4646 1/2 W MASCOT ST 90019
Certificate Information: 4646 1/2 W MASCOT ST 90019
- Application / Permit
- 21010-10000-02690
- Plan Check / Job No.
- B21LA10195
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan NEW DETACHED 2 STORY ADU WITH ATTACHED 2 CAR GARAGE 1ST FLOOR OF ADU: 516 S.F. 2ND FLOOR OF ADU: 677 S.F. TOTAL OF ADU: 1,193 S.F. ATTACHED 2 CAR GARAGE: 499 S.F.
- Permit Issued
- Issued on 12/14/2021
- Issuing Office
- Current Status
- CofO Issued on 11/19/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/29/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/1/2021 | ARSALAN SHABESTARI |
| Corrections Issued | 7/3/2021 | ARSALAN SHABESTARI |
| Quality Review Completed | 7/15/2021 | MICHAEL PEREZ |
| Applicant returned to address corrections | 11/15/2021 | ARSALAN SHABESTARI |
| Plan Check Approved | 12/8/2021 | ARSALAN SHABESTARI |
| Issued | 12/14/2021 | APPLICANT |
| CofO in Progress | 11/4/2022 | STUART CHAPMAN |
| Permit Finaled | 11/19/2022 | DEROLD HAUFF |
| CofO Issued | 11/19/2022 | DEROLD HAUFF |
| Permit Finaled | 11/19/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 7/26/2021 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 8/10/2021 | JEANIE LAM |
| Sewer availability | Cleared | 8/10/2021 | JEANIE LAM |
| Hydrant and Access approval | Cleared | 9/13/2021 | GILBERT URREA |
| Construction near power lines | Cleared | 10/12/2021 | RIDWAN HARDY |
| Construction within easement | Cleared | 10/12/2021 | RIDWAN HARDY |
| Low Impact Development | Cleared | 10/19/2021 | MARCO SANCHEZ |
| Roof/Waste drainage to street | Cleared | 11/18/2021 | JEANIE LAM |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/27/2022 | Approved | STUART CHAPMAN |
| METHANE-Barrier | 1/27/2022 | Approved | STUART CHAPMAN |
| METHANE-Subgrade | 1/27/2022 | Approved | STUART CHAPMAN |
| PLUMBING-Rough | 1/27/2022 | Partial Approval | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/9/2022 | Partial Approval | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/22/2022 | Corrections Issued | STUART CHAPMAN |
| BUILDING-Rough-Frame | 3/30/2022 | Corrections Issued | STUART CHAPMAN |
| ELECTRICAL-Rough | 3/30/2022 | Approved | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/30/2022 | Partial Approval | STUART CHAPMAN |
| HVAC-Rough | 3/30/2022 | Corrections Issued | STUART CHAPMAN |
| METHANE-Rough | 3/30/2022 | Approved | STUART CHAPMAN |
| PLUMBING-Rough | 3/30/2022 | Approved | STUART CHAPMAN |
| Verify Sprinkler Sign Off | 3/30/2022 | Approved | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/14/2022 | Not Ready for Inspection | STUART CHAPMAN |
| Interior/Exterior Lathing | 4/14/2022 | Corrections Issued | STUART CHAPMAN |
| BUILDING-Rough-Frame | 4/20/2022 | Approved | STUART CHAPMAN |
| Green Building Rough | 4/20/2022 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 4/20/2022 | Partial Approval | STUART CHAPMAN |
| Insulation | 5/5/2022 | Approved | STUART CHAPMAN |
| Drywall Nailing | 6/3/2022 | Approved | STUART CHAPMAN |
| Shower Pan | 6/16/2022 | Approved | STUART CHAPMAN |
| Final | 10/18/2022 | Corrections Issued | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 10/18/2022 | SGSOV Approved | STUART CHAPMAN |
| Service/Power Release | 10/18/2022 | Not Ready for Inspection | STUART CHAPMAN |
| Smoke Detectors | 10/18/2022 | Approved | STUART CHAPMAN |
| ELECTRICAL-Final | 11/2/2022 | Approved | STUART CHAPMAN |
| Final | 11/2/2022 | OK to Issue CofO | STUART CHAPMAN |
| HVAC-Final | 11/2/2022 | Approved | STUART CHAPMAN |
| PLUMBING-Final | 11/2/2022 | Approved | STUART CHAPMAN |
| Service/Power Release | 11/2/2022 | Approved | STUART CHAPMAN |