3003 S CANFIELD AVE 90034
Certificate Information: 3003 S CANFIELD AVE 90034
- Application / Permit
- 21010-10000-02604
- Plan Check / Job No.
- B21LA09967
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2-STORY SFD WITH ATTACHED 2-CAR GARAGE. NFPA 13D
- Permit Issued
- Issued on 9/11/2024
- Issuing Office
- Metro
- Current Status
- Issued on 9/11/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/25/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/17/2021 | VIVIAN LAO |
| Corrections Issued | 6/24/2021 | VIVIAN LAO |
| Quality Review Completed | 6/30/2021 | MICHAEL PEREZ |
| Building Plans Picked Up | 7/7/2021 | APPLICANT |
| Applicant returned to address corrections | 3/8/2022 | VIVIAN LAO |
| Applicant returned to address corrections | 8/12/2022 | VIVIAN LAO |
| Applicant returned to address corrections | 8/1/2023 | VIVIAN LAO |
| Applicant returned to address corrections | 9/12/2023 | VIVIAN LAO |
| Plan Check Approved | 9/19/2023 | VIVIAN LAO |
| Issued | 9/11/2024 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/4/2021 | HISASHI KOBAYAKAWA |
| Hydrant and Access approval | Cleared | 10/2/2021 | GILBERT URREA |
| GPI Written Notices | Cleared | 3/8/2022 | VIVIAN LAO |
| Grading Pre-Inspection | Cleared | 3/8/2022 | VIVIAN LAO |
| Construction near power lines | Cleared | 1/30/2023 | NADER ISKANDER |
| Low Impact Development | Cleared | 6/21/2023 | MELINEH AGHAKHABIAN |
| Roof/Waste drainage to street | Cleared | 6/21/2023 | HISASHI KOBAYAKAWA |
| Miscellaneous | Cleared | 7/18/2023 | AHMED AMARRAGY |
| Address approval | Cleared | 1/4/2024 | DARIN LAM |
| Sewer availability | Cleared | 1/4/2024 | DARIN LAM |
Contact Information
| Contractor | Liu Jialong Construction; Lic. No.: 1072125-B | 17806 AUTRY CT CHINO HILLS, CA 91709 |
| Engineer | Lee,, Allen C; Lic. No.: GE2781 | 11823 SLAUSON AVE STE 46 SANTA FE SPRINGS, CA 90670 |
| Engineer | Wu,, Shu; Lic. No.: C90391 | 136 LOST HILLS IRVINE, CA 92618 |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Service/Power Release | 10/17/2024 | Approved | MEL KHACHATOURIAN |
| Excavation/Setback/Form/Re-Bar | 11/5/2024 | Corrections Issued | ASHLEY THOMPSON |
| Footing/Foundation/Slab | 11/5/2024 | Not Ready for Inspection | ASHLEY THOMPSON |
| Excavation/Setback/Form/Re-Bar | 11/21/2024 | Partial Approval | ASHLEY THOMPSON |
| PLUMBING-Rough | 11/21/2024 | Corrections Issued | ASHLEY THOMPSON |
| PLUMBING-Rough | 12/4/2024 | Corrections Issued | STEPHANIE SWANSON |
| Excavation/Setback/Form/Re-Bar | 12/24/2024 | Corrections Issued | JESUS RODRIGUEZ |
| Excavation/Setback/Form/Re-Bar | 1/10/2025 | Corrections Issued | EVAN COOPER |
| Footing/Foundation/Slab | 1/24/2025 | Approved | ARAM AVEDISIAN |
| PLUMBING-Rough | 1/24/2025 | Partial Approval | ARAM AVEDISIAN |
| Deputy Steel/Welding | 2/12/2025 | Conditional Approval | ASHLEY THOMPSON |
| Floor/Roof Diaphrgm/Shear Wall | 2/28/2025 | Corrections Issued | ARAM AVEDISIAN |
| Deputy Wood Construction | 3/28/2025 | Conditional Approval | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 3/28/2025 | Conditional Approval | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 6/24/2025 | Not Ready for Inspection | ASHLEY THOMPSON |
| PLUMBING-Rough | 6/24/2025 | Corrections Issued | ASHLEY THOMPSON |
| ELECTRICAL-Rough | 6/26/2025 | Corrections Issued | ASHLEY THOMPSON |
| ELECTRICAL-Rough | 7/1/2025 | Approved | ASHLEY THOMPSON |
| Floor/Roof Diaphrgm/Shear Wall | 7/1/2025 | Corrections Issued | ASHLEY THOMPSON |
| PLUMBING-Rough | 7/1/2025 | Approved | ASHLEY THOMPSON |
| HVAC-Rough | 8/13/2025 | Corrections Issued | ASHLEY THOMPSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/31/2025 | Not Ready for Inspection | ASHLEY THOMPSON |
| HVAC-Rough | 10/31/2025 | Not Ready for Inspection | ASHLEY THOMPSON |
| Floor/Roof Diaphrgm/Shear Wall | 12/18/2025 | Partial Approval | ASHLEY THOMPSON |
| HVAC-Rough | 12/18/2025 | Conditional Approval | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 12/18/2025 | Partial Approval | ASHLEY THOMPSON |
| BUILDING-Rough-Frame | 1/9/2026 | Corrections Issued | ASHLEY THOMPSON |
| Green Building Rough | 1/9/2026 | Approved | ASHLEY THOMPSON |
| Special/Order Compliance | 1/9/2026 | Partial Inspection | DAKOTA LOW |
| Verify Sprinkler Sign Off | 1/9/2026 | Approved | ASHLEY THOMPSON |
| Wood Frame | 1/9/2026 | Partial Inspection | ANDREW NAVE |
| Insulation | 1/27/2026 | Corrections Issued | ASHLEY THOMPSON |
| Special/Order Compliance | 1/27/2026 | Partial Inspection | ASHLEY THOMPSON |
| Special/Order Compliance | 1/27/2026 | Partial Inspection | DAKOTA LOW |
| Insulation | 3/2/2026 | Approved | DANIEL VERA |
| Interior/Exterior Lathing | 3/2/2026 | Not Ready for Inspection | DANIEL VERA |
| Shower Pan | 3/2/2026 | Approved | DANIEL VERA |
| Drywall Nailing | 3/18/2026 | Approved | DANIEL VERA |
| Final | 3/18/2026 | Corrections Issued | DANIEL VERA |
| Interior/Exterior Lathing | 3/18/2026 | Approved | DANIEL VERA |
| Special/Order Compliance | 3/18/2026 | Partial Inspection | HERBERT GIRON |