2711 W 60TH ST 90043
Certificate Information: 2711 W 60TH ST 90043
- Application / Permit
- 21010-10000-02675
- Plan Check / Job No.
- B21LA10155
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) One-story detached Accessory Dwelling Unit per CA Govt. Code 65852.2(e)(1)(B). All work per WFPP. **“The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy.”**
- Permit Issued
- Issued on 10/4/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 9/5/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/27/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/3/2021 | LAWRENCE QUIRANTE |
| Corrections Issued | 6/3/2021 | LAWRENCE QUIRANTE |
| Applicant returned to address corrections | 7/30/2021 | SAMUEL GONZALEZ |
| Applicant returned to address corrections | 8/24/2021 | LAWRENCE QUIRANTE |
| Applicant returned to address corrections | 11/2/2021 | JESSE JIMENEZ |
| Applicant returned to address corrections | 12/7/2021 | EDWIN ESPIN |
| Plan Check Approved | 12/14/2021 | MINA HABILI |
| Plan Check Approved | 12/15/2021 | CHRISTOPHER KOMANCHECK |
| Building Plans Picked Up | 12/22/2021 | APPLICANT |
| Issued | 10/4/2022 | APPLICANT |
| CofO in Progress | 8/31/2023 | ENRIQUE MIRELES |
| Permit Finaled | 9/5/2023 | DEROLD HAUFF |
| Permit Finaled | 9/5/2023 | DEROLD HAUFF |
| CofO Issued | 9/5/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 9/15/2021 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 11/23/2021 | STEVE MELGAR |
| Sewer availability | Cleared | 11/23/2021 | STEVE MELGAR |
| Roof/Waste drainage to street | Cleared | 12/14/2021 | THAN WIN |
Contact Information
| Contractor | Adams Innovative Renovations; Lic. No.: 1023432-B | 335 E ALBERTONI STREET 200-755 CARSON, CA 90746 |
| Engineer | Diankov,, Nikolay Ivanov; Lic. No.: C52206 | 2222 FOTTHILL BLVD E538 LA CANADA FLINTRIDGE, CA 91011 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/17/2022 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 10/31/2022 | Approved | ENRIQUE MIRELES |
| Underground Mechanical | 11/8/2022 | Approved | ENRIQUE MIRELES |
| Sewer | 11/9/2022 | Corrections Issued | ENRIQUE MIRELES |
| Excavation/Setback/Form/Re-Bar | 11/16/2022 | Approved | ENRIQUE MIRELES |
| Sewer | 11/16/2022 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 12/9/2022 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 12/16/2022 | Approved | HORACE FULTZ |
| PLUMBING-Rough | 12/16/2022 | Conditional Approval | HORACE FULTZ |
| Interior/Exterior Lathing | 1/6/2023 | Corrections Issued | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 1/25/2023 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 1/25/2023 | Approved | ENRIQUE MIRELES |
| Verify Sprinkler Sign Off | 1/25/2023 | Approved | ENRIQUE MIRELES |
| HVAC-Rough | 1/27/2023 | No Access for Inspection | ENRIQUE MIRELES |
| PLUMBING-Rough | 1/27/2023 | No Access for Inspection | ENRIQUE MIRELES |
| Insulation | 2/3/2023 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 2/3/2023 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 2/13/2023 | Approved | ENRIQUE MIRELES |
| Service/Power Release | 3/31/2023 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Final | 6/26/2023 | Approved | ENRIQUE MIRELES |
| Final | 6/26/2023 | Corrections Issued | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 6/26/2023 | Approved | ENRIQUE MIRELES |
| Green Building Final | 6/26/2023 | Approved | ENRIQUE MIRELES |
| HVAC-Final | 6/26/2023 | Approved | ENRIQUE MIRELES |
| PLUMBING-Final | 6/26/2023 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 6/26/2023 | SGSOV Approved | ENRIQUE MIRELES |
| Smoke Detectors | 6/26/2023 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Final | 7/10/2023 | Approved | ENRIQUE MIRELES |
| Final | 7/10/2023 | Corrections Issued | ENRIQUE MIRELES |
| HVAC-Final | 7/10/2023 | Approved | ENRIQUE MIRELES |
| PLUMBING-Final | 7/10/2023 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Final | 8/17/2023 | Approved | ENRIQUE MIRELES |
| Final | 8/17/2023 | Corrections Issued | ENRIQUE MIRELES |
| HVAC-Final | 8/17/2023 | Approved | ENRIQUE MIRELES |
| PLUMBING-Final | 8/17/2023 | Approved | ENRIQUE MIRELES |
| Final | 8/21/2023 | Corrections Issued | ENRIQUE MIRELES |
| Final | 8/30/2023 | OK to Issue CofO | ENRIQUE MIRELES |