5812 W CAZAUX DR 90068
Certificate Information: 5812 W CAZAUX DR 90068
- Application / Permit
- 21010-10000-02584
- Plan Check / Job No.
- B21LA09909
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Conversion of a detached garage into an ADU per state law GCS 65852.2(e)(1)(A).
- Permit Issued
- Issued on 1/20/2022
- Issuing Office
- Current Status
- CofO Issued on 8/25/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/25/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/31/2021 | HELEN NGUYEN |
| Corrections Issued | 5/31/2021 | HELEN NGUYEN |
| Applicant returned to address corrections | 9/22/2021 | HELEN NGUYEN |
| Applicant returned to address corrections | 10/28/2021 | HELEN NGUYEN |
| Applicant returned to address corrections | 11/10/2021 | HELEN NGUYEN |
| Applicant returned to address corrections | 12/22/2021 | HELEN NGUYEN |
| Plan Check Approved | 1/5/2022 | HELEN NGUYEN |
| Issued | 1/20/2022 | APPLICANT |
| CofO in Progress | 7/27/2022 | ZEYDI STEWART |
| Permit Finaled | 8/25/2022 | DANIEL SANCHEZ |
| CofO Issued | 8/25/2022 | DANIEL SANCHEZ |
| Permit Finaled | 8/25/2022 | DANIEL SANCHEZ |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 6/24/2021 | JEANIE LAM |
| BHO/Hillside ordinance | Cleared | 6/24/2021 | JEANIE LAM |
| BHO/Hillside ordinance | Cleared | 6/24/2021 | JEANIE LAM |
| BHO/Hillside ordinance | Cleared | 6/24/2021 | JEANIE LAM |
| Sewer availability | Cleared | 6/24/2021 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 6/25/2021 | JEANIE LAM |
| Address approval | Cleared | 8/24/2021 | JEANIE LAM |
| BHO/Hillside ordinance | Cleared | 8/25/2021 | JEANIE LAM |
| "D" conditions | Cleared | 9/14/2021 | LIKYELESH ABERA |
| ZI | Cleared | 9/14/2021 | LIKYELESH ABERA |
| Hydrant and Access approval | Cleared | 12/14/2021 | JOHN CONNEALLY |
Contact Information
| Contractor | American Home Improvement Inc; Lic. No.: 835537-B | 20335 VENTURA BLVD #422 WOODLAND HILLS, CA 91364 |
| Engineer | Phan,, Phillip Trung Tri; Lic. No.: C76425 | 641 S ALMIRANTE DR WEST COVINA, CA 91791 |
Inspector Information
| JOEL ORDAZ, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| PTOLEMY HILL, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVAKIAN, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| EDMOND DECKERT, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| TIMOTHY KEY, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERT CHAVEZ, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/25/2022 | Approved | STUART CHAPMAN |
| BUILDING-Rough-Frame | 2/17/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| ELECTRICAL-Rough | 2/17/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| PLUMBING-Rough | 2/17/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| Underground Mechanical | 2/17/2022 | Corrections Issued | BRIAN SULLIVAN |
| Pre-Inspection | 3/3/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 3/17/2022 | Corrections Issued | ZEYDI STEWART |
| ELECTRICAL-Rough | 3/17/2022 | Corrections Issued | ZEYDI STEWART |
| PLUMBING-Rough | 3/17/2022 | Corrections Issued | ZEYDI STEWART |
| Special/Order Compliance | 3/17/2022 | Partial Inspection | PIERRE VEGA |
| ELECTRICAL-Rough | 4/7/2022 | Not Ready for Inspection | PIERRE VEGA |
| Footing/Foundation/Slab | 4/7/2022 | Not Ready for Inspection | PIERRE VEGA |
| PLUMBING-Rough | 4/7/2022 | Not Ready for Inspection | PIERRE VEGA |
| Footing/Foundation/Slab | 4/8/2022 | Approved | PIERRE VEGA |
| ELECTRICAL-Rough | 4/19/2022 | Not Ready for Inspection | PIERRE VEGA |
| PLUMBING-Rough | 4/19/2022 | Approved | PIERRE VEGA |
| Underground Mechanical | 4/19/2022 | Partial Approval | PIERRE VEGA |
| BUILDING-Rough-Frame | 4/29/2022 | Not Ready for Inspection | GORDON ZUBER |
| ELECTRICAL-Rough | 5/2/2022 | Corrections Issued | GORDON ZUBER |
| ELECTRICAL-Rough | 5/19/2022 | Partial Approval | ZEYDI STEWART |
| BUILDING-Rough-Frame | 5/24/2022 | Partial Approval | ZEYDI STEWART |
| Insulation | 6/2/2022 | Corrections Issued | ZEYDI STEWART |
| Insulation | 6/6/2022 | Approved | ZEYDI STEWART |
| Floor/Roof Diaphrgm/Shear Wall | 6/8/2022 | Not Ready for Inspection | ZEYDI STEWART |
| Floor/Roof Diaphrgm/Shear Wall | 6/9/2022 | Corrections Issued | ZEYDI STEWART |
| Deputy Wood Construction | 6/14/2022 | Approved | PIERRE VEGA |
| Drywall Nailing | 6/16/2022 | Approved | ZEYDI STEWART |
| BUILDING-Rough-Frame | 7/5/2022 | Not Ready for Inspection | ZEYDI STEWART |
| Final | 7/5/2022 | Not Ready for Inspection | ZEYDI STEWART |
| SGSOV-Seismic Gas S/O Valve | 7/5/2022 | SGSOV Not Ready | ZEYDI STEWART |
| Smoke Detectors | 7/5/2022 | Not Ready for Inspection | ZEYDI STEWART |
| BUILDING-Rough-Frame | 7/15/2022 | Not Ready for Inspection | ZEYDI STEWART |
| Final | 7/15/2022 | Not Ready for Inspection | ZEYDI STEWART |
| SGSOV-Seismic Gas S/O Valve | 7/15/2022 | SGSOV Not Ready | ZEYDI STEWART |
| Smoke Detectors | 7/15/2022 | Not Ready for Inspection | ZEYDI STEWART |
| Pre-Inspection | 7/18/2022 | Corrections Issued | ZEYDI STEWART |
| BUILDING-Rough-Frame | 7/21/2022 | Not Ready for Inspection | ZEYDI STEWART |
| Final | 7/21/2022 | Corrections Issued | ZEYDI STEWART |
| SGSOV-Seismic Gas S/O Valve | 7/21/2022 | SGSOV Not Ready | ZEYDI STEWART |
| Smoke Detectors | 7/21/2022 | Not Ready for Inspection | ZEYDI STEWART |
| BUILDING-Rough-Frame | 7/26/2022 | Approved | ZEYDI STEWART |
| Final | 7/26/2022 | OK to Issue CofO | ZEYDI STEWART |
| SGSOV-Seismic Gas S/O Valve | 7/26/2022 | SGSOV Approved | ZEYDI STEWART |
| Smoke Detectors | 7/26/2022 | Approved | ZEYDI STEWART |
| Special/Order Compliance | 7/26/2022 | Approved | PIERRE VEGA |