751-751 1/2 E 85TH ST 90001

Certificate Information: 751-751 1/2 E 85TH ST 90001

Application / Permit
21010-10000-02588
Plan Check / Job No.
B21LA09922
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW 2 STORY DUPLEX WITH ATTACHED 1 CAR GARAGE AT FRONT AND 2 CAR GARAGE AT REAR.
Permit Issued
Issued on 8/23/2021
Issuing Office
Current Status
CofO Issued on 1/13/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/26/2021 APPLICANT
Assigned to Plan Check Engineer 6/17/2021 KHEDER ALRAZAA
Corrections Issued 6/22/2021 KHEDER ALRAZAA
Quality Review Completed 7/1/2021 JASON HEALEY
Building Plans Picked Up 7/6/2021 APPLICANT
Plan Check Approved 8/11/2021 KHEDER ALRAZAA
Issued 8/23/2021 APPLICANT
CofO in Progress 1/8/2022 ALEJANDRO DE ARTOLA
Permit Finaled 1/13/2022 DEROLD HAUFF
CofO Issued 1/13/2022 DEROLD HAUFF
Permit Finaled 1/13/2022 DEROLD HAUFF

Permit Application Clearance Information

Trees in Parkway Cleared 7/15/2021 JOHN KIM
Address approval Cleared 7/19/2021 WALLIE JONG
Permit Cleared 7/19/2021 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 7/20/2021 WALLIE JONG
Hydrant and Access approval Cleared 7/26/2021 ROBERT DUFF
Low Impact Development Cleared 7/27/2021 TA ANH
Roof/Waste drainage to street Cleared 7/27/2021 CELINA MORENO
Sewer availability Cleared 7/27/2021 WALLIE JONG

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B P O BOX 410      SUNSET BEACH, CA 90742

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/2/2021 Approved EUGENE CASSIDY
Footing/Foundation/Slab 9/3/2021 Approved JOHN KLARIN
PLUMBING-Rough 9/14/2021 Corrections Issued CRAIG DAVIS
Underground Mechanical 9/14/2021 Corrections Issued CRAIG DAVIS
Wood Frame 9/14/2021 Not Ready for Inspection CRAIG DAVIS
BUILDING-Rough-Frame 9/16/2021 Partial Approval ALEJANDRO DE ARTOLA
PLUMBING-Rough 9/16/2021 Partial Approval ALEJANDRO DE ARTOLA
Sewer 9/16/2021 Approved ALEJANDRO DE ARTOLA
Insulation 9/17/2021 Partial Approval ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 9/20/2021 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 9/20/2021 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 9/27/2021 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 10/13/2021 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 10/14/2021 Partial Approval ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 10/20/2021 Approved ALEJANDRO DE ARTOLA
HVAC-Rough 10/20/2021 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 10/20/2021 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 10/22/2021 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Rough 10/22/2021 Approved ALEJANDRO DE ARTOLA
HVAC-Rough 10/22/2021 Approved ALEJANDRO DE ARTOLA
Verify Sprinkler Sign Off 10/22/2021 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 10/26/2021 Approved ALEJANDRO DE ARTOLA
Insulation 10/26/2021 Approved ALEJANDRO DE ARTOLA
Drywall Nailing 10/29/2021 Approved ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 10/29/2021 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 12/10/2021 No Access for Inspection SABAS ALONSO
ELECTRICAL-Final 12/15/2021 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Final 12/27/2021 Approved ALEJANDRO DE ARTOLA
Final 12/27/2021 Corrections Issued ALEJANDRO DE ARTOLA
Gas Test 12/27/2021 Approved ALEJANDRO DE ARTOLA
Green Building Final 12/27/2021 Approved ALEJANDRO DE ARTOLA
HVAC-Final 12/27/2021 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 12/27/2021 Corrections Issued ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 12/27/2021 SGSOV Approved ALEJANDRO DE ARTOLA
Service/Power Release 12/27/2021 Approved ALEJANDRO DE ARTOLA
Smoke Detectors 12/27/2021 Approved ALEJANDRO DE ARTOLA
Final 12/28/2021 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 12/28/2021 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 12/28/2021 Approved ALEJANDRO DE ARTOLA
Service/Power Release 12/28/2021 Approved ALEJANDRO DE ARTOLA
Final 1/7/2022 OK to Issue CofO ALEJANDRO DE ARTOLA