13256 W KLING ST 1-3 91423

Certificate Information: 13256 W KLING ST 1-3 91423

Application / Permit
21010-10000-02572
Plan Check / Job No.
B21LA09816
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW 3-STORY DUPLEX WITH AN ADU ON THE FIRST FLOOR PER LAMC 12.22 A.33(c) AND (e) (FRONT DUPLEX)
Permit Issued
Issued on 4/21/2023
Issuing Office
Metro
Current Status
CofO Issued on 8/7/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/7/2021 APPLICANT
Assigned to Plan Check Engineer 8/12/2021 KHEDER ALRAZAA
Plans on Hold 8/19/2021 KHEDER ALRAZAA
Hold Released 8/23/2021 KHEDER ALRAZAA
Corrections Issued 8/24/2021 KHEDER ALRAZAA
Quality Review Completed 8/31/2021 JASON HEALEY
Building Plans Picked Up 9/23/2021 APPLICANT
Applicant returned to address corrections 10/26/2021 KHEDER ALRAZAA
Applicant returned to address corrections 12/23/2021 KHEDER ALRAZAA
Applicant returned to address corrections 9/23/2022 KHEDER ALRAZAA
Plan Check Approved 3/20/2023 KHEDER ALRAZAA
Issued 4/21/2023 APPLICANT
CofO in Progress 7/22/2024 CHRISTOPHE COCHRAN
Permit Finaled 8/7/2024 RUBEN SALAS
CofO Issued 8/7/2024 RUBEN SALAS
Permit Finaled 8/7/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 9/14/2021 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 9/15/2021 GABRIEL ROBLES
Sewer availability Cleared 9/15/2021 GABRIEL ROBLES
Permit Cleared 9/21/2021 GABRIEL ROBLES
"Q" conditions Cleared 9/22/2021 LAUREN PADICK
Frnt yard landscape/Water mgmt Cleared 12/7/2021 LAUREN PADICK
ZI Cleared 12/7/2021 LAUREN PADICK
Trees in Parkway Cleared 12/8/2021 ADALBERTO VERA
Low Impact Development Cleared 12/16/2021 TA ANH
Roof/Waste drainage to street Cleared 12/20/2021 CARLOS AGUILERA
Hydrant and Access approval Cleared 1/19/2022 KURT CORRAL
Highway dedication Cleared 2/8/2022 CARLOS AGUILERA
Construction within easement Cleared 10/25/2022 RIDWAN HARDY
DAS Clearance Cleared 1/17/2023 KHEDER ALRAZAA

Contact Information

Architect Feagins,, Larry; Lic. No.: C27009 669 N THIRD AVENUE      UPLAND, CA 91786
Contractor Owner-Builder       ,
Engineer Helou,, Dawn Renee; Lic. No.: C52361 22701 ERWIN ST      WOODLAND HILLS, CA 91367
Engineer Xiao,, Qiang; Lic. No.: S5289 1520 BROOKHOLLOW #45      SANTA ANA, CA 92705
Landscape Architect Macias,, Jaime; Lic. No.: LA5870 953 FLORE STREET      ANAHEIM, CA 92802

Inspector Information

CHRISTOPHE COCHRAN, (818) 374-1165 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 5/30/2023 Approved CHRISTOPHE COCHRAN
Footing/Foundation/Slab 6/8/2023 Approved CHRISTOPHE COCHRAN
Deputy Reinf. Concrete 6/12/2023 Conditional Approval MICHAEL SMITH
Sewer 6/13/2023 Approved CHRISTOPHE COCHRAN
Special/Order Compliance 6/22/2023 Off-Hour Fees Due
Floor/Roof Diaphrgm/Shear Wall 6/23/2023 Partial Approval CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 6/26/2023 Not Ready for Inspection CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 6/29/2023 Partial Approval CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 7/6/2023 Corrections Issued CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 7/11/2023 Partial Approval JUAN VALENZUELA
Special/Order Compliance 7/11/2023 Approved JUAN VALENZUELA
PLUMBING-Rough 7/31/2023 Not Ready for Inspection CHRISTOPHE COCHRAN
PLUMBING-Rough 8/1/2023 Not Ready for Inspection CHRISTOPHE COCHRAN
ELECTRICAL-Rough 8/7/2023 Not Ready for Inspection CHRISTOPHE COCHRAN
HVAC-Rough 8/7/2023 Corrections Issued CHRISTOPHE COCHRAN
PLUMBING-Rough 8/8/2023 Corrections Issued CHRISTOPHE COCHRAN
ELECTRICAL-Rough 8/14/2023 Partial Approval CHRISTOPHE COCHRAN
HVAC-Rough 8/14/2023 Approved CHRISTOPHE COCHRAN
PLUMBING-Rough 8/14/2023 Partial Approval CHRISTOPHE COCHRAN
Wood Frame 8/14/2023 Partial Approval CHRISTOPHE COCHRAN
ELECTRICAL-Rough 8/29/2023 No Access for Inspection CHRISTOPHE COCHRAN
Insulation 8/29/2023 No Access for Inspection CHRISTOPHE COCHRAN
Interior/Exterior Lathing 8/29/2023 No Access for Inspection CHRISTOPHE COCHRAN
PLUMBING-Rough 8/29/2023 No Access for Inspection CHRISTOPHE COCHRAN
Shower Pan 8/29/2023 No Access for Inspection CHRISTOPHE COCHRAN
ELECTRICAL-Rough 8/31/2023 Corrections Issued CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 8/31/2023 Corrections Issued CHRISTOPHE COCHRAN
Insulation 8/31/2023 Not Ready for Inspection CHRISTOPHE COCHRAN
Interior/Exterior Lathing 8/31/2023 Partial Approval CHRISTOPHE COCHRAN
PLUMBING-Rough 8/31/2023 Approved CHRISTOPHE COCHRAN
Shower Pan 8/31/2023 Approved CHRISTOPHE COCHRAN
ELECTRICAL-Rough 9/5/2023 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 9/5/2023 Not Ready for Inspection CHRISTOPHE COCHRAN
Interior/Exterior Lathing 9/6/2023 Approved CHRISTOPHE COCHRAN
Insulation 9/8/2023 Approved RYAN SALAZAR
Drywall Nailing 9/21/2023 Approved CHRISTOPHE COCHRAN
Green Building Rough 9/21/2023 Approved CHRISTOPHE COCHRAN
Underground Mechanical 11/14/2023 Partial Approval CHRISTOPHE COCHRAN
Underground Mechanical 11/17/2023 Approved CHRISTOPHER ROJAS
HVAC-Final 1/19/2024 Corrections Issued CHRISTOPHE COCHRAN
PLUMBING-Final 1/19/2024 Corrections Issued CHRISTOPHE COCHRAN
ELECTRICAL-Final 6/11/2024 Approved CHRISTOPHE COCHRAN
HVAC-Final 6/11/2024 Not Ready for Inspection CHRISTOPHE COCHRAN
PLUMBING-Final 6/11/2024 Not Ready for Inspection CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 7/9/2024 Conditional Approval SALVADOR MARTINEZ
ELECTRICAL-Final 7/9/2024 Approved SALVADOR MARTINEZ
Final 7/9/2024 Not Ready for Inspection SALVADOR MARTINEZ
Green Building Final 7/9/2024 Not Ready for Inspection SALVADOR MARTINEZ
HVAC-Final 7/9/2024 Not Ready for Inspection SALVADOR MARTINEZ
MERV13>=Final 7/9/2024 Not Ready for Inspection SALVADOR MARTINEZ
MERV13>=Rough 7/9/2024 Not Ready for Inspection SALVADOR MARTINEZ
PLUMBING-Final 7/9/2024 Not Ready for Inspection SALVADOR MARTINEZ
SGSOV-Seismic Gas S/O Valve 7/9/2024 SGSOV Approved SALVADOR MARTINEZ
Service/Power Release 7/9/2024 Not Ready for Inspection SALVADOR MARTINEZ
Smoke Detectors 7/9/2024 Approved SALVADOR MARTINEZ
Verify Sprinkler Sign Off 7/9/2024 Approved SALVADOR MARTINEZ
BUILDING-Rough-Frame 7/15/2024 Approved CHRISTOPHE COCHRAN
Final 7/15/2024 Corrections Issued CHRISTOPHE COCHRAN
Green Building Final 7/15/2024 Approved CHRISTOPHE COCHRAN
MERV13>=Final 7/15/2024 Approved CHRISTOPHE COCHRAN
MERV13>=Rough 7/15/2024 Approved CHRISTOPHE COCHRAN
Service/Power Release 7/15/2024 Not Ready for Inspection CHRISTOPHE COCHRAN
Final 7/22/2024 OK to Issue CofO CHRISTOPHE COCHRAN
Service/Power Release 7/22/2024 Approved CHRISTOPHE COCHRAN