1321 W LAS FLORES DR 90041
Certificate Information: 1321 W LAS FLORES DR 90041
- Application / Permit
- 21010-10000-02569
- Plan Check / Job No.
- B21LA09798
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- E-PLAN: PROPOSED DETACHED ACCESSORY DWELLING UNIT PER ORDINANCE. ***SHALL BE SPRINKLERED PER NFPA 13D***
- Permit Issued
- Issued on 10/12/2021
- Issuing Office
- Current Status
- CofO Issued on 4/19/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/24/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/10/2021 | MICHAEL LOPEZ |
| Corrections Issued | 6/17/2021 | MICHAEL LOPEZ |
| Quality Review Completed | 6/21/2021 | WING SUEN |
| Applicant returned to address corrections | 10/1/2021 | MICHAEL LOPEZ |
| Plan Check Approved | 10/6/2021 | MICHAEL LOPEZ |
| Issued | 10/12/2021 | APPLICANT |
| CofO in Progress | 4/7/2022 | CRAIG VAUGHAN |
| CofO Issued | 4/19/2022 | DEROLD HAUFF |
| Permit Finaled | 4/19/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 6/15/2021 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 6/16/2021 | CECILIO NAVARRO |
| Sewer availability | Cleared | 6/16/2021 | RENZ SORIANO |
| Low Impact Development | Cleared | 8/8/2021 | TA ANH |
| Roof/Waste drainage to street | Cleared | 8/12/2021 | THAN WIN |
| Hydrant and Access approval | Cleared | 8/18/2021 | MATTHEW CRAIG |
| Miscellaneous | Cleared | 8/26/2021 | ALBERT TAM |
| GPI Written Notices | Cleared | 10/5/2021 | KIRK LINKLATER |
| Grading Pre-Inspection | Cleared | 10/5/2021 | KIRK LINKLATER |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | George,, George Amgad; Lic. No.: C91528 | 5 BROWNFIELD LN POMONA, CA 91766 |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/9/2021 | Approved | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 11/23/2021 | Partial Approval | CRAIG VAUGHAN |
| PLUMBING-Rough | 11/23/2021 | Partial Approval | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/30/2021 | Partial Approval | AMY COLIN |
| Wood Frame | 12/13/2021 | Not Ready for Inspection | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 12/15/2021 | Approved | CRAIG VAUGHAN |
| Pre-Inspection | 12/15/2021 | Approved | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/20/2021 | Partial Approval | COREY HUPP |
| PLUMBING-Rough | 12/20/2021 | Approved | COREY HUPP |
| Interior/Exterior Lathing | 1/3/2022 | Partial Approval | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 1/4/2022 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Insulation | 1/7/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 1/10/2022 | Partial Approval | CRAIG VAUGHAN |
| Wood Frame | 1/25/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 1/26/2022 | Approved | CRAIG VAUGHAN |
| Green Building Rough | 1/26/2022 | Approved | CRAIG VAUGHAN |
| HVAC-Rough | 1/26/2022 | Approved | CRAIG VAUGHAN |
| Verify Sprinkler Sign Off | 1/26/2022 | Approved | CRAIG VAUGHAN |
| Insulation | 1/28/2022 | Approved | CRAIG VAUGHAN |
| Shower Pan | 1/28/2022 | Approved | CRAIG VAUGHAN |
| Shower Pan | 1/31/2022 | Approved | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 2/4/2022 | Approved | CHARLES BOGHOSKHAN |
| Drywall Nailing | 2/7/2022 | Approved | CHARLES BOGHOSKHAN |
| Gas Test | 2/7/2022 | Not Ready for Inspection | CHARLES BOGHOSKHAN |
| Underground Mechanical | 2/8/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| Underground Mechanical | 2/25/2022 | Corrections Issued | CRAIG VAUGHAN |
| Underground Mechanical | 3/1/2022 | Approved | CHARLES BOGHOSKHAN |
| Underground Mechanical | 3/10/2022 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Final | 3/16/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| Service/Power Release | 3/16/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| ELECTRICAL-Final | 3/21/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| Service/Power Release | 3/21/2022 | Approved | CRAIG VAUGHAN |
| Gas Test | 3/24/2022 | Approved | CRAIG VAUGHAN |
| PLUMBING-Final | 3/31/2022 | No Access for Inspection | SCOTT FINNILA |
| Final | 4/4/2022 | Corrections Issued | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 4/4/2022 | Approved | CRAIG VAUGHAN |
| Green Building Final | 4/4/2022 | Approved | CRAIG VAUGHAN |
| HVAC-Final | 4/4/2022 | Corrections Issued | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 4/4/2022 | SGSOV Approved | CRAIG VAUGHAN |
| ELECTRICAL-Final | 4/6/2022 | Approved | CRAIG VAUGHAN |
| Final | 4/6/2022 | OK to Issue CofO | CRAIG VAUGHAN |
| HVAC-Final | 4/6/2022 | Approved | CRAIG VAUGHAN |
| PLUMBING-Final | 4/6/2022 | Approved | CRAIG VAUGHAN |
| Smoke Detectors | 4/6/2022 | Approved | CRAIG VAUGHAN |