13256 W KLING ST 1-3 91423
Certificate Information: 13256 W KLING ST 1-3 91423
- Application / Permit
- 21010-10000-02572
- Plan Check / Job No.
- B21LA09816
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW 3-STORY DUPLEX WITH AN ADU ON THE FIRST FLOOR PER LAMC 12.22 A.33(c) AND (e) (FRONT DUPLEX)
- Permit Issued
- Issued on 4/21/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 8/7/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/7/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/12/2021 | KHEDER ALRAZAA |
| Plans on Hold | 8/19/2021 | KHEDER ALRAZAA |
| Hold Released | 8/23/2021 | KHEDER ALRAZAA |
| Corrections Issued | 8/24/2021 | KHEDER ALRAZAA |
| Quality Review Completed | 8/31/2021 | JASON HEALEY |
| Building Plans Picked Up | 9/23/2021 | APPLICANT |
| Applicant returned to address corrections | 10/26/2021 | KHEDER ALRAZAA |
| Applicant returned to address corrections | 12/23/2021 | KHEDER ALRAZAA |
| Applicant returned to address corrections | 9/23/2022 | KHEDER ALRAZAA |
| Plan Check Approved | 3/20/2023 | KHEDER ALRAZAA |
| Issued | 4/21/2023 | APPLICANT |
| CofO in Progress | 7/22/2024 | CHRISTOPHE COCHRAN |
| Permit Finaled | 8/7/2024 | RUBEN SALAS |
| CofO Issued | 8/7/2024 | RUBEN SALAS |
| Permit Finaled | 8/7/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 9/14/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 9/15/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 9/15/2021 | GABRIEL ROBLES |
| Permit | Cleared | 9/21/2021 | GABRIEL ROBLES |
| "Q" conditions | Cleared | 9/22/2021 | LAUREN PADICK |
| Frnt yard landscape/Water mgmt | Cleared | 12/7/2021 | LAUREN PADICK |
| ZI | Cleared | 12/7/2021 | LAUREN PADICK |
| Trees in Parkway | Cleared | 12/8/2021 | ADALBERTO VERA |
| Low Impact Development | Cleared | 12/16/2021 | TA ANH |
| Roof/Waste drainage to street | Cleared | 12/20/2021 | CARLOS AGUILERA |
| Hydrant and Access approval | Cleared | 1/19/2022 | KURT CORRAL |
| Highway dedication | Cleared | 2/8/2022 | CARLOS AGUILERA |
| Construction within easement | Cleared | 10/25/2022 | RIDWAN HARDY |
| DAS Clearance | Cleared | 1/17/2023 | KHEDER ALRAZAA |
Contact Information
| Architect | Feagins,, Larry; Lic. No.: C27009 | 669 N THIRD AVENUE UPLAND, CA 91786 |
| Contractor | Owner-Builder | , |
| Engineer | Helou,, Dawn Renee; Lic. No.: C52361 | 22701 ERWIN ST WOODLAND HILLS, CA 91367 |
| Engineer | Xiao,, Qiang; Lic. No.: S5289 | 1520 BROOKHOLLOW #45 SANTA ANA, CA 92705 |
| Landscape Architect | Macias,, Jaime; Lic. No.: LA5870 | 953 FLORE STREET ANAHEIM, CA 92802 |
Inspector Information
| CHRISTOPHE COCHRAN, (818) 374-1165 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 5/30/2023 | Approved | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 6/8/2023 | Approved | CHRISTOPHE COCHRAN |
| Deputy Reinf. Concrete | 6/12/2023 | Conditional Approval | MICHAEL SMITH |
| Sewer | 6/13/2023 | Approved | CHRISTOPHE COCHRAN |
| Special/Order Compliance | 6/22/2023 | Off-Hour Fees Due | |
| Floor/Roof Diaphrgm/Shear Wall | 6/23/2023 | Partial Approval | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/26/2023 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/29/2023 | Partial Approval | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/6/2023 | Corrections Issued | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/11/2023 | Partial Approval | JUAN VALENZUELA |
| Special/Order Compliance | 7/11/2023 | Approved | JUAN VALENZUELA |
| PLUMBING-Rough | 7/31/2023 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 8/1/2023 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 8/7/2023 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| HVAC-Rough | 8/7/2023 | Corrections Issued | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 8/8/2023 | Corrections Issued | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 8/14/2023 | Partial Approval | CHRISTOPHE COCHRAN |
| HVAC-Rough | 8/14/2023 | Approved | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 8/14/2023 | Partial Approval | CHRISTOPHE COCHRAN |
| Wood Frame | 8/14/2023 | Partial Approval | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 8/29/2023 | No Access for Inspection | CHRISTOPHE COCHRAN |
| Insulation | 8/29/2023 | No Access for Inspection | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 8/29/2023 | No Access for Inspection | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 8/29/2023 | No Access for Inspection | CHRISTOPHE COCHRAN |
| Shower Pan | 8/29/2023 | No Access for Inspection | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 8/31/2023 | Corrections Issued | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/31/2023 | Corrections Issued | CHRISTOPHE COCHRAN |
| Insulation | 8/31/2023 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 8/31/2023 | Partial Approval | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 8/31/2023 | Approved | CHRISTOPHE COCHRAN |
| Shower Pan | 8/31/2023 | Approved | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 9/5/2023 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 9/5/2023 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 9/6/2023 | Approved | CHRISTOPHE COCHRAN |
| Insulation | 9/8/2023 | Approved | RYAN SALAZAR |
| Drywall Nailing | 9/21/2023 | Approved | CHRISTOPHE COCHRAN |
| Green Building Rough | 9/21/2023 | Approved | CHRISTOPHE COCHRAN |
| Underground Mechanical | 11/14/2023 | Partial Approval | CHRISTOPHE COCHRAN |
| Underground Mechanical | 11/17/2023 | Approved | CHRISTOPHER ROJAS |
| HVAC-Final | 1/19/2024 | Corrections Issued | CHRISTOPHE COCHRAN |
| PLUMBING-Final | 1/19/2024 | Corrections Issued | CHRISTOPHE COCHRAN |
| ELECTRICAL-Final | 6/11/2024 | Approved | CHRISTOPHE COCHRAN |
| HVAC-Final | 6/11/2024 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| PLUMBING-Final | 6/11/2024 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 7/9/2024 | Conditional Approval | SALVADOR MARTINEZ |
| ELECTRICAL-Final | 7/9/2024 | Approved | SALVADOR MARTINEZ |
| Final | 7/9/2024 | Not Ready for Inspection | SALVADOR MARTINEZ |
| Green Building Final | 7/9/2024 | Not Ready for Inspection | SALVADOR MARTINEZ |
| HVAC-Final | 7/9/2024 | Not Ready for Inspection | SALVADOR MARTINEZ |
| MERV13>=Final | 7/9/2024 | Not Ready for Inspection | SALVADOR MARTINEZ |
| MERV13>=Rough | 7/9/2024 | Not Ready for Inspection | SALVADOR MARTINEZ |
| PLUMBING-Final | 7/9/2024 | Not Ready for Inspection | SALVADOR MARTINEZ |
| SGSOV-Seismic Gas S/O Valve | 7/9/2024 | SGSOV Approved | SALVADOR MARTINEZ |
| Service/Power Release | 7/9/2024 | Not Ready for Inspection | SALVADOR MARTINEZ |
| Smoke Detectors | 7/9/2024 | Approved | SALVADOR MARTINEZ |
| Verify Sprinkler Sign Off | 7/9/2024 | Approved | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 7/15/2024 | Approved | CHRISTOPHE COCHRAN |
| Final | 7/15/2024 | Corrections Issued | CHRISTOPHE COCHRAN |
| Green Building Final | 7/15/2024 | Approved | CHRISTOPHE COCHRAN |
| MERV13>=Final | 7/15/2024 | Approved | CHRISTOPHE COCHRAN |
| MERV13>=Rough | 7/15/2024 | Approved | CHRISTOPHE COCHRAN |
| Service/Power Release | 7/15/2024 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Final | 7/22/2024 | OK to Issue CofO | CHRISTOPHE COCHRAN |
| Service/Power Release | 7/22/2024 | Approved | CHRISTOPHE COCHRAN |