYEN |
| Issued | 12/16/2021 | APPLICANT |
| CofO in Progress | 1/30/2023 | THOMAS LOGRASSO |
| Permit Finaled | 2/7/2023 | DEROLD HAUFF |
| CofO Issued | 2/7/2023 | DEROLD HAUFF |
| Permit Finaled | 2/7/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 7/8/2021 | THOMAS LANG |
| Sewer availability | Cleared | 7/8/2021 | THOMAS LANG |
| Eng Process Fee Ord 176,300 | Cleared | 7/13/2021 | THOMAS LANG |
Contact Information
| Contractor | Abril Jesus Jr; Lic. No.: 980059-B | , |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/1/2022 | Partial Inspection | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 8/18/2022 | Partial Approval | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 8/18/2022 | Approved | THOMAS LOGRASSO |
| HVAC-Rough | 8/18/2022 | Corrections Issued | THOMAS LOGRASSO |
| PLUMBING-Rough | 8/18/2022 | Approved | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 9/16/2022 | Approved | THOMAS LOGRASSO |
| Final | 9/16/2022 | Corrections Issued | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 9/16/2022 | SGSOV Approved | THOMAS LOGRASSO |
| Smoke Detectors | 9/16/2022 | Approved | THOMAS LOGRASSO |
| Final | 9/23/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Final | 1/30/2023 | OK to Issue CofO | THOMAS LOGRASSO |