4646 1/2 W MASCOT ST 90019

Certificate Information: 4646 1/2 W MASCOT ST 90019

Application / Permit
21010-10000-02690
Plan Check / Job No.
B21LA10195
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan NEW DETACHED 2 STORY ADU WITH ATTACHED 2 CAR GARAGE 1ST FLOOR OF ADU: 516 S.F. 2ND FLOOR OF ADU: 677 S.F. TOTAL OF ADU: 1,193 S.F. ATTACHED 2 CAR GARAGE: 499 S.F.
Permit Issued
Issued on 12/14/2021
Issuing Office
Current Status
CofO Issued on 11/19/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/29/2021 APPLICANT
Assigned to Plan Check Engineer 7/1/2021 ARSALAN SHABESTARI
Corrections Issued 7/3/2021 ARSALAN SHABESTARI
Quality Review Completed 7/15/2021 MICHAEL PEREZ
Applicant returned to address corrections 11/15/2021 ARSALAN SHABESTARI
Plan Check Approved 12/8/2021 ARSALAN SHABESTARI
Issued 12/14/2021 APPLICANT
CofO in Progress 11/4/2022 STUART CHAPMAN
Permit Finaled 11/19/2022 DEROLD HAUFF
CofO Issued 11/19/2022 DEROLD HAUFF
Permit Finaled 11/19/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 7/26/2021 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 8/10/2021 JEANIE LAM
Sewer availability Cleared 8/10/2021 JEANIE LAM
Hydrant and Access approval Cleared 9/13/2021 GILBERT URREA
Construction near power lines Cleared 10/12/2021 RIDWAN HARDY
Construction within easement Cleared 10/12/2021 RIDWAN HARDY
Low Impact Development Cleared 10/19/2021 MARCO SANCHEZ
Roof/Waste drainage to street Cleared 11/18/2021 JEANIE LAM

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/27/2022 Approved STUART CHAPMAN
METHANE-Barrier 1/27/2022 Approved STUART CHAPMAN
METHANE-Subgrade 1/27/2022 Approved STUART CHAPMAN
PLUMBING-Rough 1/27/2022 Partial Approval STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 2/9/2022 Partial Approval STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 3/22/2022 Corrections Issued STUART CHAPMAN
BUILDING-Rough-Frame 3/30/2022 Corrections Issued STUART CHAPMAN
ELECTRICAL-Rough 3/30/2022 Approved STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 3/30/2022 Partial Approval STUART CHAPMAN
HVAC-Rough 3/30/2022 Corrections Issued STUART CHAPMAN
METHANE-Rough 3/30/2022 Approved STUART CHAPMAN
PLUMBING-Rough 3/30/2022 Approved STUART CHAPMAN
Verify Sprinkler Sign Off 3/30/2022 Approved STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 4/14/2022 Not Ready for Inspection STUART CHAPMAN
Interior/Exterior Lathing 4/14/2022 Corrections Issued STUART CHAPMAN
BUILDING-Rough-Frame 4/20/2022 Approved STUART CHAPMAN
Green Building Rough 4/20/2022 Approved STUART CHAPMAN
Interior/Exterior Lathing 4/20/2022 Partial Approval STUART CHAPMAN
Insulation 5/5/2022 Approved STUART CHAPMAN
Drywall Nailing 6/3/2022 Approved STUART CHAPMAN
Shower Pan 6/16/2022 Approved STUART CHAPMAN
Final 10/18/2022 Corrections Issued STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 10/18/2022 SGSOV Approved STUART CHAPMAN
Service/Power Release 10/18/2022 Not Ready for Inspection STUART CHAPMAN
Smoke Detectors 10/18/2022 Approved STUART CHAPMAN
ELECTRICAL-Final 11/2/2022 Approved STUART CHAPMAN
Final 11/2/2022 OK to Issue CofO STUART CHAPMAN
HVAC-Final 11/2/2022 Approved STUART CHAPMAN
PLUMBING-Final 11/2/2022 Approved STUART CHAPMAN
Service/Power Release 11/2/2022 Approved STUART CHAPMAN